Quantification & Costing Flashcards

1
Q

Why were the new Rules of Measurement introduced.

A

To standardise and improve the accuracy of measuring works.

NRM aimed to enhance cost management, reduce disputes, and provide cost compatibility with international standards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is NRM 1

A

Order of cost estimating and elemental cost planning for capital building works

provides a structured basis for measuring building works and for the production of cost estimates and cost plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key sections of NRM 1

A

Part 1 - general introduction explaining the purpose of the documents and how it should be used.

Part 2 - Measurement rules for the production of cost estimates

Part 3 - Measurement rules for the production of elemental cost plans

Part 4 - Tabulated rules of measurement for elemental cost planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Why should you use the New Rules of measurement

A

The NRM provides a common and consistent basis for the production of cost estimates and cost plans

NRM is seen as best practice, therefore in the event QS had a claim against them for negligence, if they could prove they used NRM it could provide a good defence against the claim.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does GEA stand for

A

Gross External Area

this is the area of the building measured externally at each floor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What does GIA stand for

A

Gross Internal area

area of the building measured to the internal face of the external walls.
Excludes external open sided balconies, canopies, external walls and fuel stores

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does NIA stand for

A

Net internal area

this is the area of useable space measured to the internal face of the perimeter wall at each floor level.

The NIA excludes internal structural walls, columns, spaces with headroom less than 1.5m, lift lobbies, toilets, plant rooms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Where are all the abbreviations found

A

The Code of Measuring Practice, issued by the RICS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the purpose of the code of measuring practice

A

Provides precise definitions to allow for accurate and consistent measurement of buildings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What would you expect the percentage of NIA to GIA to be

A

The percentage would depend on the type of project you are undertaking

For example in an office building, the NIA to GIA would be roughly 70%-85%

Where 70% is considered as relatively inefficient, a percentage of 85% is considered very efficient.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What do you measure in accordance with

A

The method of measurement would depend on the region, project and client i am working for

For example in the united kingdom, in the building sector, i would use the New Rules of Measurement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the purpose of a BOQ

A

To provide the estimator with an accurate picture of the scope of works and common consistent basis for pricing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How would you prepare a BOQ

A

Compile all necessary information - drawings specifications, schedules, document registers.

If the Information provided was sufficient to allow for the BOQ to be compiled, i would discuss with the project team the best method of measurement to be adopted.

i would then commence the take-off and work from the sub-structure upwards.

following the BOQ production i would carry out regular meetings and review any updated drawings to ensure that no that no works items have been missed between packages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How would you structure a BOQ

A

In accordance with an elemental breakdown structure under NRM 2, I would include the following sections:-

o Preliminaries (Main Contract).
o Facilitating Works.
o Substructure.
o Superstructure.
o Internal Finishes.
o Fittings, Furnishings and Equipment.
o Services.
o External Works.
o Provisional Sums.
o Dayworks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How would you describe the preliminaries section in a BOQ

A
  • The preliminaries detail out items of works that are required but are not associated in the main measured works.

For example, site set up, management & supervision, or insurances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How do you evaluate a variation which is based on a BQ item which contains an error

A

Assuming the same nature and conditions are applicable, the variation would be based on the BOQ rate in the contract

unless both parties agree to amend the rate to a fair and reasonable alternative

17
Q

What is a Provisional Sum

A

It is an allowance for item of works that cannot be defined or accurately priced.

