Procurement & Tendering Flashcards
(39 cards)
What is Procurement
The overall process of acquiring construction works
What should be considered when selecting a procurement route
Specifics to the project objectives such as
- Time
- Cost
-Quality
- Risk
What are the main procurement methods
Traditional
Design & Build
Management Contracting
Construction management
- Single Stage
- Two Stage
- Negotiated
What is traditional procurement
Traditional Procurement is where the design and specification is developed by the client and the design team pre-contract and then issued out to a list of contractors for a competitive process. A contractor is then employed to under take the construction works
How does traditional procurement work
- The client takes on the risk for the design and the design teams performance
- The contractor takes on the financial risk for the construction works
What are the advantages of traditional procurement
- It provides cost certainty to the client as the contractor provides a price based on the developed design
- The client retains control over the design and specification
- design changes are relatively easy to arrange and value
What are the disadvantages of traditional procurement
- Longer pre-contract programme due to design development
- No input from the contractor on buildability
What is Design and Build
- Design and Build is where the contractor has involvement with the design, planning, control and as well as the construction of the project in line with the employers requirements.
How does Design & Build work
The client provides the contractor with their Employers requirements and the Contractor responds with their contractor proposals, which include a price for the works.
It transfers the risk of the design development over to the contractor as well as the construction works.
What are the advantages of design and Build
- There is a single point of responsibility for the design and construction.
- There is earlier commencement onsite
- Contractors experience harnessed during the design phase
What are the disadvantages of design and build?
- Quality
- The client has to commit to a concept design early
- Clients may find it hard to prepare a sufficient comprehensive brief
- Variations from the original brief can often be expensive
How much design input will the contractor have in a design and build?
- This depends on the amount of design work the employer has already completed at the time of tender
- This can range from full design to production information and co-ordination only
If the client wishes to start onsite asap, what route would you recemend
If time was their overriding priority then a design & build procurement option would be best suited
What is GMP
Guaranteed maximum price
What does GMP mean to you?
A lump sum contract under which there is no adjustment to tender price unless design changes are requested by the client.
What is partnering?
- a long term approach of structuring business relationships
- it involves two or more organisations working together to achieve specific mutual objectives
What is strategic partnering
- A long term relationship that is established with a view to undertaking a number of projects over a long period
What are the benefits of partnering
- The potential for conflict is reduced
- Improved client satisfacaiton
- Improved buildability with early involvement of contractors.
- Better predictability of time and cost
What is open tendering
- Open tendering allows anyone to submit a tender for the works or services that are required. little to no barriers to entry
What is selective tendering
this restricts the number of tenderers by pre-selecting a limited number of contractors to tender for the work
What are the two types of selective tendering
single and two stage
What is serial tendering
Contractors are asked to bid for a project on the basis that if they complete the intial
What could selecting the wrong contractor lead to
- a bad client & contractor relationship
- A dissatisfied client
- An insolvent contractor
What would you include in a set of tender documents
in accordance with the JCT practice note 2017 i would include:
- ITT
- Form of tender
- pre-construction information
-pricing documentation
- drawings & specification
- conditions of proposed contract