Session 10. Flashcards
2. All plumbing inspections shall be performed at the sole cost and expense of the: A. Holder of the permit. B. Licensed Master Plumber. C. Owner. D. Builder.
C. Owner.
1. All plumbing system piping shall be tested with either water or, or for piping systems other than ... , by air: A. Cast iron. B. Copper. C. Stainless steel. D. Plastic.
D. Plastic.
3. All plumbing tests shall be made by: A. The registered engineer. B. The permit holder. C. General contractor. D. Builder.
B. The permit holder.
4. The maximum gas demand, the volume of gas to be provided to a premises is calculated in: A. Cubic inches per hour. B. Cubic feet per hour. C. Cubic mater per hour. D. Liters per hour.
B. Cubic feet per hour.
- For gas pipe sizing:
A. The totally connected hourly load shall be used as its basis.
B.The totally connected flow on a minute basis.
C. The totally connected daily flow twenty-four hours as its basis.
D. The totally connected weekly flow shall be used at its basis.
A. The totally connected hourly load shall be used as its basis.
6. Individual outlets to gas ranges shall not be less than: A. 0.75 inches. B. 0.625 inches. C. 0.50 inches. D. 0.375 inches.
A. 0.75 inches.
- Gas piping shall be sized in accordance with one of the following:
A. Pipe sizing tales or equations with section 402.4.
B. The sizing tables included in a listed piping system’s manufacturer’s installation instruction.
C. Other approved engineering methods.
D. A, B & C.
D. A, B & C.
- Pipe size of each section of gas piping of the longest pipe run from the point of delivery to the most remote outlet shall be determined using:
A. Using the shortest run of piping and the load of the section.
B. Using the longest run of piping and the load of the section.
C. Calculating the total use of gas on the complete pipe.
D. Cast iron, copper pipe, brass pipe, aluminum-alloy pipe and metallic tubing.
D. Cast iron, copper pipe, brass pipe, aluminum-alloy pipe and metallic tubing.
- In the installation of gas piping thread (joint) compounds (pipe dope) shall be resistant to the action of liquefied petroleum gas or to any other chemical constituents of the gases to be conducted through the piping. Use of cotton thread (lamp wick) is:
A. Permitted.
B. Permitted when a defect is found in the threaded joint.
C. Permitted when approved.
D. Prohibited.
D. Prohibited.
11. Pipe joint not approved when installing gas piping: A. Threaded. B. Flanged. C. Welded. D. Brazed.
D. Brazed.
- When installing equipment shutoff valves, each appliance shall be provided with a shutoff valve separate from the appliance.
the shutoff valve shall be located in the same room as the appliance, not further than … from the appliance, and shall be installed … from the union, connector or quick disconnect device it serves:
A. 2 feet upstream.
B. 4 feet upstream.
C. 6 feet upstream.
D. 8 feet upstream.
C. 6 feet upstream.
13. An outside gas service line valve (curb) is required when the gas pressure is: A. Any pressure. B. Less than 150 psi. C. Less than 1/2 psi. D. More than 3 psi.
A. Any pressure.
14. Tubing joints and flared gas pipe joints: A. Will be permitted. B. Shall not be used. C. Will be permitted if used indoors. D. Will be permitted sometimes.
B. Shall not be used.
15. Standard face flanges shall be permitted for use in this fuel gas code. Where 150-pound pressure-rated steel flanges are bolted to class 125 cast-iron flanges, the raised face on steel flanges: A. Shall be removed. B. Shall remain. C. Shall remain with an approved gasket. D. Remain up to 225 psi.
A. Shall be removed.
16. Materials for gaskets shall be capable of withstanding the design temperature and pressure of the piping system, and the chemical constituents of the gas being conducted, without change to its chemical and physical properties. The effects of fire exposure to the joint shall be considered in choosing the material. Acceptable materials shall not include: A. Metal or non-asbestos fiber. B. Aluminum "O" rings. C. Spiral wound material gaskets. D. Asbestos hard material.
D. Asbestos hard material.
- In fuel gas pipelines, when a flanged joint is opened:
A. Care must be taken not to deform the gasket in any manner, to be reused.
B. The gasket shall be replaced.
C. The gasket may be replaced.
D. The gasket may be replaced with the manufacture’s approved sealant.
B. The gasket shall be replaced.
- Full-face gaskets:
A. Shall be used with all cast-iron flanges.
B. Shall be used in all steel flanges.
C. Shall never be used.
D. Shall only be used when the flange is rated above 250 pounds.
A. Shall be used with all cast-iron flanges.
- When installing gas fuel piping lines, they shall:
A. Not be installed within a stair enclosure or required exit or exit way.
B. Not be installed in any shaft containing standpipe risers.
C. Not be installed within any space housing a fire pump.
D. A, B & C.
D. A, B & C.
20. Underground piping, where installed below grade through the outer foundation or basement wall of a building, shall be: A. Coated by the manufacturer. B. Schedule 80 pipe or greater. C. Encased in a protective pipe sleeve. D. Red leaded and tar coated.
C. Encased in a protective pipe sleeve.
- Underground piping, where installed below grade through the outer foundation or basement wall of a building:
A. Shall be fully tarred by the manufacturer.
B. The annular space between the gas piping and the sleeve shall be sealed.
C. The annular space between the gas piping and the sleeve shall be packed with oakum or jute.
D. The annular space between the gas piping and the sleeve shall be filled with bees wax.
B. The annular space between the gas piping and the sleeve shall be sealed.
22. Gas pipe branches shall be taken off the riser with not less than a: A. Double swing . B. Single swing . C. Two-elbow swing. D. An elbow and a "T" joint.
C. Two-elbow swing.
- Piping in solid floors shall be laid in:
A. Compacted virgin sand and covered in a manner that will allow access to the piping.
B. Clean earth with no frozen dirt and covered in a manner that will allow access to the piping.
C. Poured concrete.
D. Channels in the floor and covered in a manner that will allow access to the piping.
D. Channels in the floor and covered in a manner that will allow access to the piping
All gas piping installed outdoors shall be elevated above ground and where installed across roof surfaces, shall be elevated not less than: A. 1-inch. B. 1-1./2 inches. C. 2-inches. D. 3-1./2 inches.
D. 3-1./2 inches.
- Metallic pipe exposed to corrosive action, such as soil condition or moisture, shall be protected in an approved manner.
zinc coatings (galvanizing):
A. Shall not be deemed adequate protection for gas piping underground.
B. Zinc coatings (galvanizing) shall be deemed adequate protection for gas piping exposed in exterior locations.
C. Ferrous metals exposed in exterior locations shall not be protected from corrosion.
D. A & B are correct.
D. A & B are correct.