Questions From Mocks Flashcards
How long was the actual planning period?
20 weeks in total
How long was allowed for planning period on the programme
16 weeks
What caused the lead valley to fail?
Thermal expansion over time and the bay lengths being overly long for the code of lead used caused cracking.
What code of lead did you specify for the valley?
Code 6 as per lead sheet training academy guidance
How did you assess the significance of the building?
The previously listed building consent pack had included an historic building assessment that had undertaken a study on the history of the property, which identified the areas of significance and how the building had evolved over time.
And the historic england guidance on conservation principles
How old is the farm house
18th century
What is the maximum escape distance in one direction that required the second staircase.
It depends on the use of the building, the distances are set out in approved document B.
For this building In a single direction the maximum distance is 18m.
This is increased to 45m if there is two directions of escape.
What would you tella client if they asked you to look at the suitability of fire doors
I can undertake a visual inspection only, a fire engineer would need to assess suitability.
What are the method statement for asesbestos removal at overford
Negative pressure enclosure, air quality monitoring, under licence work
What are the client duties under CDM
Apoint a principle designer and contractors
The pd usally takes on the following client duties
Provide the PCI information.
Ensuring suitable management arrangements are made for the project
Notifying the hse were required
Ensure the project jas sufficient time and resources
Check the cpp
Maintain the h&s file
What does the lead designer do
Coordinate the design team
How did you assess quaily of work
I compared the work onsite to the spesification and schedule of work
What is Ridges complaint handling procedure.
A complaint should be ackonwledged as soon as possible and the CHP provided
If a complaint has been made verbally this must then be provided in a written form.
The complaint will be responded by a partner within 14 days, the outcome will then be decided within 28 days from any further comment.
If not satisfactory the complaint will be reviewed afresh by the responible senior partner within 28 days.
What is the width of a door for a wheelchair to pass through
It can be as little as 750mm but it depends on situation, Ideally 1m width. Approved document M has a table which sets out requirements.
How long from the end of a tenancy does the landlord have to bring a claim
schedules should be sent within 56 days after end of the lease
What is the difference between a named or nominated subcontractor?
named subcontractors are chosen from a listed, nominated are selected directly
What ate some protected characteristics
Race, sexual orientation, religion, age
What certificates would you issue at the end of the project.
Pc certificate then certificate of making good at the end of the defect period
What would you need for an advanced payment under the JCT
An advanced payment bond and a vesting certificate for any materials bought in advance kept off site
How would you advise on remedying defects out of scope (Fifield)
I could give high-level general advice, but generally I would avoid giving detailed advice on items outside of the scope of services.
What H&S regulation do you need to be aware of when working in roofs?
the health and safety at Work Act, and the working at height regulations
Did the asbestos removal company certificate certify that there were absolutely no fibres in the air?
a certificate of reoccupation was issued which assess that the air quality was within tolerance
what effect does MEES have
Buildings with a rating of E or below cannot be let without an exemption
what are LADS
LADS are the damages a contractor pays for being in breach of contract