Module 1 - H Flashcards

1
Q

bottleneck

A

A facility, function, department, or resource whose capacity is less than the demand placed upon it. For example, a machine or work center exists where jobs are processed at a slower rate than they are demanded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

buffer

A

1) A quantity of materials awaiting further processing. It can refer to raw materials, semifinished stores or hold points, or a work backlog that is purposely maintained behind a work center. 2) In the theory of constraints, these can be time or material and support throughput and/or due date performance. These can be maintained at the constraint, convergent points (with a constraint part), divergent points, and shipping points.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

buffer management

A

In the theory of constraints, a process in which all expediting in a shop is driven by what is scheduled to be in the buffers (constraint, shipping, and assembly buffers). By expediting this material into the buffers, the system helps avoid idleness at the constraint and missed customer due dates. In addition, the reasons items are missing from the buffer are identified, and the frequency of occurrence is used to prioritize improvement activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

capacity control

A

The process of measuring production output and comparing it with the capacity plan, determining if the variance exceeds pre-established limits, and taking corrective action to get back on plan if the limits are exceeded.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

capacity-constrained resource (CCR)

A

A resource that is not a constraint but will become a constraint unless scheduled carefully. Any resource that, if its capacity is not carefully managed, is likely to compromise the throughput of the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

constraint

A

1) Any element or factor that prevents a system from achieving a higher level of performance with respect to its goal. Constraints can be physical, such as a machine center or lack of material, but they can also be managerial, such as a policy or procedure. 2) One of a set of equations that cannot be violated in an optimization procedure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

cycle time

A

1) In industrial engineering, the time between the completion of two discrete units of production. 2) In materials management, the length of time from when material enters a production facility until it exits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

dispatching

A

The selecting and sequencing of available jobs to be run at individual workstations and the assignment of those jobs to workers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

drum schedule

A

The detailed production schedule for a resource that sets the pace for the entire system. The drum schedule must reconcile the customer requirements with the system’s constraint(s).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

drum-buffer-rope (DBR

A

The theory of constraints method for scheduling and managing operations that have an internal constraint or capacity-constrained resource

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

final assembly schedule (FAS)

A

A schedule of end items to finish the product for specific customers’ orders in a make-to-order or assemble-to-order environment. It is also referred to as the finishing schedule because it may involve operations other than the final assembly; also, it may not involve assembly (e.g., final mixing, cutting, packaging). The FAS is prepared after receipt of a customer order as constrained by the availability of material and capacity, and it schedules the operations required to complete the product from the level where it is stocked (or master scheduled) to the end-item level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

finite forward scheduling

A

An equipment scheduling technique that builds a schedule by proceeding sequentially from the initial period to the final period while observing capacity limits. A Gantt chart may be used with this technique.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

finite loading

A

Assigning no more work to a work center than the work center can be expected to execute in a given time period. The specific term usually refers to a computer technique that involves calculating shop priority revisions in order to level load operation by operation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

five focusing steps

A

In the theory of constraints, a process to continuously improve organizational profit by evaluating the production system and market mix to determine how to make the most profit using the system constraint. The steps consist of (1) identifying the constraint to the system, (2) deciding how to exploit the constraint to the system, (3) subordinating all nonconstraints to the constraint, (4) elevating the constraint to the system, and (5) returning to step 1 if the constraint is broken in any previous step, while not allowing inertia to set in.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

flow control

A

A specific production control system that is based primarily on setting production rates and feeding work into production to meet these planned rates, then monitoring and controlling production.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

forward scheduling

A

A scheduling technique where the scheduler proceeds from a known start date and computes the completion date for an order, usually proceeding from the first operation to the last. Dates generated by this technique are generally the earliest start dates for operations.

17
Q

idle capacity

A

The available capacity that exists on nonconstraint resources beyond the capacity required to support the constraint. Idle capacity has two components: protective capacity and excess capacity.

18
Q

infinite loading

A

Calculation of the capacity required at work centers in the time periods required regardless of the capacity available to perform this work

19
Q

input/output control (I/O)

A

A technique for capacity control where planned and actual inputs and planned and actual outputs of a work center are monitored. Planned inputs and outputs for each work center are developed by capacity requirements planning and approved by manufacturing management. Actual input is compared to planned input to identify when work center output might vary from the plan because work is not available at the work center. Actual output is also compared to planned output to identify problems within the work center

20
Q

job shop scheduling

A

The production planning and control techniques used to sequence and prioritize production quantities across operations in a job shop.

21
Q

manufacturing order

A

A document, group of documents, or schedule conveying authority for the manufacture of specified parts or products in specified quantities.

22
Q

operations sequencing

A

A technique for short-term planning of actual jobs to be run in each work center based upon capacity (i.e., existing workforce and machine availability) and priorities. The result is a set of projected completion times for the operations and simulated queue levels for facilities

23
Q

overlapped schedule

A

A manufacturing schedule that “overlaps” successive operations. Overlapping occurs when the completed portion of an order at one work center is processed at one or more succeeding work centers before the pieces left behind are finished at the preceding work centers.

24
Q

priority control

A

The process of communicating start and completion dates to manufacturing departments in order to execute a plan. The dispatch list is the tool normally used to provide these dates and priorities based on the current plan and status of all open orders

25
production activity control (PAC
The function of routing and dispatching the work to be accomplished through the production facility and of performing supplier control. PAC encompasses the principles, approaches, and techniques needed to schedule, control, measure, and evaluate the effectiveness of production operations
26
productive capacity
In the theory of constraints, the maximum of the output capabilities of a resource (or series of resources) or the market demand for that output for a given time period.
27
protective capacity
The resource capacity needed to protect system throughput—ensuring that some capacity above the capacity required to exploit the constraint is available to catch up when disruptions inevitably occur. Nonconstraint resources need protective capacity to rebuild the bank in front of the constraint or capacity-constrained resource (CCR) and/or on the shipping dock before throughput is lost and to empty the space buffer when it fills.
28
protective inventory
In the theory of constraints, the amount of inventory required relative to the protective capacity in the system to achieve a specific throughput rate at the constraint.
29
split lot
A manufacturing order quantity that has been divided into two or more smaller quantities, usually after the order has been released. The quantities of a split lot may be worked on in parallel, or a portion of the original quantity may be sent ahead to a subsequent operation to be worked on while work on the remainder of the quantity is being completed at the current operation. The purpose of splitting a lot is to reduce the lead time of the order
30
store
A storage point located upstream of a work station, intended to make it easier to see customer requirements.
31
theory of constraints (TOC)
A holistic management philosophy developed by Dr. Eliyahu M. Goldratt, based on the principle that complex systems exhibit inherent simplicity. Even a very complex system comprising thousands of people and pieces of equipment can have, at any given time, only a very, very small number of variables—perhaps only one, known as a constraint—that actually limit the ability to generate more of the system’s goal.
32
throughput
The rate at which the system generates “goal units.” Because throughput is a rate, it is always expressed for a given time period—such as per month, week, day, or even minute. If the goal units are money, throughput is an amount of money per time period. In that case, throughput is calculated as revenues received minus totally variable costs divided by units of the chosen time period.
33
time buffer
Protection against uncertainty that takes the form of time.
34
work order
1) An order to the machine shop for tool manufacture or equipment maintenance; not to be confused with a manufacturing order. 2) An authorization to start work on an activity (e.g., maintenance) or product.