18
Q

What is the difference between defined and undefined Provisional sums

A
  • Defined Provisional sums are those which have been described in sufficient detail that the contractor is expected to have made allowance for them in their programming, planning and preliminaries
  • Where there is insufficient information, the works are classed under a undefined provisional sum entitling the contractor to cost for prelim and an extension to the programme if required
19
Q

How did you check that the items measured for the BOQ were accurate

A
  • At RG we have a comp check system where upon completion, a joint review of the drawings is carried out by my senior colleagues to ensure all scope of work items are captured
  • Junior colleagues assist with undertaking spot checks on the quantities to ensure these are accurate
20
Q

What is NRM2

A

Detailed measurement for building works

  • Provides a set of detailed measurement rules for the preparation of bulls of quantities
  • The rules address all aspects production including guidance on the structure and format
21
Q

What is a Preamble

A
  • A preamble is an explanation of a document that is commonly found in contract, specifications and bills of quantities
  • It can help with the interpretation of the document
22
Q

What are method related charges

A
  • A method related charge is a one-off item related to the method of carrying out the work and does not form part of the permanent works.

For example provision of temporary propping required for a weakened elevation of an existing building

23
Q

What are time related charges

A

Time related charges are method related charges that are considered proportional to time taken to carry out the works for example plant hire

24
Q

What are fixed charges

A

Fixed charges are method related charges that do not vary with time. For example service connection charges

25
How do you quantify internal partitions
Section 2.7 of NRM1 details the measurement of internal walls and partitions. Measurement rules highlight the thickness to be stated and measured in m2 on the centre line. no deduction made for openings
26
What is a schedule 2 quotation
- A schedule 2 quotation aims to regulate the prices submitted by the contractor - The contractors quotation must cross reference to the rates and prices in the contract bills - Therefore, the contractor cannot simply disregard its tender rates and offer inflated prices when quoting variations
27
What are the problems with provisional sums to the PQS
- Contractor may get economies of scale/ cheaper prices PQS would not know about - Not much incentive for contractor to bring cost down
28
What are the different methods of measurement for a cost estimate
1. Functional Unit 2. Floor area 3. Elemental 4. Approximate Quantities 5. Bill of Quantities
29
What is the rule for variations under dayworks in JCT
If variations cannot be properly measured they can be valued on a 'daywork' basis these can be valued as: Option 1 - Percentage addition (Prime cost to which a % is added for OHP) Option 2 - All inclusive rates (quoted at tender and incorporated in the contract documents. include allowance for OHP)
30
What are the three New Rules of Measurement Volumes
NRM 1: Order of cost estimating and cost planning NRM 2: Detailed measurement of building works NRM3: Building maintenance works
31
How would you use benchmarking data
I would adjust for the following: - Inflation - Location - Abnormals
32
What risk allowances does NRM state need to be accounted for
Construction Risk Design Risk Employer Change Risk Employer Other Risk Total risk allowance = base cost estimate x % risk allowance for each of the above then added together
33
What is the differences between IPMS and NRM
IPMS: Focuses on area measurement standards, providing specific guidelines for how to measure floor areas, useable space, and external areas of buildings. NRM: provides a more detailed breakdown of measurement and pricing of construction work, including materials, labour, and overheads, and covers stages from preliminary design through to post-construction cost management
34
How are NRM and IMPS linked
NRM 1,2 and 3 are linked to IMPS 1 and 2, which set the rules for measuring GEFA and GIFA respectively
35
How does IMPS relate to the Code of Measuring Practice
IMPS 1 = GEA IMPS 2 = GIA IMPS 3 = NIA
36
What if a client asks you to use a different measuring practice
I would advise the client of the benefits of IPMS, however if they still wanted us to process with a different measurement practice, I would ask the client to confirm this in writing and use the measurement method the client has requested.
37
What are the benefits of IPMS over the Code
- Brings greater confidence and consistency to the global property market and allows greater transparency - It is globally recognised standard - Works alongside the international standard for accountancy and valuation - can be used by any number of stakeholders in a property
38
How would you measure for demolition/ facilitating works
Quantifying facilitating works: can be measured by site area, affected area, volume, length, time, or by item, depending on the type of work. Facilitating Works: Specialist tasks required before building works can begin, such as demolition, removal of hazardous materials, or soil stabilization. Enabling works: Broader term that includes facilitating works along with temporary works and permanent works (e.g, demolition, site investigations, access roads, mains services)