2004 NRC Flashcards
(99 cards)
Unit 2 has been at 60% power for 3 days.
The following conditions exist:
• Control Bank D is at 174 steps withdrawn.
• Rod Control is in automatic.
• RCS Auctioneered High Tave is 564 deg F and steady.
Control Bank D rods start withdrawing at 8 steps per minute. With Control Bank D at 177 steps, Rod Control is placed in Manual, and all rod motion stops.
Which ONE of the following describes why control rods will be inserted in manual to 174 steps withdrawn in accordance with 02-OHP-4022-012-003, Continuous Control Bank Movement?
a. To prevent reduced charging flow.
b. To prevent exceeding QPTR Limits.
c. To restore RCS pressure to normal.
d. To restore Tave to programmed band.
d. Correct - 60% power, programmed Tave is~ 563.2 degrees. Act. Tave is ~0.8 deg above program. When rods withdraw, power will rise, then the reactivity from the rise in temperature will cause power to return to ~ it’s pre-withdraw power, with Tave higher. Auct. high Tave feeds other systems that rely on Tave to remain on program. Rods are reinserted to restore equilibrium.
Unit 1 is in the process of starting up following an outage. Reactor trip breaker testing was taking place with power at 2%. A loss of offsite power results in the trip of all RCPs. Additionally, CRID 2 is lost when the CD EDG energizes T11D.
The following conditions exist:
• Reactor trip breaker A - OPEN
• Reactor trip bypass breaker A - OPEN
• Reactor trip breaker B - OPEN
• Reactor trip bypass breaker B - CLOSED
• WR startup rate is -0.3 dpm
• RCS Tavg is 547°F and lowering
Which ONE of the following is the NEXT action required of the operators and why?
a. Send an operator to locally verify reactor trip breakers are open because control room indications are NOT accurate with a loss of CRID 2.
b. Transition to 01-OHP-4023-FR-S.1, Response to Nuclear Power Generation/ATWS, because the reactor failed to trip.
c. Transition to 01-OHP-4023-E-0, Reactor Trip or Safety Injection, because the reactor has tripped.
d. Manually close the steam dump valves because they incorrectly opened due to the reactor trip breaker status.
c. Correct - The Plant has tripped. Only 1 trip breaker/bypass set is required to open to trip the plant. With the plant in Mode 2, 01-OHP-4023-E-0 is applicable.
The plant has experienced a large break LOCA. The reactor has tripped and an SI signal is present. Charging Pumps Suction from RWST IMO-910 opened BUT IMO-911 failed to open.
Which ONE of the following is the impact of this action on the Charging Pump suction flow?
a. Both operating charging pumps will receive suction flow from the VCT.
b. Both operating charging pumps will receive suction flow from the RWST.
c. One charging pump will continue to take suction from the VCT and one charging pump will take suction from the RWST.
d. One charging pump will take suction from the RWST. The other charging pump will have no suction until operator action is taken.
b. Correct - CVCS suction from the RWST is provided through the IMO-910 and IMO-911 valves which are in a parallel arrangement allowing either valve to provide suction to both pumps.
Unit 2 Reactor Startup is in progress with Reactor Power at 2E-8 amps and rising.
The following conditions exist:
• Annunciator Panel 207 Drop 62, RCP 3 Bearing Temp High, is alarming
• Annunciator Panel 207 Drop 63, RCP 3 BRG Seal Water Temp High, is alarming
• RCP No. 3 Lower Bearing water temperature is 228°F and rising.
• RCP No. 3 Motor Bearing temperature is 174°F and stable.
• RCP No. 3 Seal Leakoff temperature is 179°F and rising.
• RCP No. 3 Seal Injection Flow is 10 gpm.
Which ONE of the following operator actions MUST be taken based upon these conditions?
a. Manually trip the reactor, Enter 02-OHP 4023.E-0, Reactor Trip or Safety Injection, perform immediate actions, then trip the No. 3 RCP.
b. Initiate reactor shutdown per 02-OHP 4021.001.003, Power Reduction and trip the No. 3 RCP after the reactor is shutdown.
c. Do NOT trip the reactor. Trip the No. 3 RCP and be in Hot Shutdown in 1 hour.
d. Do NOT trip the reactor. Trip the No. 3 RCP and close the No. 1 seal leakoff valve.
a. Correct - The Plant is not analyzed/licensed to operate with less than 4 RCPs. Lower bearing water temperature is > 225°F which requires a trip. The reactor must first be tripped and verified and then the RCP is tripped.
