Project Finance Flashcards
What is cashflow?
Forecasted position of external valuation for each month for the duration of the job
What is a CVR?
Cost Value reconcillation
Allows overview of projects finances to be reviewed cost over value
What is a risk allowance?
.the amount added to the base cost estimate for items that cannot be precisely predicted to arrive at the cost limit.
Why is a contribution action plan used?
as a risk management tool to assess likely occurences of likely losses or gains
What is a liability?
Liability is a term in accounting that is used to describe any kind of financial obligation that a business has to pay at the end of an accounting period to a person or a business. Liabilities are settled by transferring economic benefits such as money, goods or services.
What is an accrual?
a charge for work that has been done but not yet invoiced, for which provision is made at the end of a financial period
What is an example of value engineering referenced?
Building partitions to underside of ceiling
What is change control procedures?
the process through which all requests to change the approved baseline of a project, programme or portfolio are captured, evaluated and then approved, rejected or deferred
How was the project CVR queried in the monthly performance review?
Subcontract variations were queried
Cost to complete of prelims was questioned
How was the risk management plan queried?
How did you formulate the cashflow?
Review programme with project manager and complete an external valuation for each month to the end of project
Related guidance to cost reporting?
RICS Black book:
- Cash flow forecasting 1st edition.
- Cost Reporting 1st Edition
- Interim Valuations and Payment
- Valuing Change
- Final account procedures
What is the purpose of post-contract cost / financial reporting?
- Provide overview of client’s current financial commitment
- Inform client of the likely outturn costs of the project
- Forecast outturn costs compared to budget and/or tender sum
- Give client understanding of potential savings / VE / additional monies required
- Report contract progress against pre-contract predictions
What information would you include in a post-contract cost report?
- Summary
- Contract sum
- Instructed variations
- Anticipated variations
- Provisional sum adjustments
- VE options
- Anticipated final account (forecast)
- Risk allowances / contingencies
- Cashflow forecast and certified payments
- Commentary on project status
Difference between cost and price?
- Cost is the expense incurred in the production of a product / service
- Price refers to payment required for supply of a product / service
How would you deal with a large and (in your opinion) unrealistic claim for loss and expense in your cost report?
- Report claim and highlight concern with figure submitted
- Assuming CA deems the principal of the claim is valid, I would assess the claim
- Update client on a regular basis until conclusion reached
What is a cash flow projection (/ forecast)?
- Financial planning tool showing predicted flow of cash in and out of project, typically shown month-by-month
- Typically form an ‘S curve’
What formula can be used to predict anticipated payments?
- S curve algorithm
Difference between employer cash flow and contractor (/ construction) cash flow projections?
- Employer -> usually considers project in broader context, may include costs such as fees (statutory, consultant, legal), charges (land acquisition, marketing and sales)
- Contractor -> construction costs
How does [the employer] benefit from accurate cash flow projections?
- Assist with planning expenditure- ensures apt funding in place
- Gain understanding of potential financial commitment at specific point in the future
- Sense check monthly contractor valuations
If payments to the contractor are behind the projection, what might this indicate?
- Construction works may be behind programme
If payments to the contractor are ahead of the projection, what might this indicate?
- Construction works may be ahead of programme or the contractor is over-claiming
How would you create a cashflow forecast?
- Require construction programme and CSA
- Values associated with element could be forecasted to reflect their installation within the programme
- Split works into different packages as shown on programme, include individual s-curves for each package
- (Can request cashflow from subcontractors to assist)
- Alternatively - use previous cashflow from similar scheme / cashflow forecasting software, though may not be as accurate
Different ways to produce a cash flow?
- S curve calculator to calculate expenditure over course of construction
- Use programme and pricing schedule to plot expenditure
- Request contractor to submit cashflow