2006 NRC Flashcards
(99 cards)
Rod Control was in AUTO with Unit 1 power at 79% when MPC-253, Turbine Impulse Pressure Channel 1, failed low. The crew determined that a Turbine Runback was NOT in progress and placed rod control in Manual.
Which ONE of the following actions are required to “Restore Equilibrium Conditions” in accordance with 01-OHP-4022-012-003, Continuous Control Bank Movement
a. Initiate boration
b. Reduce Turbine Load
c. Insert Control Rods
d. Initiate dilution
b. Correct – Per 01-OHP-4022-012-003, Continuous Control Bank Movement, a reduction in steam demand is the prefered method to restore Tave to Tref. The failure of MPC-253 would have caused the control Rods to Insert (Tref lowered)
During a power accension, with reactor power at 48%, control Bank C - Group 1 rod B-8 drops. Prior to the drop it was at 230 steps. While restoring the rod, control rod urgent failure alarm occurs.
Which one of the following explains why the alarm actuated?
a. All other Bank C - Group 1 rod lift coil disconnect switches are open
b. All Bank C - Group 2 rod lift coil disconnect switches are open
c. The step counter of the pulse to analog (P/A) converter was not reset to 0
d. Group C rod moving with group D rods withdrawn
b. Correct – Since the dropped rod is completely inserted, the lift coil disconnect switches for all operable rods within the affected bank are opened. An Urgent failure will occur when the misaligned rod begins to move. This is caused by the non-movement of the group without the misaligned rod
During power escalation of Unit 2, a single rod in Control Bank D is misaligned. Procedure OHP 4022.012.005, Dropped Or Misaligned Rod is being performed. A CAUTION prior to step #2 requires that any required power reductions must be accomplished using boration rather than control rods.
The purpose of this requirement is to prevent:
a. Moving the control rods until a failure analysis can be initiated.
b. Another rod failure until the cause of the initial failure can be identified.
c. Exaggerating any existing flux tilts.
d. Exceeding Rod Insertion Limits during the power reduction.
c. Correct - With a single misaligned rod, flux tilts could develop across the core. Further movement of the rods could cause a greater tilt and subsequent oscillations.
The following plant conditions exist:
• A Reactor trip from 100% power has occurred on Unit 2.
• 2-OHP-4023-E-0, Reactor Trip Or Safety Injection, is being implemented.
• Containment pressure is 0.6 psig and stable.
• SG NR Levels are offscale low.
• RCS pressure is 2150 psig and lowering.
• Control Rod H-8 is indicating 32 steps.
• All systems responded normally to actuation signals.
Which ONE of the following actions would be taken?
a. Transition to 02-OHP-4023-ES-0-1, Reactor Trip Response, and initiate boration for a stuck rod.
b. Transition to 02-OHP-4023-ES-0-1, Reactor Trip Response. Rod H-8 condition is expected so boration is not required for a stuck rod.
c. Initiate Safety Injection and continue with 02-OHP-4023-E-0, Reactor Trip Or Safety Injection, as pressurizer pressure is too low.
d. Initiate Safety Injection and continue with 02-OHP-4023-E-0, Reactor Trip Or Safety Injection, as Steam Generator levels are too low.
a. Transition to 02-OHP-4023-ES-0-1, Reactor Trip Response, and initiate boration for a stuck rod.
* Procedural changed occurred after this exam. Requirement is currently <10 steps on all rods for both units.
Which ONE of the following correctly describes the plant response if the listed instrument fails HIGH while in the LTOP mode?
a. RVLIS Wide Range pressure instrument NPS-110 will cause PORV NRV-153 to OPEN.
b. RVLIS Wide Range pressure instrument NPS-110 will cause PORV NRV-152 to OPEN.
c. Wide Range RCS pressure instrument NPS-121 will cause PORV NRV-153 to OPEN.
d. Wide Range RCS pressure instrument NPS-121 will cause PORV NRV-152 to OPEN.
c. Correct - Pressurizer PORV NRV-153 will open if NPS-121 fails open.
Which of the following is the basis for establishing / maintaining S/G Narrow Range level between 27%-50% (non-adverse containment) for small or intermediate LOCA’s?
a. Maintains a static head of water to reduce any existing S/G tube leakage.
b. Ensures adequate feed flow or S/G inventory to ensure a secondary heat sink.
c. A RCP may have to be started if 02-OHP-4023-FR-C.1 is entered later in the event.
d. Maintains the water level above the top of the U-tubes to prevent depressurizing S/G.
b. Correct - E-1 Basis Document states the purpose of establishing 27% level is to ensure adequate feed flow or S/G inventory to maintain a secondary heat sink for small or intermediate size LOCAs and secondary break accidents. 50% is the S/G narrow range upper control band limit.