Unit 1 Reactor power is at 50%. The following conditions exist: • PRZ level is stable at program level • QRV-251 Charging Flow Controller is in MANUAL • Charging and letdown are balanced. Which ONE of the following describes the effect on the plant if QRV-251 Charging Flow Controller remains in MANUAL and power is increased to 100%? a. Charging flow will RISE b. Charging flow will LOWER c. PRZ level will LOWER d. PRZ level will RISE
d. Correct - With QRV-251 Charging Flow Controller in Manual Charging flow will remain constant since RCS pressure is constant. As the RCS heats up the Pressurizer Level will rise as the water expands.
Per Technical Specifications, which ONE of the following conditions MEETS the associated MINIMUM requirement for the Borated Water Sources to be considered OPERABLE in Mode 3?
(2-Figure 19.17 Boric Acid Storage Tank Volume is attached)
a. A flowpath to the Centrifugal Charging Pump (CCP) via Boric Acid Flow Control Valve, 2-QRV-421
b. A Boric Acid Storage Tank solution temperature of 64°F.
c. A Boric Acid Storage Tank level of 70%.
d. A Boric Acid Storage Tank boron concentration of 6540 ppm.
b. Correct - Per TS 3.1.2.8 a Minimum solution temperature of 63°F is required for Operability.
During an ATWS event, the fuel cladding fission product barrier is severely challenged.
Which ONE of the following conditions is the mechanism which causes the fuel/cladding challenge?
a. Fuel overheating from DNBR limits being exceeded.
b. High RCS pressure caused by high temperature.
c. Overpower of the fuel/fuel rod.
d. Excessive radial flux distribution.
a. Correct - If the DNBR decreases too far, the possibility exists that fuel damage will occur since the heat energy from the fuel is not efficiently removed.
The control room operators are responding to a SGTR. They have identified and isolated the ruptured S/G.
During the briefing for the initial RCS cooldown, the SRO states that the RCPs should be stopped and natural circulation should be established prior to the cooldown.
The RO states that the RCPs should remain running and forced reactor coolant circulation should be used during the cooldown.
Which ONE of the following identifies which crew member is correct and why?
a. The RO – because forced circulation will reduce susceptibility to pressurized thermal shock and minimize boron dilution concerns.
b. The RO – because with a SG tube rupture, natural circulation conditions will be difficult to establish.
c. The SRO – because once natural circulation is established the ruptured SG will not cooldown and depressurize thereby limiting the total amount of leakage.
d. The SRO – because natural circulation will preclude any damage to the RCP’s and minimize RCS pressure perturbations.
A. Correct - Forced circulation will provide better mixing and a uniform RCS cooldown rate. If the RCPs are stopped the loop flows on natural circulation will be greatly reduced and cold SI water being injected near the isolated SG may collect near the vessel downcomer and lead to a pressurized thermal shock condition.
During performance of 02-OHP-4023-ES-3.1, Post SGTR Cooldown Using Backfill the ruptured steam generator narrow range level was found to be less than 26%. The operators were instructed to refill the steam generator to 62%.
What is the concern with ruptured steam generator level less than required?
a. Uncovering the U-tube could result in an uncontrolled depressurization of the ruptured steam generator causing a reinitiation of the primary to secondary leak.
b. The broken tube could be uncovered allowing steam to flow into the RCS resulting in steam binding of the RCPs.
c. The feed ring could uncover, resulting in a water hammer and aggravating the tube damage whenever AFW is initiated subsequently.
d. SG level must remain in the narrow range, or AFW must be > 25,000 lb/hr to prevent SG dry out.
a. Correct - When SG level is in the narrow range, the steam region in the ruptured SG is insulated from the colder water in the U-Tubes region by a layer of warm water. This maintains SG pressure. If level drops the Steam can condense on the cooler surface of the U-Tubes.
Unit 2 has experienced a steamline break. None of the main steam isolation valves can be closed. 02-OHP-4023-ECA-2.1, “Uncontrolled Depressurization of all Steam Generators,” has been implemented.
Which ONE of the following statements is correct regarding Attachment A, Local SG Isolation?
a. Isolation of both steam supply lines to the TDAFP is allowed, regardless of the status of the other sources of feed flow to the SGs, since no secondary heat sink is intact.
b. Integrity must be restored to all SGs, before the operator can transition to E-2, Faulted Steam Generator Isolation, via the foldout page.
c. Valves are closed one loop at a time in order to restore integrity to at least one SG as early as possible.
d. The Operator is allowed to place the Stop Valve Dump Valve control switches to LOCKOUT only if the selected valve is NOT accessible for local isolation.
c. Correct - Valves are closed one loop at a time in order to ensure a complete, local check of the valves for each SG to restore integrity to at least one SG as early as possible.
