Reactor Coolant System & Rx Vessel Internals Flashcards

(40 cards)

1
Q

What component(s) provide over pressure protection for the RCS and where do they relieve to?

A

Two Power operated relief valves and three spring-loaded safeties mounted on the pressurizer; each relieve to the pressurizer relief tank (PRT).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Describe the normal operating parameters of the U1 and U2 RCS (Unit two shown in parentheses in answer)

A

Volume - 95,000 (91,000)
Flow Rate - 403,700 (408,000)
Pressure - 2235 psig
Thot - 618 (620)
Told - 560 (559)
Tave - 557 - 585.4 (557 - 589.2)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Describe the design temperature and pressure of the RCS. How does it differ from the pressurizer?

A

Design temperature of the RCS is 650F and 2485 psig. The design temperature of the Pressurizer and surge line is 680F.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Of the RCS flow that enters the reactor vessel, a portion of the flow is utilized to cool the fuel assemblies while another portion ‘bypasses’ the fuel assemblies. Describe the percentage of flow that is utilized for cooling, and the percent-makeup of each bypass flow.

A

94% of the reactor coolant flow is available for heat removal, 6% of the flow bypasses the core.

1% - Nozzle bypass (from inlet nozzle to outlet nozzle)
0.5% - Baffle wall bypass
0.5% - Head cooling bypass flow
2% - Control Rod & Instrument thimble bypass.
2% - Baffle cooling flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Where do the pressurizer spray lines pull off the RCS?

A

Cold legs 1 & 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the normal and ‘alternate’ charging paths into the RCS from CVCS at power?

A

Normal - Loop 4 cold leg
Alternate - Loop 1 cold leg

Although they are described as ‘normal’ and ‘alternate’ the loops in which charging is aligned is alternated each cycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

During cold leg injection, following a safety injection, the following pump(s) inject into each cold leg through a 10-inch pipe:

A

SI Accumulators
SI Pumps
RHR Pumps

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

During cold leg injection, following a safety injection, the following pump(s) inject into each cold leg through a 1.5-inch pipe:

A

CCPs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

During hot leg recirculation, which two ECCS pumps can be aligned to the RCS hot legs, and to which hot legs can they be aligned?

A

RHR Pumps - Hot Legs 2 & 3
SI Pumps - All 4 Hot legs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Where does normal letdown pull off the RCS? What about Excess letdown?

A

Normal letdown - Intermediate leg 3
Excess letdown - Intermediate leg 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Describe the design and parameters associated with RCP Seal Leakoff #1

A

RCP Seal #1 is a film-riding seal.
- Receives 3 gpm and travels up the shaft, lubricating the radial bearing and leaking through the #1 seal.
- Seal injection temperature should be limited to LESS than 130F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Describe the design and parameters associated with RCP Seal Leakoff #2

A

RCP Seal #2 is a face-rubbing seal
- VCT backpressure forces approx. 3 gph through RCP Seal #2 and is directed to the RCDT.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Describe the design and parameters associated with RCP Seal Leakoff #3

A

RCP Seal #3 is a face-rubbing seal
- Supplied via the RCP standpipe (maintained by RMUW)
- Approx. 800 cc/hr half of which is directed to the containment sumps, and the other half to the seal #2 leakoff (RCDT)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Describe the RCP Seal Package flows

A

8 gpm of seal flow is aligned to each of the reactor coolant pumps. 5 gpm of the seal flow flows down the shaft, through the thermal barrier, and into the RCS. 3 gpm of the seal flow is directed up the shaft to each of the three seal packages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Describe the flow path of CCW to the RCP thermal barrier and any conditions or automatic actions that may affect it.

A

CCW enters containment through 1-HV-4700 and 1-HV4699 where it reaches a common header. This common header supplies CCW to each RCP thermal barrier and returns to the CCW system through containment isolations 1-HV-4696 and 1-HV-4709.

  • Both CCW supply and return to the RCPs is isolated on a containment isolation phase B (6.2 psig CNTMT atmosphere)
  • Each RCP thermal barrier outlet valve and the common return header isolation valve (ORC) 1-HV-4709 close on a high return temperature of 182.5F
  • Common CCW return header isolation valve (IRC) 1-HV-4696 isolates on high return flow of 64 gpm from any RCP
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What conditions must be met in order to open the RCP Seal water injection bypass valve u8142 and why would we want to?

A

u8142 may be opened to align more seal flow to the #1 seal or pump radial bearing on increasing temperature.

Required conditions:
1. RCS pressure is between 100 and 1000 psig
2. #1 seal leakoff valve is opened
3. #1 seal leakoff flow rate is <1 gpm
4. Seal injection water flow rate to each RCP is >/= 8 gpm

Why?:
Seal water injection temperature approaching 235F

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the purpose of the RCP flywheel and ratchet plate?

A

Extend the coast-down of RCPs post-trip and prevent reverse rotation.

18
Q

Describe the function of the RCP Cold Loop / Hot Loop switch

A

The RCP Cold Loop switch enables a higher over-current trip setpoint and the failure to accelerate / locked rotor automatic trips. These trips are disabled 30 seconds after pump start.

19
Q

How many successive RCP starts are permitted?

A

Two successive RCP starts are permitted provided the motor is allowed to coast to a stop between starts (~5 mins).

A third start may be permitted when the winding and the core have cooled by running a period of 20 minutes, or by standing idle for 45 minutes. (Recall the motors are air cooled, air is only pulled in while the motor is running).

20
Q

Describe the RCP Oil lift pump operation and associated interlocks

A

There are no automatic starts associated with the RCP Oil lift pump. Therefore, the lift pump must be manually run until the lift oil pressure has reached 600 psig (administrative minimum run time of two minutes).

After the RCP has been in operation for 1 minute, the oil lift pump may be turned off.

21
Q

Describe the function and capacity of the pressurizer spray valves

A

Two pressurizer spray valves, PCV-0455B from cold leg 1 and PCV-0455C from cold leg 4, function to reduce pressure by cooling the pressurizer. Each valve is capable of 450 gpm of flow, 900 gpm together.

A manual bypass valve around the spray valves is throttled to maintain a constant flow into the pressurizer, which helps maintain chemical and thermal equilibrium with the rest of the RCS.

22
Q

Describe the function and operation of the PORVs

A

PCV-0455A and PCV-0456 relieve steam from the top of the pressurizer at a nominal set point of 2335 psig. Each has a capacity of 210,000 lbm/hr.

Actuated by nitrogen pressure; fail closed on loss of nitrogen or power. Nitrogen accumulators (100 psig) allow for each PORV to be cycle 100 times over a 10 minute period.

Primarily function to prevent challenging the pressurizer safety valves and provide a means for LTOP.

23
Q

Describe the function and operation of the pressurizer safety valves

A

Three 6-inch safety valves, each with a capacity of 420,000 lbm/hr ensure the RCS is protected from overpressure conditions by lifting at 2460 (less than 110% design pressure) psig with a 3% accumulation.

Each safety valves relieve to the PRT and each line has a strap-on temperature element to provide indication of an open or leaking safety valve

Magnetic Reed switches - Intermediate position results in both light indications dark.

24
Q

Describe the function and operation of the pressurizer relief tank

A

The PRT functions to condense and cool the discharge from the pressurizer safety and relief valves. It is normally filled 64%-88% (RMUW) with a 1-7 psig nitrogen blanket at 113F.

The steam discharge line is submerged so that steam can be condensed by the water volume in the tank.

Two rupture disks prevent overpressure at 91 PSID (differential pressure between the inside of the tank and containment atmosphere).