- U2 is 27-50%
- U1 is 20-50%
Unit 2 Reactor Startup is in progress with Reactor Power at 2% and rising.
The following conditions exist:
• RCP No. 3 Lower Bearing water temperature is 208°F and stable.
• RCP No. 3 Motor Bearing temperature is 187°F and stable.
• RCP No. 3 Seal Leakoff temperature is 179°F and stable.
• RCP No. 3 Motor Temperature is 148°C and rising.
• Annunciator 107 Drop 40, RCP Motor Overheated - LIT
Which ONE of the following operator actions MUST be taken based upon these conditions?
a. Do NOT trip the reactor. Trip the No. 3 RCP. Power must be maintained less than 5% (Mode 2).
b. Initiate reactor shutdown per 02 OHP 4021.001.003, Power Reduction and trip the No. 3 RCP within 8 Hours.
c. Manually trip the reactor, Enter 02 OHP 4023.E 0, Reactor Trip or Safety Injection, perform immediate actions, then trip the No. 3 RCP.
d. Immediately Trip the No. 3 RCP. Initiate reactor shutdown per 02 OHP 4021.001.003, Power Reduction and be in Mode 3 within 6 Hours.
b. Initiate reactor shutdown per 02 OHP 4021.001.003, Power Reduction and trip the No. 3 RCP within 8 Hours.
With 120 gpm letdown in service and blender controls in automatic on Unit 1, the VCT level transmitter QLC-452 fails to 100%.
With NO operator action, actual VCT level will:
a. lower to 2.5% and RWST swapover will occur automatically.
b. lower to 14% and stabilize due to auto makeup flow.
c. lower to zero and eventually result in loss of CCP suction.
d. rise to 87% and stabilize due to full divert flow.
c. Correct – A Failure of QLC-452 high will cause Letdown to divert to the HUT. Auto VCT makeup will attempt to control VCT level between 14 and 24% (Makeup will not keep up with 120 gpm letdown). Eventually the VCT level will lower to the RWST switchover setpoint. With 452 failed high, the coincidence for switchover will not be made up and level will continue lowering to 0%. At this time suction will be lost to the charging pumps and they will trip.
The following Unit 2 conditions exist:
• The unit is in MODE 5 at 150oF with the RCS intact.
• Both trains of RHR are available, with the 2 West RHR train is in operation.
• Both PORVs are lined up for LTOP mode of operation.
• The West CCP and Both SI pumps are Tagged out.
Due to indication of cavitation on 2 West RHR Pump, the crew enters 02-OHP-4022-017-001, Loss of RHR Cooling.
Per the procedure, the crew isolates both trains of RHR by placing both RHR pumps in Pull-to-Lock and closes RHR suction valves IMO-128 and ICM-129.
How does this action affect the Technical Specification operability of Overpressure Protection Systems?
a. Technical Specification requirements are met. Both PORVs are available for overpressure control.
b. Technical Specification requirements are NOT met. The RHR suction relief must be available for overpressure protection.
c. Technical Specification requirements are NOT met. The Charging Pump must be Isolated/ Tagged -Out.
d. Technical Specification requirements are met. Isolating RHR suction valves does not affect operability of the RHR suction relief.
a. Correct – Tech. Spec requirements are met. Both PORVs are available for overpressure control. T.S. 3.4.12 requires 2 overpressure protection flowpaths, whether both PORVs a PORV and RHR suction relief. Closing the RHR suction valves isolates the RHR suction reliefs, but the PORVs are still available.
The following plant conditions exist:
• RCS pressure is 1600 psig and lowering
• Pressurizer is empty
• Containment pressure is stable at 1.5 psig
You have been directed to close 2-WMO-734, ESW outlet valve for CCW HX 2 East.
What actions; if any, must be taken to close the valve?
a. The valve control switch must be put in pull-to-stop and must be closed locally.
b. When the valve reaches its preset position you can close the valve using the control switch.
c. No action is necessary, the valve has already been closed by an automatic signal.
d. SI must be reset to close the valve using the control switch.
b. Correct – The valve can be closed by holding the control switch to close after it has reached its throttle position.
