Q-LINE INDOC HANDBOOK Flashcards
How Long is your PPC valid for ?
Initial and Upgrade are valid from the - 1st day of the 7th month after the PPC
Recurrent PPC - 1st day of the 13th month after the PPC, provided a loft is done in between.
How long is a Temp authorization valid for ?
90 Days
How long is the maximum duty day ?
14 in 24hrs
24hrs off in 3-12 hr consecutive duty days unless 24hrs off in between each duty day
What do we do if we are scheduled for a 14 hour but we’re too tired to continue flying
Call in Fatigued
What happens to your duty day if you are notified of a delayed reporting time before leaving the rest facility ?
If its an excess of the 3 hour, then the duty starts 3 hours after the original scheduled duty start. If the delay is less then 3 hours then the duty starts at the revised duty start.
What if you’re notified of a delay after you have left the rest facility ?
look up ?
When can we extend our duty beyond 14HR and what must we get in terms of rest ?
When crew agrees and its safe to do so
UOC
the rest period must be increased by at least the amount of the extension
PIC shall submit paper work
Porter has to keep the paper work until the next audit and notifies their assigned inspector within 30 days
15 HR crew augmented may be increased by 2 hours
What is the company policy on minimum scheduled rest, at home base, away and on a monthly schedule to meet transport Canada regulations ?
11 base
10 away from base
36 in 7
3 in 17
What is meant by “suitable rest facility ?
single occupancy room, well ventilated with minimum noise.
How many days free from duty do we need according to the regulations ?
36-7
3-17
How much notice do you need for a split duty ?
Minimum of 2 HRS or its already on your monthly schedule
How long can your split duty be ?
a split duty can extend your duty up to one half the length of the rest period to a maximum of 3 hours if :
- Advance notice ( on your monthly schedule or at least 2 HRS )
- At least 4 hours in suitable accommodations
- No interruption during the rest period
- The next day rest period is increased at least the amount of the extension
54
Are there any situations that Porter says definitely do NOT count as UOC ?
crewing issues the company was aware before crew left the rest facility, forecast weather, mechanical problem, connections etc.
If any of these are the case then delayed reporting time should be practiced.
Who makes the final decision for to extend the duty day based on UOC ?
The captain after consulting with the rest of the crew and they all agree.
Is adverse weather UOC ?
it can be depending if it was forecast or not.
Is a mechanical problem UOC ?
yes, sudden mechanical problems may be considered for UOC.
What happens if SOCC said “we’re considering this and UOC and you’re good to g,” but the Captain and crew don’t agree.
contact the chief pilot or DFO. mediate the situation
DEST fuel: How is it calculated, and what does it mean ?
it is compromised of:
- Take off and climb to 1500’ at take off power
- Climb to the anticipated cruise altitude
- Cruise to the TOD considering winds and temperature (
wights ) - Descend to the final approach fix and at destination and land also considering or vectors and holding.
ENRT RES: how is it calculated ? is it really 5% percent ?
Its 5% of the DEST Fuel to a maximum of 15min.
you may not have to carry it if you comply with 725.25
HOLD Fuel, how is it calculated ?
Holding Fuel for 45min at 5000’ above the alternate airport for a forecast wight and ISA.
ALTN Fuel: how is it calculated ?
- Climb from the missed approach point to the cruising altitude
- All flight plan Fuel burns to the alternate are based on LRC
- Descend to the final approach fix and land at the alternate
ADD Fuel: When would you need it ?
contingency fuel
loose and engine, descend to MSA or 10,000’ divert to suitable alternate shoot and approach miss and hold at 1,500’ for 30 min
EXTRA Fuel:
This is extra fuel loaded in excess of the minimum on the OFP
How is MIN BRF calculated ?
How do we reduce MIN BRF ?
the sum of:
DEST ENRT RES ALTN HOLD ADD