1
Q

substantial completion

A

owner can occupy space
warranties begin
GC states when it is ready

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

final completion & final payment

A

All punch items are complete (GC holds the punch list)
GC gets final payment (last % + all retainers)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Phases & % of time

A

SD 15%
DD 20%
CD 45%
BID/PROCUREMENT 5%
CA 15%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Level of dwg in predesign?

A

Sketch image

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Level of dwg in SD?

A

Plans
overall elevations
key section
estimated dimensions (100’)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Level of dwg in DD?

A

Plans
overall elevations
key section

+
wall sections
MEP
Roof
RCP
interior elevations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Level of dwg in CD?

A

Plans
overall elevations
key section
wall sections
MEP
Roof
RCP
interior elevations

+
exterior details, interior details

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

RFI type 1

A

Graphic/Conforming rFI
2 HR points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

RFI type 2

A

Coordination/Missing Info
5 HR points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

RFI type 3

A

code/contract information
10 HR points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly