SOE - Optional Competencies Flashcards
Why is it important to record progress and manage quality?
These documents are a universal reference point and very useful to measure progress or look when specific items were discussed or decided. It also helps to confirm actions and hold people accountable.
Managing quality is important to ensure that the project is completed to the standard specified and minimise and potential defects.
What are the key aspects of a good set of site minutes?
Dated, including weather conditions. Clear, well written and inclusive of all matters discussed with reference to action points and relevant responsible people.
What information should be recorded when visiting to carry out progress and quality management?
Date. Weather. Number of operatives on site. Progress of works in relation to programme. Any delays and the causes. Any snags. If the materials being used are in line with the specifications. Health and safety concerns. Photographs should be taken.
How do you undertake a progress inspection?
Once on site, I will make contact with the site manager and walk around the site to see what progress has been made.
I review this against the programme and previous inspection.
I review any action notes from the previous report and assess progress of these.
I will not any new action points and allocate these to a specific person.
I take and store photographs.
What are some quality descriptors?
Details and standards the contractor should adhere to, such as British standards, the specification and manufacturers guidelines.
How do you ensure quality?
Appoint a competent contractor.
Include standards in the specification and check compliance with this.
Ask for samples.
Check the materials and workmanship against the spec.
What are some common recommendations from the Lead Sheet Associations technical standards?
Flashings should not be laid in lengths longer than 1.5m.
Lap joints should be 150mm.
Upstands should be 75mm.
Code 3 – Soakers
Code 4 – Soakers, flashings and vertical cladding.
Code 5 – Flashings, flat roofing, parapet and tapered valley gutters, pitched roofs, vertical cladding, dormers, and bay roofs and canopies.
Code 6 – Flashings, flat roofing, parapet and tapered valley gutters, pitched roofs, vertical cladding, dormers, and bay roofs and canopies.
Code 7 - Code 5 – Flat roofing, parapet and tapered valley gutters, pitched roofs, dormers, and bay roofs and canopies.
Code 7 - Code 5 – Flat roofing, parapet and tapered valley gutters, pitched roofs, dormers, and bay roofs and canopies.
During your visit to Sterne Street, you noted that the lead detailing had not been installed in line with the LSA standards, how was it installed?
In lengths longer than 1.5m, minimum upstands around 20-30mm, no laps joints.
Is there an alternative to leadwork?
Yes, there are several alternatives such as zinc, aluminium and polymer rubbers.
What are you looking for when inspecting the works progress and quality management?
That the works are being carried out to a good standard, in line with the specification and in line with the programme.
What would you do if a contract began to fall behind the programme?
I would assess which aspects were behind and recommend that they provide more resources to the project to help catch up.
What is the process at the end of a defects liability period?
I inspect the site with the contractor, review the works and issue a snagging list to the contractor. Following completion of the snagging items I will reinspect before issuing a certificate of making good defects on completion, followed by a final payment certificate.
How do you treat snags?
I undertake regular site inspections and note any defects or snags as works progress, I will highlight these to the site foreman so they can be dealt with as soon as possible.
If quality is poor, what do you do?
I would review with the site foreman and ask them to remove and recomplete the works. I would withhold payment for that element of works until complete.
How do you report progress to a client on a project?
Depending on the size of the project, I will either issue weekly or monthly progress reports, which include an overview of the works, a comment on quality, progress vs programme and a project cost summary.
How did you deal with the contractor carrying out works that were not specified?
I met with the contractor to discuss the works defined in the specification and also referred to the meeting notes from previous inspections confirming that the work carried out was not required. They accepted this and agreed that there would be no cost to the client.
What is traditional procurement strategy?
Traditional procurement is a method for acquiring goods and services that involves a separate design and construction phase. (Desing – Bid – Build).
This means the process can be slow, but also means there is some certainty over the design, cost and duration. It is the least risky and tenders are accurate and competitive.
What is a design and build procurement strategy?
This is when a single contractor assumes the responsibility for designing and building the project.
It is generally quicker than the traditional method as works can start before all of the design elements are fully completed.
What is a construction management route?
The client directly employs multiple sub contractors, rather than appointing one main contractor.
This provides the client with greater control over the contractors.
It allows for early commencement, but has less cost certainty due to ongoing design and individual trade contracts. The client requires experience to manage effectively.
What influences the selection of the most suitable procurement strategy?
Timeline
Budget
Risk
Ownership
Tell me about single stage tendering, and when it is used.
Tender documents are issued to competing contractors who are bidding based on identical tender documentation and usually the fully finished design.
Contractors are given a deadline to return submissions, which are then assessed for suitability before one contractor is appointed.
It is used when the design is complete, the client is not in a rush and needs some cost certainty.
Tell me about two-stage tendering and when it is used.
This method involves two stages. In the first stage contractor submit their qualifications, experience and a broad cost proposal based on early design stages.
The client then selects one or more contractors to proceed with the second stage, where detailed pricing and design are negotiated.
This is used for complex projects where the involvement of a contractor is beneficial to help with the final design. However, costs are less certain.
What is the latest JCT Practice note?
2017
Why did you believe a traditional procurement route was suitable for Middlefields, following your meeting with the managing agent?
Wanted a start I summer, so no rush.
The specification would have been confirmed prior to tender.
Needed cost certainty.