Throughput Accounting and Project Planning Flashcards

(23 cards)

1
Q

What is the equation for throughput

A

Revenue per production Run - Materials and Freight out

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the formula for profit velocity

A

throughput / Production Time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are some ways of maximizing profit velocity

A

avoid downtime (shift changes/brakes)

outsource low profit velocity work

optimize change over

reduce waste

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what is Project Planed Value (PV)

A

Estimated value of the work planned to be done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is Project Earned Value (EV)

A

Estimated value of the work actually accomplished

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what is project actual cost (AC)

A

Actual costs incurred to date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is project budget at completion (BAC)

A

currently expected total cost of a project (PV end point)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is project estimated cost at completion (EAC)

A

how much we expect the total project to cost at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

what is project estimated cost to complete (ETC)

A

how much more to finish (From now)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is project variance at completion (VAC)

A

how much over / under are we expected to be at completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the planned Value formula

A

PV = Planned % Complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what is the earned value formula

A

EV = Actual % complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the Actual Cost Formula

A

AC = Actual Cost..

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the schedule performance index

A

SPI = EV/PV (>1 is favorable)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the Schedule Variance

A

SV = EV - PV (Positive is favorable)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the Cost Performance Index Formula

A

CPI = EV/AC (>1 is favorable)

17
Q

what is the cost variance Formula

A

CV = EV - AC (Positive is favorable)

18
Q

What is the cost Estimate at Completion Formula

A

EAC = BCA/CPI

19
Q

What is the cost estimate to complete formula

A

ETC = EAC - AC

20
Q

what is the variance at completion formula

A

VAC = BAC - EAC

21
Q

What are the Return of Investment Basics

A

Identify the investment
Identify the net benefits
Identify the timeline
Determine the return OF investment (investment / timeline)

Annual Benefits - annual Return of investment = Return ON investment

22
Q

What is the %ROI formula

A

%ROI = Annual Monetary returns ON investment / Investment