Unit 1 has just entered mode 3 following a maintenance outage to replace a leaky fuel assembly. During work on the East RHR pump, an accidental spill causes radiation levels to increase.
The following radiation channels have alarmed:
• ERA-7305 U1 East RHR Pump Room - RED
• VRS-1505 Unit Vent Effluent Low Range Noble Gas - RED
Which ONE of the following is true regarding system operations based on these conditions?
a. The Auxiliary Building Supply fans have automatically tripped.
b. The AES Fan Charcoal Filter has automatically aligned.
c. The AES Fan Charcoal Filter must be manually placed in service.
d. The Auxiliary Building Supply fans must be manually tripped.
c. Correct - If the alarm actuates on the ERA-7300 pump rooms the Operator is required to place the AES Fan Charcoal Filter test Selector Switch to the CHAR FILT position.
During a Large Break LOCA, an evaluation of plant status is made during Step 11 of 01-OHP-4023-E-1, Loss of Reactor or Secondary Coolant. Part of this evaluation includes a check of ECCS pump compartment sump alarms and auxiliary building vent stack and area radiation monitors.
Which ONE of the following reasons describes the BASIS for checking these radiation monitors?
a. Determine if local actions can be performed without excessive personnel exposure.
b. Determine if ECCS leakage exceeds that assumed in the control room dose analysis.
c. Determine if a transition should be made to address a LOCA outside of Containment.
d. Collect current radiation values to assist in Emergency Event classification.
c. Correct - Plant sump alarms and radiation monitors are both checked to identify leakage in the auxiliary building. this check is made to determine if the operator should make a transition to 01-OHP-4023-ECA-1.2, LOCA Outside Containment.
Unit 1 has experienced a Reactor Trip. A Safety Injection was actuated when Pressurizer PORV, NRV-151, opened and did not reclose. Subsequently, the PORV Isolation NMO-151 was closed. The Crew has reset SI and Phase A Containment Isolation and attempted to restore Control Air to Containment by placing control switches for XCR-100, 101, 102, and 103 to the open position.
The following conditions exist:
Indicating Light Green Red
• XCR-100 Control Air Supply Header No. 2 NOT LIT NOT LIT
• XCR-101 Control Air Supply Header No.2 NOT LIT LIT
• XCR-102 Control Air Supply Header No. 1 NOT LIT NOT LIT
• XCR-103 Control Air Supply Header No. 1 NOT LIT LIT
• All Containment Air Pressure Low Alarms - LIT
Which ONE of the following describes the cause of these conditions and the current status of the plant?
a. Phase A has failed to RESET causing a loss of RCS pressure control (PORVs and Sprays won’t open).
b. Power has been lost to Train A Air Supply Valves causing a loss of Letdown.
c. Power has been lost to Train B Air Supply Valves causing a loss of Seal Injection.
d. An air leak inside containment has caused isolation of Air Supply valves causing a loss of CCW to the RCPs.
b. Correct - The Letdown line is isolated by air inside containment operated valves QRV-111, 112, 160, 161, and 162.
Which ONE of the following states the reason for depressurizing all intact steam generators as directed by OHP 4023-FR-C.1, Response to Inadequate Core Cooling?
a. Allow more feedwater into the steam generators to enhance Natural Circulation.
b. Inject a sufficient quantity of borated water to provide adequate shutdown margin.
c. Allow the SI Accumulators and the RHR system to inject water into the core.
d. Establish sufficient subcooling to maximize Natural Circulation flow.
c. Correct - The rapid depressurization of the secondary is the most efficient way to reduce primary pressure. Since the High head ECCS pumps are not injecting the attempt is made to lower pressure and inject the Accumulators and allow RHR pumps to inject.
Unit 1 was operating at 100% power. The West CCP had been tagged out due to a bearing failure.
The following sequence of events occurs:
• A reactor trip and safety injection occurs in response to a Steam Generator Tube Rupture.
• SI is reset.
• The T11D, 4kV AC ESF Bus subsequently loses normal power but is re-energized by the T11D Emergency Diesel Generator.
• T11D Automatic load sequencing is complete.
Which ONE of the following statements correctly describes the status the East CCP?
