Procurement & Tendering Flashcards

(39 cards)

1
Q

What is Procurement

A

The overall process of acquiring construction works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What should be considered when selecting a procurement route

A

Specifics to the project objectives such as
- Time
- Cost
-Quality
- Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the main procurement methods

A

Traditional
Design & Build
Management Contracting
Construction management

  • Single Stage
  • Two Stage
  • Negotiated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is traditional procurement

A

Traditional Procurement is where the design and specification is developed by the client and the design team pre-contract and then issued out to a list of contractors for a competitive process. A contractor is then employed to under take the construction works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How does traditional procurement work

A
  • The client takes on the risk for the design and the design teams performance
  • The contractor takes on the financial risk for the construction works
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the advantages of traditional procurement

A
  • It provides cost certainty to the client as the contractor provides a price based on the developed design
  • The client retains control over the design and specification
  • design changes are relatively easy to arrange and value
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the disadvantages of traditional procurement

A
  • Longer pre-contract programme due to design development
  • No input from the contractor on buildability
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Design and Build

A
  • Design and Build is where the contractor has involvement with the design, planning, control and as well as the construction of the project in line with the employers requirements.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How does Design & Build work

A

The client provides the contractor with their Employers requirements and the Contractor responds with their contractor proposals, which include a price for the works.

It transfers the risk of the design development over to the contractor as well as the construction works.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the advantages of design and Build

A
  • There is a single point of responsibility for the design and construction.
  • There is earlier commencement onsite
  • Contractors experience harnessed during the design phase
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the disadvantages of design and build?

A
  • Quality
  • The client has to commit to a concept design early
  • Clients may find it hard to prepare a sufficient comprehensive brief
  • Variations from the original brief can often be expensive
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How much design input will the contractor have in a design and build?

A
  • This depends on the amount of design work the employer has already completed at the time of tender
  • This can range from full design to production information and co-ordination only
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If the client wishes to start onsite asap, what route would you recemend

A

If time was their overriding priority then a design & build procurement option would be best suited

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is GMP

A

Guaranteed maximum price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What does GMP mean to you?

A

A lump sum contract under which there is no adjustment to tender price unless design changes are requested by the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is partnering?

A
  • a long term approach of structuring business relationships
  • it involves two or more organisations working together to achieve specific mutual objectives
17
Q

What is strategic partnering

A
  • A long term relationship that is established with a view to undertaking a number of projects over a long period
18
Q

What are the benefits of partnering

A
  • The potential for conflict is reduced
  • Improved client satisfacaiton
  • Improved buildability with early involvement of contractors.
  • Better predictability of time and cost
19
Q

What is open tendering

A
  • Open tendering allows anyone to submit a tender for the works or services that are required. little to no barriers to entry
20
Q

What is selective tendering

A

this restricts the number of tenderers by pre-selecting a limited number of contractors to tender for the work

21
Q

What are the two types of selective tendering

A

single and two stage

22
Q

What is serial tendering

A

Contractors are asked to bid for a project on the basis that if they complete the intial

23
Q

What could selecting the wrong contractor lead to

A
  • a bad client & contractor relationship
  • A dissatisfied client
  • An insolvent contractor
24
Q

What would you include in a set of tender documents

A

in accordance with the JCT practice note 2017 i would include:
- ITT
- Form of tender
- pre-construction information
-pricing documentation
- drawings & specification
- conditions of proposed contract

25
What is a form of tender
- A pre-printed formal statement in which the tenderer fills in the blank spaces. - The tenderer provides their name, address and price for the woks
26
What are the employers requirements?
They set out the clients requirements including the function, size and quality of the project.
27
What are the Contractors proposals?
- The Contractors response to the Employers requirements. - They are the key documentation for the client at the tender review
28
What information would you request in the pre-qualification questionnaire
- management structure - Relevant experience - Company accounts - Health and Safety records - provision of bonds & warranties
29
How would you determine the duration of the tender period
- it depends on the procurement process and size of the project. - it is better to ensure there is sufficient time so the contractors can price the project correctly - rather than rush and encourage contractors to price a high risk element into a tender
30
What is a PQQ
Sets out a series of questions for potential tenderers to answer in order to reduce the number of tenders to those that are best suited to the project
31
What does the ITT document set out?
The ITT document sets out: - state the recipient, time, date and location of submission - Explain the method of dealing with queries - Give site visit contact details - Require a confirmation of receipt of tender.
32
What does the preliminaries document set out?
- Provides a description of the project that allows the contractor to assess costs which cannot be allocated to a specific element of works - This will include a general summary, method statements, pre-construction information, planning conditions and section/phasing of the work.
33
How would you deal with Arithmetical Errors in Tendering?
Alternative 1 - The tenderer cannot correct the tender price. The QS should amend computing errors and inform the contractor, who can choose to confirm or withdraw. Alternative 2 - The tenderer can correct the tender price. The QS should amend computing errors and inform the contractor, who can choose to confirm or amend.
34
What would you include in a tender report?
- Introduction - tender return dates - Tender opening record - Amount of normalisation/ rationalisation - Rationalised totals - Comparison against PTE/ Budget - Analysis of normalisation/ rationalisation - Recommendation
35
Can you select the highest tender?
- For a private client yes, Cost it is not always the most important factor for the client - Risk, capability, quality. - However for public, no
36
What are the purpose of post tender interviews?
Run through queries meet proposed site team assess client and contractor compatibility
37
How is CDP managed
1. CDP items and ER's stipulated by design team 2. Contractors proposals submitted with tender 3. CPs are reviewed and approval given 4. Incorporation into the works/ Contract
38
What are some typical qualifications included in a tender
Allowance for samples Assumed finishes Access to site
39
Why is the development of a PTE important
- A pre-tender estimate ensures the client can afford the project and provides a basis for comparing tenders. - While not part of the formal tender process, the PTE is essential for smooth tender analysis.