M8 CONCEPTS Flashcards

(19 cards)

1
Q

to build the project in accordance with the plans and specifications, within budget and on schedule.

A

Construction Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Assumption for Construction Phase

The design plans and specifications contain no errors and meet the owner’s requirements and appropriate codes and standards.

A

Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Assumption for Construction Phase

The [Blank] is acceptable ; that is, it is what the owner can afford and what the contractor can build it for, with a reasonable profit.

A

Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Assumption for Construction Phase

The [Blank] is reasonable; that is, short enough to finish when the owner needs it and long enough for the contractor to do the work.

A

Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • contract documents are prepared by the owner’s designer.
  • Final design, consisting of the construction drawings, is done by an engineering/construction contractor, who performs final design and provides construction services using subcontractors.
A

Bridging Project delivery method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

the term commonly used for projects that must be completed in the earliest possible time.

A

Fast-track Projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

the term commonly used for projects that are designed, built, and put into operation before the project is turned over to the owner.

A

Turn-key Projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Duties and Roles During Construction Phase

  • Owner: Approve as required
  • CM: Coordinate, Expedite & Review
  • Designer: Specify submittals required, Review & approved
  • Contractor: Provide
A

Submittals-shop Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Duties and Roles During Construction Phase

  • Owner: Observe
  • CM: Observe
  • Designer: Observe
  • Contractor: Originate
A

Construction Methods, Procedures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Duties and Roles During Construction Phase

  • Owner: Observe
  • CM: Observe
  • Designer: Observe
  • Contractor: Originate
A

Submittals-shop Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Duties and Roles During Construction Phase

  • Owner: Approve, Respond
  • CM: Review, Approve & Assemble
  • Designer: Review, Approve & Assemble
  • Contractor: Submit
A

Payment Requests

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Duties and Roles During Construction Phase

  • Owner: Approve, Execute
  • CM: Request, Review, Approve & Distribute
  • Designer: Request, Review, Approve & Distribute
  • Contractor: Execute, Respond
A

Change Orders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Duties and Roles During Construction Phase

  • Owner: Receive & File
  • CM: Coordinate, Monitor
  • Designer: Check, Draft
  • Contractor: Provide as built
A

Drawings-as-built

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A document made, detailing remaining or flawed items.

A

Punch List

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  • includes representatives of owner, contractor, and the key design professionals (the architect, as well as civil, electrical, and mechanical engineers, etc.)
  • project manager should schedule and conduct this
A

Final Walk-through Inspection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

requires the contractor to guarantee all material, equipment, and work to be of good quality and free of defects

17
Q

TRUE OR FALSE

The contract requires the contractor to guarantee all material, equipment, and work to be of good quality and free of defects in accordance with the contract documents for a period of one year after completion of construction.

18
Q

should occur after each project to gather valuable lessons for future improvements. Participants, such as the owner, lead designers, and construction representatives, should attend.

A

Post Project Critique