25
What are the inputs to the subcooled margin monitor and what does it measure?
The SMM compares the highest valid RCS temperature with the lowest valid RCS pressure to produce the most conservative measurement of subcooling margin. The instrument reads from -300F to 300F where zero is saturated, less than zero is subcooled, and greater than zero is superheated
26
How do the reactor vessel flange O-rings work. How do they operate, and what indication do we have of leakage?
The reactor vessel flange O-rings are a silver-plated alloy that is perforated to accept system pressure and seal; referred to as 'self-energizing'. The inner O-ring is aligned through RC-8069B (N.O) and the outer O-ring is aligned through RC-8069A (N.C) Alarm indication on 1-ALB-05C at 140F at the outlet of the O-ring Leakoff .
27
List the MANUAL trip criteria for the RCPs
Upper & Lower Motor Bearing Temps = 195F Radial Bearing Temp = 225F Seal Inlet Temp = 235F Stator Winding Temp = 300F
28
List the RCP Vibration alarm and immediate shutdown criteria
Alarm: Shaft - 15 mills Frame - 3 mills Immediate shutdown criteria: Shaft - >15 mills and increasing @ >1 mil/hr or 20 mills max Frame - > 3 mills and increasing @ >0.2 mil/hr or 5 mills max
29
List the RCP Seal #1 Failure manual trips and their associated action times.
1. 6 gpm leakoff with rising temperatures = Immediate 2. 6 gpm leakoff with stable temperatures = 8 hours 3. 8 gpm leakoff = Immediate 4. <0.8 gpm leakoff = 8 hours 5. RCP radial bearing or seal inlet temps rising = Immediate RCP & Rx Trip.
30
Is an RCP that is experiencing a Seal #2 or #3 failure required to be shutdown?
No, and RCP is allowed to run with a seal #2 or seal #3 failure provided pump parameters remain stable.
31
What is the 'shut-down seal' in relation to the RCPs and when are they active?
The shut-down seals are located between the #1 seal and the #1 seal leakoff line. They are thermally actuated when exposed to elevated reactor coolant temperatures (260-320F) and provide a <1 gpm leak-tight seal on a loss of all RCP cooling (station blackout).
32
The Reactor Head requires one operable vent path via two solenoid-operated rockwell valves. What is their function, where are these valves powered from, where do they relieve to, and what are their failure positions?
The reactor vessel head solenoid vent valves are powered from uED1-1, they fail closed on a loss of power, and they relieve directly to containment atmosphere. They function to relieve non-condensable gasses that may occur during natural circulation or under post-accident conditions.
33
What is the function of the Neutron panels mounted on the vessel?
Neutron panels serve to provide shielding to the parts of the vessel closest to the core barrel from neutron embrittlement.
34
What is the function of the Secondary Core Support?
The secondary core support functions to limit the distance that the core barrel will drop following a postulated failure of the core barrel flange. It's designed to absorb the energy of the drop and limit the fall to ensure that the control rods may be inserted, coolant flow will not be blocked, and all fuel assemblies will remain within the core baffles.
35
List the RCS overpressure / under-pressure mitigation setpoints
Safety Limit - 2735 Pressurizer Safeties lift - 2460 (3% accumulation) High Pressure Rx Trip - 2385 PORV Open - 2335 Spray Valves Full Open - 2310 Spray Valves Begin to Open - 2260 C Heaters min current - 2250 NOP - 2235 C heaters max current - 2220 (DNB) Backup heaters on - 2210 PORV Block - 2185 P-11 - 1960 Low Pressure Rx Trip - 1880 SI - 1820
36
When do spray valves start to open and when are they full open?
Begin to open at 2260 psig, full open at 2310 psig
37
When are C heaters at maximum current? Minimum?
Maximum current 2220 psig, minimum at 2250 psig
38
When do backup heaters start?
2210 psig
39
What is the low pressure Rx Trip setpoint?
1880 psig
40
When do the PORVs open in auto?
2335 psig