The East CCP …
a. has tripped and automatically restarted.
b. was NOT affected by the loss of Bus T11D.
c. has tripped and may be manually started immediately.
d. has tripped and may NOT be manually started until the load conservation signal resets.
c. Correct - The ECCS timer and SI signals are the only auto starts for the CCPs. The pumps will NOT automatically start following a load shed. The East CCP is powered from T11D while the West CCP is powered from T11A.
Hydrogen is supplied to the Volume Control Tank (VCT).
This design feature of the CVCS system is provided to …
a. lower iodine levels in the RCS.
b. control the pH in the RCS.
c. increase demineralizer efficiency for corrosion products.
d. minimize oxygen in the RCS.
d. Correct - Hydrogen is used to scavenge dissolved oxygen from the RCS.
During implementation of 02-OHP-4023-FR-Z.1, Response to High Containment Pressure, the operators are directed to check for 02-OHP-4023-ECA-1.1, Loss of Emergency Coolant Recirculation, actions NOT in effect.
The reason for this verification is that in procedure 02-OHP-4023-ECA-1.1:
a. the initiation of RHR spray is performed prior to 50 minutes following the event to aid in reducing containment pressure.
b. containment pressure is allowed to rise slightly to account for reduced operation of containment spray pumps.
c. containment pressure is allowed to rise to 12 psig with NO containment spray pumps operating.
d. the steam generators are NOT isolated even if faulted to allow for additional RCS cooldown.
b. Correct - Procedure 02-OHP-4023-ECA-1.1 uses less restrictive criteria, which permits reduced spray pump operation depending on RWST level and containment pressure. This is done to conserve RWST inventory.
Unit 2 was operating at 100% power
The following alarms are received:
• Panel 204
• Drop 88 - West CCW Surge Tank LVL HI OR LOW
• Drop 98 - East CCW Surge Tank LVL HI OR LOW
• Panel 207
• Drop 7, RCP #1 Thermal Barrier Clg Wtr D/P High
• Drop 8, RCP #1 Thermal Barrier Clg Wtr Temp High
• Drop 9, RCP #1 Thermal Barrier DP Low
• Panel 238
• Drop 10, R-17A East CCW Header High Radiation
Which ONE of the following statements is the required action and why? The required actions are to verify CCW vent (2-CRV-412) shut, notify Chem. Lab and RP of high activity, and…
a. trip the reactor and #21 RCP then enter E-0 since the #1 RCP seal has failed.
b. monitor RCP Bearing temperatures since CCW lines in containment have ruptured.
c. close RCP thermal barrier valves (2-CCM-453 and 454) since the #21 RCP thermal barrier has failed.
d. remove letdown from service and place excess letdown in service since the letdown heat exchanger has failed.
c. Correct - Panel 207 Drops 7, 8, & 9 indicate a failure of the RCP Thermal Barrier. These alarms along with the others (Surge tank level and radiation) indicate the need to close the CCW from RCP Thermal Barrier Valves as per 02-OHP-4022-016-003 steps 1 & 2.
A steamline break has occurred on Unit 1 SG #11. The break was isolated and Safety Injection (SI) has just been terminated.
The following plant conditions exist:
• East CCP aligned to VCT with normal charging and letdown in service
• SI and RHR pumps shutdown
• RCPs are stopped
• Pressurizer pressure = 1800 psig and rising
• Pressurizer level = 64% and rising
• RCS Core Exit temperature = 503°F and rising
• Containment pressure = 0.1 psi
SG 11 12 13 14
• Levels (NR) 0% 13% 20% 20%
• Pressures (psig) 0 825 830 830
Which ONE of the following actions are required for plant recovery and why?
a. Open SG PORVs to stabilize the heatup to prevent pressurizer overfill.
b. Raise Charging flow to raise the Pressurizer level to 82% to enable RCP start.
c. Reinitiate High Head SI flow to stop the heatup.
d. Close SG PORVs to allow plant to return to normal temperature and pressure.
a. Correct - Opening the SG PORVs will stabilize the plant heatup and limit the rise in PRZ level (due to RCS expansion).
The crew has entered OHP-4023-FR-C-2, Response to Degraded Core Cooling.
The following conditions exist:
• RCS Hot Leg Temperatures are 300°F.
• RVLIS NR indications are 37%.
Which ONE of the following would be most effective in restoring core cooling?
a. Depressurizing SGs to Atmospheric Pressure.
b. Aligning BIT flow from the Opposite Unit.
c. Starting a Residual Heat Removal Pump.
d. Starting a Reactor Coolant Pump.
c. Correct - An RHR pump will provide the greatest injection flow to restore inventory and thus will restore core cooling. At this temperature with the RCS Saturated, pressure will be less than 60 psig resulting in ~3000 gpm from the RHR pump.
