Module 1 - E Flashcards

1
Q

available time

A

The number of hours a work center can be used, based on management decisions regarding shift structure, extra shifts, regular overtime, observance of weekends and public holidays, shutdowns, and the like

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

back scheduling

A

A technique for calculating operation start dates and due dates. The schedule is computed starting with the due date for the order and working backward to determine the required start date and/or due dates for each operation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

capacity

A

1) The capability of a system to perform its expected function. 2) The capability of a worker, machine, work center, plant, or organization to produce output per time period. The amount required represents the system capability needed to make a given product mix (assuming technology, product specification, etc.). As a planning function, both the amount available and the amount required can be measured in the short term (requirements plan), intermediate term (rough-cut plan), and long term (resource requirements plan). Control is the execution through the I/O control report of the short-term plan. This can be classified as budgeted, dedicated, demonstrated, productive, protective, rated, safety, standing, or theoretical. 3) Required mental ability to enter into a contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

capacity available

A

The capability of a system or resource to produce a quantity of output in a particular time period

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

capacity management

A

The function of establishing, measuring, monitoring, and adjusting limits or levels of capacity in order to execute all manufacturing schedules (i.e., the production plan, master production schedule, material requirements plan, and dispatch list). This is executed at four levels: resource requirements planning, rough-cut planning, requirements planning, and input/output control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

capacity planning

A

The process of determining the amount of capacity required to produce in the future. This process may be performed at an aggregate or product-line level, at the master-scheduling level, and at the material requirements planning level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

capacity required

A

The capacity of a system or resource needed to produce a desired output in a particular time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

capacity requirements planning (CRP)

A

The function of establishing, measuring, and adjusting limits or levels of capacity. In this context, the term refers to the process of determining in detail the amount of labor and machine resources required to accomplish the tasks of production. Open shop orders and planned orders in the MRP system are input to this, which through the use of parts routings and time standards translates these orders into hours of work by work center by time period. Even though rough-cut capacity planning may indicate that sufficient capacity exists to execute the MPS, this may show that capacity is insufficient during specific time periods.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

demonstrated capacity

A

Proven capacity calculated from actual performance data, usually expressed as the average number of items produced multiplied by the standard hours per item.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

efficiency

A

A measurement (usually expressed as a percentage) of the actual output relative to the standard output expected. Efficiency measures how well something is performing relative to existing standards; in contrast, productivity measures output relative to a specific input (e.g., tons/labor hour). Efficiency is the ratio of (1) actual units produced to the standard rate of production expected in a time period, or (2) standard hours produced to actual hours worked (taking longer means less efficiency), or (3) actual dollar volume of output to a standard dollar volume in a time period. For example: (1) There is a standard of 100 pieces per hour and 780 units are produced in one eight-hour shift; the efficiency is 780 ÷ 800 converted to a percentage, or 97.5 percent. (2) The work is measured in hours and took 8.21 hours to produce 8 standard hours; the efficiency is 8 ÷ 8.21 converted to a percentage, or 97.5 percent. (3) The work is measured in dollars and produces $780 with a standard of $800; the efficiency is $780 ÷ $800 converted to a percentage, or 97.5 percent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

external setup time

A

The time associated with elements of a setup procedure performed while the process or machine is running.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

internal setup time

A

The time associated with elements of a setup procedure performed while the process or machine is not running

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

lead time

A

1) A span of time required to perform a process (or series of operations). 2) In a logistics context, the time between recognition of the need for an order and the receipt of goods. Individual components of lead time can include order preparation time, queue time, processing time, move or transportation time, and receiving and inspection time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

load

A

The amount of planned work scheduled for and actual work released to a facility, work center, or operation for a specific span of time. Usually expressed in terms of standard hours of work or, when items consume similar resources at the same rate, units of production.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

load profile

A

A display of future capacity requirements based on released and/or planned orders over a given span of time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

manufacturing calendar

A

A calendar used in inventory and production planning functions that consecutively numbers only the working days so that the component and work order scheduling may be done based on the actual number of workdays available.

