Pricing - COMPLETE Flashcards

1
Q

Stipulated Sum

A

aka - lump sum, fixed sum bid
- one single number value that represents all costs required to build project
- competitively bid projects typically rely on this approach (DBB, DB, Publicly funded)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Items that go into project cost:

A

cost of construction/work
construction contingencies
contractor overhead costs, profit, bonds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

GMP

A
  • cost of construction the contractor assures the client the project will be built for
  • developed by GC prior to completion of construction docs
  • usually includes line item prices and allowances, contingencies
  • typical for projects with acccelerated schedules
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cost Plus

A

AKA time and material (t&m)
based on actual cost of work
subcontractors + contractor submit detailed accounting of cost of materials, equipment, etc.
labor to construct project is reimbursed at predetermined hourly rates for actual hours expended
contractors receive overhead and profit payments at fixed rate
typical for: small projects, existing conditions are unknown, scope is hard to define, change orders within a stipulated sum or GMP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Unit Prices

A

typical for: when full project scope is unknown
costs for each specific unit of work (materials, labor, fees, profit)
contractor is compensated for number of units of each system constructed based on unit prices

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Target Price

A

typical for DB
owner sets construction cost as part of procurement documents, db team provides most scope for the cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly