Specifications And Schedules Flashcards
(18 cards)
As blueprints represent the construction project through pictures, ____________ are the word descriptions of the work to be done
Specifications
True or false? Specifications contain any information that cannot fit in the drawing because of the large amount of written detail that is necessary
True
HVAC information is placed in what division?
23
What is the difference between specifications and schedules?
Specifications describe the work to be done
Schedules provide info on what goes where
What are changes to the original blueprints called?
Revisions
What are changes to the specifications called?
Addenda
True or false? Addenda and revisions do not supersede original drawings
False
In what order does information found in blueprints, specs, and schedules get prioritized?
Addenda supersedes original specs
Specs supersede blueprint revisions
Revised blueprints supersede originals
What makes it easier to find and coordinate info between trades?
Drawing legend table
What do mechanical general notes do?
Provide additional directions for determining the general intent of the specifications
Where would you find allowed manufactures of grilles?
Specifications or grille schedule
True or false? The actual intent off drawings and specifications is to be complimentary with neither taking precedent over the other.
True, but in the event of discrepancies specs supersede drawings
What plans and views do architectural drawings typically include?
-site plan
-floor plan
-exterior elevation
-interior elevation
-material specs
-building sectional views
-detail sectional views
What do engineering drawings show?
How the building is to be constructed as well as mechanical infrastructure
What are changes to drawings on site during installation are referred to as?
As-builds
True or false? It is good practice to orally agree to changes on drawing even if it costs more money as it keeps general contractors happy
False. Never orally agree to a drawing change that is going to cost more money, as you may be left financially responsible for added costs
True or false. The national master specification (NMS) is a comprehensive library of construction standards
True
True or false Standard specification formats follow the CSC master format?
True