Test Review Questions - COMPLETE Flashcards

1
Q

What is included in the ‘Cost of the work’?

A

construction costs, contractor profit & overhead

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What do drawings communicate in the contract documents?

A

quantity and setting of building components and systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What do specifications communicate in the contract documents?

A

specifications communicate the type an d quality of building components and systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What do zoning regulations impact?

A

historic preservation requirements, building setbacks, signage restrictions

NOT egress, accessibility of building construction type

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

At what time in the project timelines is it best for costs to be controlled?

A

at beginning of project when determining scope, quality, project delivery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Are designing & documenting alternates a part of arch’s basis services?

A

YES - you can not charge an add service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Based on AIA B101, what expected dates should the owner provide the arch?

A

start of construction
date of substantial completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Which entity handles ADA violations?

A

Department of Justice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When reviewing submittals the arch is responsible for which of the following?

A

Materials
finishes
VOC’s

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When reviewing submittals the arch is NOT responsible for which of the following?

A

quantities
dimensions
installation method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What info is included on change order document?

A

contract sum prior to change order
amount that the contract sum increases or decreases
net change by previously authorized change orders
new date of substantial completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is AIA A133?

A

Standard form of agreement between owner - CM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

AIA A141?

A

owner - design builder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

AIA A105

A

short form of agreement between owner-contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How many days does a contractor have to provide notification to the architect of a unknown or concealed condition?

A

14 days
according to AIA A201

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are documents that would be included in both project manual + contract documents package?

A

tech specs
owner-contractor agreement
support conditions
gen conditions

ANY BID RELATED ITEMS (BID FORMS, INVITE TO BID) ARE WRONG BECAUSE THEY ARE NOT IN THE CONTRACT DOCS

17
Q

What are primary issues that need to be considered when determining the project delivery method?

A

contractors role
arch’s role
number and type of design and con contracts
driving factors

18
Q

According to AIA C401, what is true regarding arch and consultant accountability?

A

consultant shall maintain prof liability coverage
consultant is an independent contractor
arch shall not be held responsible for acts or omissions of the consultant

19
Q

What type of meeting would be best held as a face to face meeting?

A

Kickoff meeting

NOT meetings to resolve design issues, design review meetings

20
Q

S Corporation is owned by who?

A

stockholders

21
Q

Who is responsible for obtaining a certificate of occupancy?

A

Owner

22
Q

What must take place prior to release of final payment to contractor?

A

contractor submission of required affidavits
architect’s final inspection
final change order review

NOT contractor submission of record drawings

23
Q

What is formula for initial rate of return (IRR)?

A

IIR = Annual savings/investment

24
Q

What would be required owner-provided initial information related to site documentation?

A

site grading
traffic study
soil boring logs

25
Q

What is preliminary project description (PPD)?

A

describes expected project quality in wall that all stakeholders can understand
in lieu of full set of dwgs or specs
used in early phase of project

26
Q

How does the uniformat framework establish costs?

A

Systems
breaks down projects by system rather than material or method
useful for classifying and estimating construction costs during SD

27
Q

Who pays for taxes during the construction of the building?

A

GC pays for ALL taxes

28
Q

What is a reasonable contingency?

A

10%

ie - 8 month schedule, contingency for time is 10% of, which equals 2-4 weeks

29
Q

what items are attached to or noted on the certificate of sub completion?

A
  • owner & contractor responsibilities for insurance
  • date of substantial completion
  • punch list items to be corrected
  • completion date for punch list items

NOT Cert of occupancy

30
Q

If an issue comes up in dwgs that is caused by miscoordination, what is first step arch should take in terms of project work planning?

A

take corrective actions to modify the project work plan

31
Q

If a new program is added to the project during a design review, what should the architect’s first response be?

A

notify the owner of fees for additional services due to scope creep

32
Q

Who should the architect recommend be contracted prior to SD phase in an IPD?

A

general contractor
geotechnical engineer
construction manager
(misc - historical preservationist)
NOT commissioning agent or lighting designer

33
Q

What pricing should an arch suggest from GC to know price early & at DD stage

A

GMP (based on dd dwgs, estimate, but known price)

34
Q

If an owner pauses bidding for more than 90 days after arch submits CD’s, what should arch do first when project begins again?

A

adjust cost of work to reflect changes in the construction market