week 6 - contract law Flashcards
what is meant by the discharge of a contract?
when a contract comes to an end. all obligations under the contract finish + the parties are no longer bound in law.
what are the 4 ways of discharging a contract?
- agreement
- performance
- frustration
- breach
what does it mean by discharge by agreement?
where parties agree to bring a contract to an end before all obligations have been completed.
can be bilateral or unilateral
the consideration each party offers is releasing the other party from their obligations.
what is a bilateral agreement to discharge?
where neither party has completed all their obligations.
what is a unilateral agreement to discharge?
one party has performed all their obligations but the other party wishes to be released from their obligations before performing them.
can only be released if that party provides some consideration for the release.
agreement to be released = accord.
supply of consideration to be released = satisfaction.
what is meant by discharge of frustration?
before the obligations have been completed an event may occur that makes the performance impossible.
both parties are discharged from carrying out any further obligations.
what are some examples of frustrating events?
destruction of subject matter, government intervention, non occurrence of events central to the purpose of the contract, following illegality, personal incapacity.
what is meant by discharge by breach?
where one party breaks one or more terms of the contract. this will only discharge the contract if its a condition or an innominate term that deprives the party of substantially the whole benefit of the contract.
what are the 2 types of breach?
- actual breach
- anticipatory breach
what is meant by an actual breach of a contract?
the innocent party can sue for breach + if the term broken is a condition it can also terminate the contract.
when does a actual breach of a contract occur?
when the time of the performance of a contract is due + the contract has been breached.
what is an anticipatory breach of a contract?
the innocent party may sue immediately or wait for the date of performance to pass.
when does an anticipatory breach occur?
the time of the performance of the contract has passed + one party has indicated they do not intend to perform.
what is meant by a discharge by performance?
ideal method, each party has done exactly what they have promised to do, contract ends as all obligations have been performed.
what are the remedies for a breach of contract?
if contract is breached, the innocent party may claim for one or more remedies in court.
- damages
- quantum meruit
- specific performance
what is quantum meruit?
a claim for work done, where completion has been prevented by another party.
what is specific performance?
party is legally required to complete performance of contract.
what is meant by damages?
monetary compensation aimed to put the parties into the position they would have been in had the breach not occurred.
most common remedy.
up to the court to decide the amount to grant unless already pre-estimated in the contract.
what are the aims of damages?
to restore the innocent party to the same financial position they would have been in if the contract had been performed, NOT to punish the party who broke it.
what is a nominal damage?
awarded when the innocent party has suffered no real loss.
what is meant by remoteness of damage?
claims for damages are restricted to the recovery of losses that are not too remote. courts are to decide how far the liability of the defendant extends.
what is an example of a care that laid out the test for remoteness of damage?
hadley v baxendale (1854)
Mill owner ordered a new shaft as the old one broke + no work could be done, the carrier was unaware the mill did not have a spare + was late delivering the new one.
The owner sued the carrier for loss of anticipated profits on the days it was late.
what 2 elements can damages be awarded for?
- losses that arise naturally as a result of the breach (objective test).
- loss that both parties contemplated when the contract was made (subjective test).
what occurs with the measure of damages?
if the contract was for the sale of goods, the damages are assessed according to the market rule (how much the goods cost on the open market).
if a breach results in lost opportunity, this can be recoverable if it can be quantified.