Tech Spec 2.0 AND Misc Flashcards

(3 cards)

1
Q

Completion Time

Extension Rules

A

Applicable: 2nd train becomes INOP

                          - 1st/2nd exist concurrently
                          - 2nd remains INOP after 1st restored

Total Time (Most Restrictive of):
Initial Completion time + 24 hrs.
Or
Completion time from 2nd inoperability

Does not apply to first “Once Per” actions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

LCO 2.1.1

Core Safety Limits

Actions/Modes

A

DNB 1.34
Peak Fuel <5080 (lowers 58F every 10000MWD/MTU)

Modes 1 & 2

Restore AND Mode 3 within 1 hour

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

LCO 2.1.2

RCS Safety Limit

A

Applicable: Modes 1-5

RCS Less than or Equal to 2750 psia

Applicable: Modes 3-5

Restore in 5 minutes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly