1
Q
Foundations:
Shallow Foundation Types
A

2
Q
Foundations:
Construction Sequence
A
Initial Construction Prep:
- The perimeter blockwork walls are laid.
- 50mm sand blinding layer is spread between the perimeter walls.
- Damp Proof Membrane is laid, ready to receive the rigid insulation layer.

3
Q
Foundations:
Cold Bridging and Thermal Mass
A

4
Q
Foundations:
Suspended Floor Option
A

5
Q
Junctions:
First Floor- Platform Frame
A
Notes:
- First Floor has a double joist for additional strength.
- Insulation is packed around the first floor junction to avoid a cold bridge.
- Breather Membrane from first floor stud frame overlaps ground floor membrane.The first floor cavity is ventilated by a weep vent, that allows water to escape.
- VCL (red line) wraps around the outside of floor plate to maintain the line of vapour control.

6
Q
Junctions:
Eaves- Platform Frame
A
Notes:
- The insulation is continuous, providing a robust ‘warm roof’ detail.
- Breather Membrane below the roof tiles overlaps the gutter, allowing water to drain.
- The roof cavity is ventilated.
- The VCL (red line) maintains the line of vapour control.