Project Schedule Management Flashcards
(33 cards)
What are the key inputs for define activity
- Project management plan
a. Schedule Management Plan
b. Scope Baseline (WBS, WBS dictionary, project scope statement)
What’s the key tools & technique for define activity
- Decomposition (breaking down work packages into smaller activities)
- Rolling wave planning (progressive elaboration)
What’s activity list
- list of all scheduled activities to complete work package
Note: each activity should map to one work package and should have identifier
What’s activity attribute
resources needed to complete activity, location of activity, cost, assumption, constraints, leads and lags, relationship with other activities
Milestone List
milestone = major accomplishment or event
What is sequence activity
Take list of activity and put them in order
What are the key inputs for scheduling activities
- Project Management Plan
a. Schedule Management Plan
b. Scope Baseline - Project Documents
a. Activity list
b. Activity attributes
c. Milestone list
d. Assumption log
What are the tools & techniques to sequence activities
- Precedence Diagramming Method
- Dependency Determination
3, Leads & Lags - Project Management Information System
What’re FS, FF, SS, SF
- Finish-to-Start (FS): finish activity A then can start activity B
- Finish-to-Finish (FF): finish both activities simultaneously
- Start-to-Start (SS): start activity A first before starting activity B
- Start-to-Finish (SF): cannot finish until activity A starts
What’s mandatory dependency
Have to finish one activity to start next activity (hard logic)
Discretionary dependencies
activities do not need to get done in specific order (soft logic)
External dependencies
dependent on activities outside of project team
Internal dependencies
depend on activities within the control of project team
What’s the output of sequencing activity
Project schedule network diagram
What’s the output of sequencing activity
Project schedule network diagram
project document update (those inputs)
What are the examples of input of estimating activity duration
- Project Management Plan (e.g. schedule management plan, scope baseline)
- Project document list
a. activities: activity list, attributes, milestone
b. resource: resource breakdown structure, calendar, requirement
What are the examples of input of estimating activity duration
- Project Management Plan (e.g. schedule management plan, scope baseline)
- Project document list
a. activities: activity list, attributes, milestone
b. resource: resource breakdown structure, calendar, requirement
What’s Analogous estimating? What’s the advantage and drawback
- Historical information to assign current duration
- Quick to do
- Less accurate
What’s parametric estimating
based on historical data and variable to estimate activity duration
Three point estimate (Beta distribution)
(optimistic +4 * realistic + pessimistic)/4
What’s the formula to calculate std dev
(pess-opt)/6
What’s triangular distribution
(opt + realistic + pess)/3
Critical path activities have float
False
What is float
The amount of time that can delay activity without delaying project end date