Manage Schedule - Prep Questions Flashcards
(124 cards)
The team wants to refine their understanding of what needs to be done before scheduling the project. The team will rely on the decomposition technique to identify:
A. Deliverables and schedule activities
B. Schedule activities and dependencies
C. Schedule activities and requirements
D. Work packages and activities
D. Work packages and activities
The decomposition technique decomposes deliverables into work packages and work packages into activities (answer D). The decomposition technique does not identify deliverables (answer A), dependencies (answer B) and requirements (answer C).
An agile team is developing an e-commerce website. The product owner wants to understand how the sprint work is progressing towards completion. Which of the following may the product owner check?
A. Scrum board
B. Release burndown chart
C. Product backlog
D. Product roadmap
A. Scrum board
A scrum board is used to visualize how the sprint work is progressing towards completion.
You have just joined an existing scrum team that has been working together for several months. The team is using a scrum board to visualize work information. Which of the following statements BEST describes a scrum boards?
A. Shows the tasks’ priorities
B. Shows the amount of work left
C. Shows how tasks progress towards completion
D. Shows how the product Will evolve
C. Shows how tasks progress towards completion
A scrum board is used to visualize how the sprint work is progressing towards completion.
Your project will implement the company’s new ticketing system. You are calculating late start and late finish dates by working backwards through the network diagram. Which of the following practice are you performing?
A. Schedule compression
B. Backward pass
C. Reverse scheduling
D. Reverse leveling
B. Backward pass
The backward pass calculates the late start and late finish dates of project activities, by moving backwards throughout the network diagram.
A junior project manager is using the critical path method to develop the project schedule? You should remind the project manager that the critical path method does not take __________ into account.
A. Schedule activities
B. Resource availability
C. Schedule risk provisions
D. Dependencies
B. Resource availability
The critical path method does not take resource availability into account (answer B). The critical path method takes activities (answer A), contingency reserves (answer C) and dependencies (answer D) into account.
A critical stakeholder wants to know if the team will be able to complete the accepted work within the current iteration. You should refer the stakeholder to the ___________.
A. Product backlog
B. Performance report
C. Product roadmap
D. Iteration burndown chart
D. Iteration burndown chart
Iteration burndown charts are commonly used in agile projects to represent planned and actual sprint performance (answer D).
The product owner is updating the release plan for the current release. Which of the following statements is correct?
A. The product backlog items that Will be completed within the remaining iterations are firmly defined because the release is timeboxed
B. The product backlog items that Will be completed within the remaining iterations are firmly defined because the sprints are timeboxed
C. The number of iterations required to complete the minimum viable product are firmly defined because the release is timeboxed
D. The number of iterations required to complete the selected product backlog items may vary because the release is scopeboxed
D. The number of iterations required to complete the selected product backlog items may vary because the release is scopeboxed
A scopeboxed release plan determines the number of iterations required to complete a specific set of product backlog items (answer D). The product backlog items that will be completed within the remaining iterations may vary when the release is timeboxed (answers A and B). The of iterations required to complete the minimum viable product may vary (answer C).
You recently joined a government agency and were assigned to an important project. You collected the following estimates for the duration of an activity: Optimistic = 4 days, Most Likely = 6 days,
Pessimistic = 12 days. What is the estimated duration using the Beta estimation technique?
A. 6.6
B. 7 33
C. 8
D. 40
A. 6.6
The Beta expected duration is calculated as (o+p+4pm)/6., using an optimistic (o), pessimistic (p) and most likely (m). Therefore the three-point estimate is 6.7.
An agile team has a total of six members, three members who work full time and three members who work part time. At the beginning of the second sprint, team members are defining the tasks required
to meet the sprint goal. Which of the following statements regarding tasks are correct? (Choose three.)
A. They may be displayed in a Kanban board
B. They are defined during product backlog refinement
C. They are recorded in the product backlog
D. Should have sufficient detail to ensure that team members understand how the work Will be done
E. They are the actions required to complete product backlog items
F. They are a concise and intuitive description of a feature
A. They may be displayed in a Kanban board
D. Should have sufficient detail to ensure that team members understand how the work Will be done
E. They are the actions required to complete product backlog items
Tasks represent small actions required to create product backlog items (answers D and E). Tasks may be recorded in the kanban board (answer A). Tasks are defined as part of sprint planning (answer B) and are not recorded in the product backlog (answer C). A user story is a concise and intuitive description of a feature (answer F).
A financial institution needs to release a new service until the end of the current year. During the project early stages, the project manager is considering several crashing alternatives to reduce the
project overall duration. All of the following are valid alternatives to crash the schedule, EXCEPT:
A. Allocating more resources to critical activities
B. Shifting resources from non-critical activities to critical activities
C. Adjusting the activity duration estimates
D. Using more skilled resources
C. Adjusting the activity duration estimates
The project manager should not adjust the activity duration estimates (answer C) without adjusting other project constraints. The remaining answers represent valid crashing approaches.
You have just taken over a project that is running behind schedule. The sponsor has asked you to compress the schedule without using additional resources. What is the BEST course of action?
A. Level the existing resources
B. Crash the schedule
C. Fast track the schedule
D. Run a schedule simulation
C. Fast track the schedule
Fast tracking accelerates the schedule by overlapping schedule activities that would usually be done sequentially (answer C). Resource leveling (answer A) and schedule simulations (answer D) do not shorten the schedule duration. Crashing (answer B) could compress the schedule but would require bringing in additional resources.
An activity has an optimistic estimate of 2 days, a most likely estimate of 5 days and a pessimistic estimate of 14 days. Using the Beta technique, what would be the activity standard deviation?