Three-position control switches in control room
CLOSE – Closes valve
PULL TO STOP – No longer needed since modified to hold-to-operate
OPEN – Opens valve
The listed plant conditions indicate an SI so the valve will automatically move to preset intermediate position on receipt of an SI signal corresponding to an approximate flow rate of 5000 gpm.
Assume that the Pressurizer master pressure controller output were failed AS IS just before a large, rapid secondary load rejection.
Which of the following would occur naturally in the Pressurizer to limit the magnitude of the resulting pressure transient on the primary system?
a. An outsurge causes the steam space to expand in the PRZ. This allows some liquid to flash to steam and limits the resulting pressure drop in the RCS.
b. An insurge of hotter water heats the Pzr. More liquid then flashes to steam helping to limit the resulting pressure drop in the RCS.
c. An insurge of cooler water compresses the steam space in the Pzr. Steam is condensed to water helping to limit the overall pressure increase in the RCS.
d. An outsurge cools the Pzr. This allows some steam to condense to water and limits the resulting pressure increase in the RCS.
c. Correct - A secondary load rejection will cause RCS temperature to rise. Pressurizer pressure will initially follow the level trend. As Tavg initially increases, level will increase causing an insurge which causes pressure to rise. Since the water from the insurge is cooler than the pressurizer liquid, steam is condensed to water helping to limit the overall pressure increase in the RCS.
The following plant conditions exist:
• Unit 1 has experienced an Anticipated Transient Without Scram (ATWS), and has implemented 01-OHP-4023-FR-S.1, Response to Nuclear Power Generation/ATWS.
• 1-QMO-410, emergency boration to CCP suction valve will NOT OPEN.
• SI has been initiated.
Which one of the following identifies the correct actions and reason to satisfy 01-OHP-4023-FR-S.1 Step 5, Initiate Emergency Boration Of RCS?
a. 1) Open at least one CCP suction from RWST valve: 1-IMO-910 -OR- 1-IMO-911
2) Close at least one CCP suction from VCT valve: 1-QMO-451 -OR-1-QMO-452
3) Maximize charging flow.
4) Verify letdown flow established.
This ensures at least 70 gpm of Borated RWST water is injected through the Normal Charging flowpath.
b. 1) Open both boration valves: 1-QRV-400 -AND- 1-QRV-421
2) Start both boric acid transfer pumps in FAST speed.
This ensures at least 36 gpm of Borated BAST water is injected through the Normal Charging flowpath.
c. 1) Open at least one of the boration valves: 1-QRV-400 -OR- 1-QRV-421
2) Start both boric acid transfer pumps in FAST speed.
This ensures at least 36 gpm of Borated BAST water is injected through the Normal Charging flowpath.
d. 1.) Verify Pressurizer Pressure is <2335 psig.
This ensures at least 70 gpm of Borated RWST water is injected through the BIT injection lines.
d. Correct - On a Safety Injection, Both CCPs start, IMO-910 & 911 Open, and the BIT Injection Lines Open providing RWST injection to the RCS. Step 5b RNO has the Operator go to step 5c which checks Pressurizer pressure if a SI is actuated.
The following plant conditions exist:
• Ann. 205, Drop 28, SFP Temp High - LIT.
• South (U2) SFP pump out for maintenance.
• South SFP Hx is available for use.
• North SFP Hx shell develops a large leak requiring Hx to be isolated.
Procedure 12-OHP-4022-018-001, Loss of Spent Fuel Pit Cooling allows cross-tie of the North SFP Pump through a 3” line to the South SFP Hx.
This action will…
a. maintain the SFP temperature at normal conditions until repairs are made.
b. prevent the SFP from boiling, but result in operation at elevated temperature.
c. prevent the SFP from boiling if used in conjunction with 125 gpm makeup.
d. extend the time to SFP boiling to allow time for repair of system.
d. Cross tying the North Pump through the 3” line to the South HX will delay the time to boiling but will not prevent boiling unless makeup flow of 175 gpm is also used.
During power operation, SG tube leakage was detected and estimated at 100 gpm when RCS pressure was 2200 psig and SG pressure was 800 psig. The plant was shutdown and a cooldown initiated.
Which ONE of the following is the approximate current leak rate if RCS pressure is 1350 psig and SG pressure is 1000 psig? Assume the break size has not changed.
a. Approximately 25 gpm
b. Approximately 50 gpm
c. Approximately 75 gpm
d. equal to the initial leak rate of 100 gpm
b. Correct - Break flow is Proportional to the Square Root of the Pressure Differential.