17
Q

move time

A

The time that a job spends in transit from one operation to another in the plant

18
Q

process batch

A

The quantity or volume of output that is to be completed at a workstation before switching to a different type of work or changing an equipment setup.

19
Q

productivity

A

1) An overall measure of the ability to produce a good or a service. It is the actual output of production compared to the actual input of resources. Productivity is a relative measure across time or against common entities (labor, capital, etc.). In the production literature, attempts have been made to define total productivity where the effects of labor and capital are combined and divided into the output. One example is a ratio that is calculated by adding the dollar value of labor, capital equipment, energy, and material, and so forth and dividing it into the dollar value of output in a given time period. This is one measure of total factor productivity. 2) In economics, the ratio of output in terms of dollars of sales to an input such as direct labor in terms of the total wages. Known as single factor productivity or partial factor productivity.

20
Q

queue

A

A waiting line. In manufacturing, the jobs at a given work center waiting to be processed. As queues increase, so do average queue time and work-in-process inventory.

21
Q

queue time

A

The amount of time a job waits at a work center before setup or work is performed on the job. Queue time is one element of total manufacturing lead time. Increases in queue time result in direct increases to manufacturing lead time and work-in-process inventories.

22
Q

rated capacity

A

The expected output capability of a resource or system. Capacity is traditionally calculated from such data as planned hours, efficiency, and utilization. The rated capacity is equal to hours available × efficiency × utilization.

23
Q

routing

A

1) Information detailing the method of manufacture of a particular item. It includes the operations to be performed, their sequence, the various work centers involved, and the standards for setup and run. In some companies, the routing also includes information on tooling, operator skill levels, inspection operations and testing requirements, and so on. 2) In information systems, the process of defining the path a message will take from one computer to another computer.

24
Q

run time

A

The time required to process a piece or lot at a specific operation. Run time does not include setup time.

25
setup
1) The work required to change a specific machine, resource, work center, or line from making the last good piece of item A to making the first good piece of item B. 2) The refitting of equipment to neutralize the effects of the last lot produced (e.g., teardown of the just-completed production, preparation of the equipment for production of the next scheduled item).
26
setup time
The time required for a specific machine, resource, work center, process, or line to convert from the production of the last good piece of item A to the first good piece of item B
27
standard time
The length of time that should be required to (1) set up a given machine or operation and (2) run one batch or one or more parts, assemblies, or end products through that operation. Used in determining machine requirements and labor requirements. Assumes an average worker who follows prescribed methods, and allows time for personal rest to overcome fatigue and unavoidable delays. Also frequently used as a basis for incentive pay systems and as a basis of allocating overhead in cost accounting systems.
28
start date
In project management, the time an activity begins; may be defined as an actual start date or a planned start date.
29
transit time
A standard allowance that is assumed on any given order for the movement of items from one operation to the next.
30
utilization
1) A measure (usually expressed as a percentage) of how intensively a resource is being used to produce a good or service. Compares actual time used to available time. Traditionally, calculated as the ratio of direct time charged (run time plus setup time) to the clock time available. Utilization is a percentage between 0 percent and 100 percent that is equal to 100 percent minus the percentage of time lost due to the unavailability of machines, tools, workers, and so forth. 2) In the theory of constraints, activation of a resource that productively contributes to reaching the goal. Over-activation of a resource does not productively utilize a resource.
31
wait time
The time a job remains at a work center after an operation is completed until it is moved to the next operation. It is often expressed as a part of move time.
32
work center
A specific production area, consisting of one or more people and/or machines with similar capabilities, that can be considered as one unit for purposes of capacity requirements planning and detailed scheduling
33
yield
The amount of good or acceptable material available after the completion of a process. Usually computed as the final amount divided by the initial amount converted to a decimal or percentage. In manufacturing planning and control systems, yield is usually related to specific routing steps or to the parent item to determine how many units should be scheduled to produce a specific number of finished goods. For example, if 50 units of a product are required by a customer and a yield of 70 percent is expected, then 72 units (computed as 50 units divided by .7) should be started in the manufacturing process.