A. 2
B. 6
C. 8
D. 12
A. 2
Beta uses the formula Sigma = (P-O)/6, where O is the optimistic estimate and P is the pessimistic estimate. Therefore, sigma = (14-2)/6=2.
You are working with senior management establishing a common understanding of how the schedule will be managed. Which of the following may you define?
A. Adopted schedule management standards and schedule management responsibilities
B. Schedule data and adopted schedule performance metrics
C. Adopted schedule management standards and activity attributes
D. Schedule reporting formats and schedule forecasts
A. Adopted schedule management standards and schedule management responsibilities
The adopted schedule management standards and schedule management responsibilities are part of the schedule management plan (answer A). Schedule data (answer B) is an output of schedule development. Activity attributes (answer C) are defined in the define activities process. Schedule forecasts (answer D) are an output of the control schedule process.
Which of the following statements regarding the critical path method (CPM) are correct? (Choose three.)
A. Increasing the number of critical paths reduces the schedule risk
B. The critical path activities can have zero or positive free float
C. Each project only has one critical path
D. The critical path activities can have zero or negative float
E. The critical path method is used to level project resources
F. A project may have a negative float
B. The critical path activities can have zero or positive free float
D. The critical path activities can have zero or negative float
F. A project may have a negative float
Your construction company estimates the time required to paint a house assuming that it takes 30 minutes per square meter of surface painted. Which estimating technique is your company using?
A. Formula estimating
B. Heuristic estimating
C. Parametric estimating
D. Analogous estimating
C. Parametric estimating
Parametric estimating uses a statistical relationship between historical data and project parameters.
In a pharmaceutical project, the quality control team can perform inspection work once the laboratory work has begun. This is an example of what type of sequence?
A. Start to Finish
B. Finish to Start
C. Finish to Finish
D. Start to Start
D. Start to Start
An agile team is developing a geographic information system. Senior management wants to know which requirements qill be delivered at the end of the remaining sprints. Who is primary responsible for providing that information?
A. Team
B. Scrum master
C. Product owner
D. Project manager
C. Product owner
The product owner is responsible for prioritizing the product backlog.
You are preparing an early estimate of the duration of your new project by comparing it with a relatively similar project recorded in the organizational knowledge base. You adopted this estimating technique because:
A. It produces accurate estimates
B. Estimates are based on an objective assessment
C. Estimates are based on detailed information
D. Estimates can be quickly obtained
D. Estimates can be quickly obtained
You are using analogous estimating to estimate the project duration. Analogous estimates can be quickly obtained (answer D). Analogous estimates are neither accurate (answer A) nor objective (answer B). Analogous estimates are not typically based on detailed information (answer C).
Activity A has a duration of 6 and can start any time. Activity B has a duration of 17 and can start any time. Activity C has a duration of 4 and can start after activity A. Activity D has a duration of 7 and can
start after activity C. Activity E has a duration of 5 and can start after activities B and D. Activity F has a duration of 5 and can start after activities E. What is the project critical path?
A. B-E-F
B. A-C-D-E-F
C. A-C-E-F
D. B-E-F and A-C-D-E-F
D. B-E-F and A-C-D-E-F
The alternative paths are:
- B-E-F with 27 days
- A-C-D-E-F with 27 days
They are both critical
Mary is estimating the detailed activities duration based on the organizational historic information. She is comparing her actual project with similar projects in the organization’s history. Which
estimating technique is Mary using?
A. Analogous
B. Lessons learned
C. Expert judgement
D. Parametric
A. Analogous
An analogous estimate estimates durations based on historical information accumulated in the organization.
An activity has an optimistic duration of 10 days, a most likely duration of 13 days and a pessimistic duration of 22 days. What is the Beta standard deviation of the activity?
A. 2
B. 4
C. 12
D. 14
A. 2
The Beta standard deviation is calculated based on the optimistic (o) and pessimistic (p) estimates. The Beta standard deviation is calculates as (p-o)/6. Therefore, the standard deviation is 2.
An agile team is developing a customer service application. The scrum master recommended the practice of estimating product backlog items relying on relative estimates. Which of the following are valid reasons for estimating based on relative estimating? (Choose two.)
A. Relative estimates express actual time
B. Relative estimates are aligned to the product vision
C. Relative estimates are timeboxed
D. Relative estimates may be used to develop accurate schedules
E. Relative estimates can accommodate uncertainty
F. Relative estimates do not require detailed information
E. Relative estimates can accommodate uncertainty
F. Relative estimates do not require detailed information
Relative estimates can accommodate uncertainty (answer E) and do not require detailed information (answer F).
You were asked to help an agile team to adopt agile practices. You want to introduce the practice of estimating product items using story points. Which of the following statements regarding story points are correct? (Choose two.)
A. They promote a shared sense of accountability
B. They express the size of a task in relation to others
C. They express the size of a specific function required to complete an item
D. They enable discussions across all the disciplines required to complete an item
E. They are tied to estimates of time periods
F. They enable the team to avoid detailed discussions about the item
B. They express the size of a task in relation to others
D. They enable discussions across all the disciplines required to complete an item
While managing a project, a major defect was identified. Which of the following options should the project manager do NEXT?
A. Ask the team to work overtime
B. Request a formal change to the project schedule to account for the additional time
C. Use the project schedule contingency to repair the identified defects
D. Reduce the time allocated to other project activities to allow the team to correct the default
C. Use the project schedule contingency to repair the identified defects
If there is still available contingency it should be used to compensate for accumulated variances.