Flowint ∝ sqrt(2200 − 800 )
Flowfinal ∝ sqrt(1350−1000)
Flow is 50% of initial or 50 gpm
The following plant conditions exist:
• A loss of all FW and AFW has occurred.
• The operating crew has entered FR-H.1, Loss Of Secondary Heat Sink.
• The RO identifies that the East CCP has tripped and that the West CCP will NOT Start.
Which one of the following describes the consequences of the CCP failures?
a. RCS Bleed and Feed cooling must be established immediately to ensure sufficient SI flow.
b. A Red Path on the Core Cooling Critical Safety Function will develop due to loss of RCS inventory with no available makeup.
c. The RCS will not depressurize quickly enough to ensure sufficient SI flow to provide RCS heat removal, so other RCS openings will have to be established.
d. RCS Bleed and Feed cooling must NOT be initiated and secondary depressurization to inject condensate pump flow must be immediately initiated.
a. Correct - Step 2 of OHP-4023-FR-H.1 requires that Bleed and Feed be initiated immediately initiated if the CCPs are not available. If it is known that no CCP is available for bleed and feed, then all RCPs are stopped and bleed and feed is initiated immediately. The RCS will have to depressurize below the shutoff head of the SI pumps before any ECCS injection will occur, so the bleed and feed must be initiated prior to the loss of heat removal capability of the SGs.
The plant has experienced a Loss of All Offsite AC and only the 2AB EDG is operating. Due to the Loss of Power, the PPC is not available.
What contingency action is taken to compensate for the unavailability of the PPC?
a. Emergency Response Data System (ERDS) is activated.
b. Safety Parameter Display System (SPDS) is transmitted to the NRC.
c. PMP-2080-EPP-100 Data sheet 1, Technical Information sheet, is completed every 15 minutes.
d. PMP-2080-EPP-100 Data sheet 4, Plant Status sheet, is completed every 60 minutes.
c. Correct - Upon loss of the PPC and/or EDR the PMP-2080-EPP-100 Data sheet 1, Technical Information sheet, is completed every 15 minutes and sent to applicable facilities.
Unit 2 was operating at 100% power when a reactor trip occurred due to a loss of offsite power. The operators completed the actions of 02-OHP-4023-ES-0.1, Reactor Trip Response, and have transitioned to 02-OHP-4023-ES-0.2, Natural Circulation Cooldown, where they are initiating a natural circulation cooldown.
At the onset of the natural circulation cooldown, which ONE of the following processes will remove the MOST heat from the Reactor Vessel HEAD?
a. All CRDM fans running.
b. Upper head bypass flow.
c. Heat losses to ambient.
d. The 25 F/hr natural circulation cooldown of the RCS.
a. Correct - CRDM fan operation results in a considerable amount of heat removal from the upper head region. The results from several tests at domestic and foreign plants indicate that the Control Rod Drive Mechanism (CRDM) cooling fans aid significantly in removing heat from the upper head area. At 600°F this will result in a cooldown rate of the upper head of approximately 21°F/hr.
The following plant conditions exist:
• Unit 1 is in Mode 5
• Unit 2 is in Mode 6.
• Unit 2 Core offload is currently underway.
• The protected train is A. All equipment needed for a proper protected train alignment is available.
• DC bus 2AB is deenergized for maintenance.
• DC bus 2CD deenergizes due to equipment failure.
What action must occur due to the deenergized bus?
a. Immediately suspend core alterations and movement of irradiated fuel.
b. Immediately suspend core alterations. Fuel movement may continue in the Auxiliary Building.
c. Re-energize DC bus 2AB or 2CD within 2 hours, or declare the Unit 1 ESW system inoperable.
d. Re-energize DC bus 2AB or 2CD within 2 hours, or suspend core alterations and movement of irradiated fuel.
a. Correct - Technical Specification 3.8.5 requires one DC train to be OPERABLE. Immediate suspension of all core alterations fuel movement is required if both are lost.
Which of the following is the expected response to a High Radiation Signal on the ERS-7401 Unit 1 Control Room Area Radiation Monitor?
a. Only the Unit 1 East and West Pressurization fans start and Dampers align.
b. Either the Unit 1 East -OR- West Pressurization fan starts and Dampers align depending on which Control Room Air Handling Unit is in Service.
c. Only the Unit 1 and Unit 2 East Pressurization fans start and Dampers align.
d. Both the Unit 1 and Unit 2 East and West Pressurization fans start and Dampers align.
a. Correct - 12-OHP-4024-139 drop #12 states that both the East and West Pressurization fans will start and the associated dampers align.
