Scope Management Flashcards

(28 cards)

1
Q

Which Process Group does Plan Scope Management belong to?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which Process Group does Collect Requirements belong to?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which Process Group does Define Scope belong to?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which Process Group does Create WBS belong to?

A

Planning

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which Process Group does Validate Scope belong to?

A

Monitoring and Controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which Process Group does Control Scope belong to?

A

Monitoring and Controlling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are 3 the inputs to the Collect Requirements process?

A

Requirements Management Plan
Scope Management Plan
Stakeholder Engagement Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the input to the Define Scope process?

A

Requirements Documentation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the input to the Create WBS process?

A

Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the inputs to the Validate Scope process?

A

Verified Deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the inputs to the Control Scope process?

A

Work Performance Data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the outputs of the Plan Scope Management process?

A

Requirements Management Plan

Scope Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the outputs of the Collect Requirements process?

A

Requirements Documentation

Requirements Traceability Matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the outputs of the Define Scope process?

A

Project Scope Statement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the outputs of the Create WBS process?

A

Scope Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the 5 components of the Scope Baseline?

A
Work Breakdown Statement (WBS)
Work Packages
Planning Packages
WBS Dictionary
Scope Statement
17
Q

What are the outputs of the Validate Scope process?

A

Accepted Deliverables

18
Q

What are the outputs of the Control Scope process?

A

Work Performance Information

Change Requests

19
Q

What tools are used in the Collect Requirements process?

A

Decision Making
Data Gathering
Data Representation

20
Q

What tools are used in the Define Scope process?

A

Alternatives Analysis

Product Analysis

21
Q

What tools are used in the Create WBS process?

A

Decomposition

22
Q

What tools are used in the Validate Scope process?

23
Q

What tools are used in the Control Scope process?

A

Variance Analysis

24
Q

What is gold plating?

A

Delivering more than was agreed upon.

25
What are the 6 processes in the Scope Management knowledge area?
``` Plan Scope Management Collect Requirements Define Scope Create WBS Validate Scope Control Scope ```
26
Which 2 components of the Project Management Plan are created in the Plan Scope Management process?
Scope Management Plan | Requirements Management Plan
27
What is a Control Account?
A node on the WBS where scope, time and cost are measured.
28
What is the main purpose of the validate scope process?
To ensure the resulting product or service matches the scope.