The following conditions exist:
• Reactor has tripped from 100% power due to a loss of off-site power.
• Natural circulation has been verified.
Which ONE of the following describes the response of core Delta-T if the plant remains in hot standby?
a. Delta T will lower due to the smaller heat generation over time.
b. Delta T will rise as the water in the SGs heats up.
c. Delta T will rise due to lack of cooling to the upper vessel head.
d. Delta T will lower due to the addition of cold AFW to the SGs.
a. Correct - Decay heat production lowers over time. Delta T across the core is determined by the temperature cold leg temperature and the temperature of the fluid exiting the core. Since the fluid exiting the core is subjected to less heating the DT will lower.
A Loss of Off-Site Power has occurred on Unit 2. The crew is performing the actions of 02-OHP-4023-ES-0.2, Natural Circulation Cooldown.
The following conditions exist:
• RCS temperature is 527°F and trending down at approximately 20°F per hour
• RCS pressure is 1850 psig and trending down slowly
• 2-QRV-251, Charging Flow Control Valve, is fully open
• Pressurizer level is 4% and trending down slowly
• High Steam Flow and Low Pressurizer Pressure SI signals are BLOCKED
Which ONE of the following describes the correct action(s) for these conditions?
a. Actuate Safety Injection and return to 02-OHP-4023-E-0, Reactor Trip or Safety Injection.
b. Transition to 02-OHP-4023-ES-0.3, Natural Circulation Cooldown with a Steam Void in the Vessel.
c. Throttle closed the steam dumps to allow RCS temperature to stabilize IAW 02-OHP-4023-ES-0.2, Natural Circulation Cooldown.
d. Operate SI pumps as necessary to maintain RCS inventory and avoid overfilling the pressurizer IAW 02-OHP-4023-ES-0.2, Natural Circulation Cooldown.
a. Correct - 02-OHP-4023-ES-0.2 Foldout page directs this action when pressurizer level cannot be maintained at >5%
A LOCA is in progress and both recirculation sump suction valves (ICM 305 and ICM 306) failed to open while transferring to cold leg recirculation. The crew is currently at step 12.b. RNO of OHP-4023-ECA-1-1, Loss of Emergency Coolant Recirculation.
This step directs the crew to establish minimum ECCS flow to remove decay heat per Figure 1. This is to be accomplished by manually aligning ECCS pumps and throttling BIT discharge to cold leg valves as necessary.
The following conditions exist:
• RWST level is 18% and lowering.
• East CCP, South SI & West RHR pumps are running.
• RCS Pressure is 340 psig.
• Minimum ECCS Flow Required per Figure 1 is 280 gpm.
Which ONE of the following describes how this flow will be established?
a. Shutdown RHR Pump and throttle BIT to 280 gpm of combined CCP and SI pump flow.
b. Shutdown CCP and SI Pumps. RHR pump flow should be about 280 gpm at this pressure.
c. Shutdown SI and RHR Pumps. CCP flow should be about 280 gpm at this pressure without throttling the BIT.
d. Shutdown SI and RHR Pumps and throttle BIT to 280 gpm of CCP flow.
d. Correct - The RHR is shutdown because it is not expected to be delivering flow at this pressure. The SI pump is shutdown because its flow at this pressure would be about 700 gpm. CCP flow at this pressure would be about 550 gpm and so the BIT Valves must be throttled.
While responding to a LOCA, a transition to OHP-4023-ECA-1.1, Loss of Emergency Coolant Recirculation, was performed due to a loss of emergency coolant recirculation.
The following conditions exist:
• RWST level is 18% and lowering.
• Containment Pressure is 2.5 psig
• All ECCS pumps are running.
• Both CTS pumps were stopped.
• RCS Pressure is 940 psig.
Make up is being added to the RWST and ECCS is reduced to one train of SI flow.
What are these actions designed to do?
a. Restore RWST level so Containment Spray can be started.
b. Prevent damage to vital equipment by saving one ECCS train.
c. Establish conditions to allow restart of RCPs.
d. Delay the time to RWST depletion.
d. Correct - Makeup is added to the RWST to extend time the ECCS pumps can take suction from the RWST and supply core cooling. Reducing to one train of ECCS flow (1 CCP, SI, & RHR) delays the time to RWST depletion.