Q

contract documents consists of the following

A
  1. agreement
  2. general conditions
  3. special provisions
  4. specifications
  5. drawings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

person ordering the project for execution

A

owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

commissioned by the owner

A

architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

person so named in the contract document

A

engineer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

full time construction inspector hired by owner assisting in the supervision of the work

A

project representative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

person or firm whose proposal has been accepted & contract awarded

A

contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

having direct contact with contractor, acts in behalf of the contractor in executing any part of the contract

A

sub-contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

person, firm, or corporation providing guarantee for contractor’s bonds

A

surety

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

offer of a bidder

A

proposal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

cashier’s check or surety bond with the proposal submitted by the bidder to guarantee that the bidder will enter into the contract

A

proposal bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

(15%) approved form of security furnished by the contractors as guarantee to pay all obligations arising from the contract

A

performance bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

(15%) approved form of security furnished by the contractor as a guarantee to pay all obligations arising from the contract

A

payment bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

(15%) approved form of security furnished by the contractor to guarantee the quality of materials and workmanship performed

A

guarantee bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

contract between owner and contractor undertaking the project

A

agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

notice or invitation issued to bidders giving information of the magnitude and extent of the project, nature, etc

A

advertisement / invitation to bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

additional information on contract documents

17
Q

list of instructions on preparations and conditions for award of contract

A

instruction to bidders

18
Q

graphical representation of work

19
Q

printed documents stipulating procedural and administrative aspects of contract

A

special provisions

20
Q

written or printed description of work describing qualities of materials and mode of construction

A

specifications

21
Q

additional info issued as an addition or amendment to provisions of specs

A

supplementary specs

22
Q

outline specs enumerating type and trade names of materials used

A

schedule of materials and finishes

23
Q

list of work and corresponding value in materials and labor including profit and overhead allowance

A

breakdown of work and corresponding values

24
Q

info, advice or notification pertinent to the project

A

written notice

25
catastrophes, phenomena of nature, misfortunes, and accidents which human prudence cannot foresee or prevent
act of God/ force majeure
26
duration of time allowed by the contract for project completion
time limits
27
laws, ordinances, and government regulations applicable to the project
local laws
28
includes labor and materials, equipment, transportation, faculties necessary for completion of project
work
29
build in, mount in positions, connect or apply
install
30
purchase and or fabricate and deliver to the jobsite
furnish
31
furnish and install
provide