M8 CONCEPTS Flashcards
(19 cards)
to build the project in accordance with the plans and specifications, within budget and on schedule.
Construction Phase
Assumption for Construction Phase
The design plans and specifications contain no errors and meet the owner’s requirements and appropriate codes and standards.
Scope
Assumption for Construction Phase
The [Blank] is acceptable ; that is, it is what the owner can afford and what the contractor can build it for, with a reasonable profit.
Budget
Assumption for Construction Phase
The [Blank] is reasonable; that is, short enough to finish when the owner needs it and long enough for the contractor to do the work.
Schedule
- contract documents are prepared by the owner’s designer.
- Final design, consisting of the construction drawings, is done by an engineering/construction contractor, who performs final design and provides construction services using subcontractors.
Bridging Project delivery method
the term commonly used for projects that must be completed in the earliest possible time.
Fast-track Projects
the term commonly used for projects that are designed, built, and put into operation before the project is turned over to the owner.
Turn-key Projects
Duties and Roles During Construction Phase
- Owner: Approve as required
- CM: Coordinate, Expedite & Review
- Designer: Specify submittals required, Review & approved
- Contractor: Provide
Submittals-shop Drawings
Duties and Roles During Construction Phase
- Owner: Observe
- CM: Observe
- Designer: Observe
- Contractor: Originate
Construction Methods, Procedures
Duties and Roles During Construction Phase
- Owner: Observe
- CM: Observe
- Designer: Observe
- Contractor: Originate
Submittals-shop Drawings
Duties and Roles During Construction Phase
- Owner: Approve, Respond
- CM: Review, Approve & Assemble
- Designer: Review, Approve & Assemble
- Contractor: Submit
Payment Requests
Duties and Roles During Construction Phase
- Owner: Approve, Execute
- CM: Request, Review, Approve & Distribute
- Designer: Request, Review, Approve & Distribute
- Contractor: Execute, Respond
Change Orders
Duties and Roles During Construction Phase
- Owner: Receive & File
- CM: Coordinate, Monitor
- Designer: Check, Draft
- Contractor: Provide as built
Drawings-as-built
A document made, detailing remaining or flawed items.
Punch List
- includes representatives of owner, contractor, and the key design professionals (the architect, as well as civil, electrical, and mechanical engineers, etc.)
- project manager should schedule and conduct this
Final Walk-through Inspection
requires the contractor to guarantee all material, equipment, and work to be of good quality and free of defects
Contract
TRUE OR FALSE
The contract requires the contractor to guarantee all material, equipment, and work to be of good quality and free of defects in accordance with the contract documents for a period of one year after completion of construction.
TRUE
should occur after each project to gather valuable lessons for future improvements. Participants, such as the owner, lead designers, and construction representatives, should attend.
Post Project Critique