OFC Instn, FTTH, FSO, N/W analysers, RFMS, Satellite, VSAT Flashcards
(129 cards)
OFC is laid at a minimum distance of ___ meters from the center line of the road where the road land is wider
1) 10
2) 15
3) 20
4) 25
15 meters
OFC is planned for about ______
1) 10 to 15 years
2) 15 to 20 years
3) 20 to 25 years
4) 25 to 30 years
25 to 30 years
HDD stands for
Horizontal directional drilling.
HDD is normally deployed in soft soil.
The soil is categorized as rocky if the
1) cable trench cannot be dug without blasting and/or chiseling
2) having soft rocks along the path
3) both
1) cable trench cannot be dug without blasting and/or chiseling
All other types of soils shall be categorized as Non Rocky including Murrum & soil mixed with stone or soft rock.
Rocky soil
1) basalt
2) kachcha soil
3) Pucca soils
4) All of the above
basalt
HDPE stands for
High-density polyethylene
DWC HDPE pipe used for laying OFC. DWC stands for
Double walled corrugated
wherever OFC is passing over the ground surface
(exposed outside) and more prone to damage, ____ pipe may be used preferably
1) GI
2) RCC
3) GWC
GI
However, depending upon the site conditions and cost consideration one of the protection
viz DWC / GI / RCC pipe may be used
RCC: Reinforced cement concrete
DWC: Double walled corrugated
Trench depth is _____ cm in non-Rocky soil
1) 100 cm
2) 150 cm
3) 165 cm
4) 180 cm
165 cm measured from the top of pipe
PP rope is first drawn through HDPE. PP stands for
Polypropylene Para Pro
RCC stands for
Reinforced cement concrete
First choice for extra protection of OFC among GI and DWC
DWC: Double walled corrugated
The Joint chamber shall be of ____
1) pre-cast GI
2) pre-cast RCC
3) pre-cast DWC
pre-cast RCC
(Reinforced cement concrete)
The Route and Joint indicator shall be of ____
1) pre-cast GI
2) pre-cast RCC
3) stone
2 or 3
A minimum free clearance of _____ cms. should be maintained above or below any existing underground installation
1) 10
2) 15
3) 20
4) 25
15 cms
In all cases, the slope of the trench shall not be less than _______ degrees with the horizontal surface.
1) 10
2) 15
3) 20
4) 25
15 degrees
The width of the trench shall normally be ___ cms at the top & ___ cms at the bottom
1) 50, 30
2) 45, 30
3) 60, 40
45, 30
45 cms at the top & 30 cms at the bottom
For road and railway crossings
1) fluid-assisted
2) dry directional drilling machines
3) micro-tunnelling systems
4) any of the above
any of the above
mini trench dimension
1) 10 x 30 cm
2) 5 x 30 cm
10 x 30 cm
(5 x 30 cm for enhanced mini trench)
is normally carried out by cutting a shallow groove in the asphalt (better if not less than 7 cm), but without penetrating past the asphalt layer.
1) mini trenching
2) enhanced mini trenching
3) micro trenching
micro trenching
Installation of OFC over power lines
1) ADSS
2) OPGW
3) both
both
ADSS up to 33KV
OPGW beyond 33KV to 400KV
ADSS: All-Dielectric Self-supporting
OPGW: Optical Ground Wire
Installation of OFC over power lines over 33KV
1) ADSS
2) OPGW
3) both
OPGW: Optical Ground Wire
Fill ratio of the duct should not exceed ___%
1) 25%
2) 50%
3) 75%
50%
On long cable pulls, _______ may be used to facilitate intermediate-assist placing
operations.
1) handholes
2) manholes
handholes