Schedule Flashcards
(39 cards)
What is the key output of the Plan
Schedule Management process?
Schedule management plan
What are the key outputs of the Define
Activities process?
Activity list
Activity attributes
Milestone list
Change requests
What is the key output of the Sequence
Activities process?
Project schedule network diagram
What are the key outputs of the Estimate Activity Durations process?
Duration estimates
Basis of estimates
Updates to project documents
Describe the Develop Schedule process.
What are some of its key outputs?
An iterative process that creates a project schedule that is bought into, approved, realistic, and formal
Outputs: Project schedule Schedule baseline Change requests Schedule data
What are the key outputs of the Control Schedule process?
Work performance information
Schedule forecasts
Change requests
Updates to the schedule management
plan, performance measurement
baseline, and project documents
How does scheduling work in an
adaptive environment?
Adaptive teams form a general plan then try the first chunks of work and re-evaluate the next steps based on actual progress
What is rolling wave planning?
Planning at a higher level and
developing more detailed plans when the work is to be done
What do network diagrams show?
The network diagram shows just
dependencies (logical relationships)
If estimates and leads and lags are added to the diagram later in the schedule management process, it can also show the critical path
If plotted out against time (or placed
against a calendar-based scale), the
network diagram is a time-scaled
schedule network diagram
What are the four types of logical
relationships between activities in the
precedence diagramming method?
Finish-to-start (FS): An activity must
finish before the successor can start
Start-to-start (SS): An activity must start
before the successor can start
Finish-to-finish (FF): An activity must
finish before the successor can finish
Start-to-finish (SF): An activity must
start before the successor can finish
What are mandatory dependencies?
What are discretionary dependencies?
Mandatory: The order in which activities must be done, due to the inherent nature of the work or as required by a contract; also called hard logic
Discretionary: The order in which
the organization has chosen to have
work performed; also called preferred,
preferential, or soft logic
What are external dependencies?
What are internal dependencies?
External: Dependencies based on the
needs of a party outside the project
Internal: Dependencies based on the
needs of the project; may be under the
control of the project team
What is a lag?
What is a lead?
Lag: Waiting time inserted between
activities
Lead: How soon an activity can start
before its predecessor activity is
completed
What is padding?
What is the problem with padding?
A pad is extra time or cost added to an
estimate because the estimator does not have enough information
Padding undermines the professional
responsibility of a project manager to
develop a realistic schedule and budget
What are some estimating techniques
used in an agile environment?
Relative sizing
Affinity estimating
T-shirt sizing
Planning poker
What is analogous estimating?
When is it done?
Analogous estimating uses expert
judgment and historical information to
predict the future
It can be done at various times, and the
level of accuracy depends on how closely the project or activity matches the past historical data used
What is parametric estimating?
What tools might an estimator use to
create parametric estimates?
Parametric estimating involves creating
a mathematical equation using data from historical records or other sources, such as industry requirements or standard metrics, to create estimates
Regression analysis or a learning curve
What is an example of a heuristic?
The 80/20 rule
A heuristic is a generally accepted rule,
or best practice
What is the difference between
triangular distribution and beta
distribution?
Triangular distribution is a simple average giving equal weight to each of the three-point estimates when calculating the expected activity duration or cost; it uses the formula (P + 0 + M)/3
Beta distribution is a weighted average
that gives stronger consideration to the
most likely estimate; it uses the formula
(P + 4M + 0)/6
What is alternatives analysis?
Alternatives analysis involves evaluating the impact of each option on project constraints, including financial investment versus time saved and level of risk
This process will result in the
determination of the best approach to
completing project work within the
constraints
What are some inputs to Estimate
Activity Durations?
Activity list and activity attributes Assumption log Lessons learned register Resource breakdown structure Resource requirements Project team assignments Resource calendars Risk register
What is required for bottom-up
estimating?
An accurate WBS
What is the difference between T-shirt
sizing and planning poker?
They are both adaptive estimating
techniques, but T-shirt sizing assigns
effort and number of user stories of each feature in terms of T-shirt sizes, while planning poker uses cards to assign a relative unit (such as story points) to each user story with the goal of building an agreed-upon estimate of the work
What are the two types of reserves being evaluated in reserve analysis?
Contingency reserves and management reserves