Unit 1 is operating at 100%, steady state condition, when Annunciator Panel 118, Drop 84, ESW PIPE TUNNEL SUMP LEVEL HI-HI, alarm is received. East ESW supply and return flows indicate an abnormal high differential.
Unit 2 has reported that 02-OHP-4022-019-001, ESW SYSTEM LOSS/RUPTURE has been implemented.
What action(s) would be taken by BOTH Unit control room operators?
a. Align alternate ESW cooling to non affected diesel generators.
b. Stop affected header ESW pumps.
c. Place associated diesel generators in tripped condition.
d. Close affected header unit crosstie valves.
d. Correct - When ESW supply and return flows indicate an abnormal high differential both units are directed to isolate the affected header unit crosstie valves.
The control room has been evacuated per 02-OHP-4025-001-001, Emergency Remote Shutdown. The crew has performed 02-OHP-4025-LS-6-1, Seal Injection from CVCS Cross-Tie and 02-OHP-4025-LS-6-3, BIT Injection alignment.
Which ONE of the following describes the source and method of monitoring borated water addition?
Prior to aligning RHR for shutdown cooling, RCS boration is accomplished by . . .
a. manually aligning Unit 1 Boric Acid makeup to feed Unit 2 through the crosstie. Flow is tracked by Unit 1 Boric Acid flow recorder.
b. locally aligning Unit 2 Boric Acid makeup to feed Unit 2 through the crosstie. Flow is tracked by Boric Acid Flow indicator on the Local Instrument Panel.
c. manually aligning Unit 1 CCP suction to the RWST to feed Unit 2 through the crosstie. Flow is tracked by the sum of local seal injection flows and the Unit 1/2 CCP Crosstie Flow indicator.
d. manually aligning Unit 1 CCP suction to the RWST to feed Unit 2 through the crosstie. Flow is tracked by the Unit 1/2 CCP Crosstie Flow indicator.
d. Correct - Prior to initiating the Unit Crosstie, Unit 1 is directed to trip the unit and align CCP suction to the RWST. The Total flow from Unit 1 to Unit 2 is indicated on the Unit ½ CCP Crosstie Flow indicator.
Which ONE of the following conditions would require an LCO Action Statement entry for Technical Specification Section 3.6, Containment Systems?
a. While in MODE 1, an electrician opens the outer airlock door at the lower containment access without prior approval.
b. While in MODE 3, Containment internal pressure is found to be -0.5 psig prior to placing Containment Purge in service.
c. While in MODE 4, The outer airlock door interlock is discovered to be non-functional.
d. While in MODE 5, during performance of the Overall Integrated Containment Leakage Rate Test, Containment leakage exceeds the maximum allowable Technical Specification leakage rates.
c. Correct - The airlock door interlocks are required to be operable in Modes 1 - 4 per T.S. 3.6.2.
Unit 2 experienced a reactor trip from 100% power. The operators have transitioned from 02-OHP-4023-E-0 Reactor Trip or Safety Injection to 02-OHP-4023-ES-0.1 Reactor Trip Response.
• ERA-8309, Reactor Coolant Filter Room has a high alarm.
• ERA-8303, East CCP Room shows a rising trend, but has yet to alarm.
• The SRO implements 2-OHP-4022-002-019, High Reactor Coolant Activity or Failed Fuel.
Which ONE of the following describes the correct actions to take with the CVCS system and the basis for these actions?
a. Charging and Letdown are isolated to contain the high radioactivity within the containment building.
b. Letdown is diverted to the CVCS HUT to limit radiation levels in the charging pump area.
c. Charging and Letdown are maximized through the letdown demineralizers to maximize clean up.
d. Excess Letdown is placed in service through the letdown demineralizers to maximize clean up.
c. Correct - 12-OHP-4022-002-019 directs the operator to verify Letdown lineup and maximize letdown flow to help reduce RCS Activity.
The following conditions exist:
• A plant startup is in progress.
• Reactor power is 25%.
• All control systems are in AUTOMATIC.
• Control Bank D rods are at 150 steps.
The lower detector for power range nuclear instrument channel N41 fails HIGH, causing channel total power indication to increase to 70%.
Assuming no operator action is taken, what will be the response of the rod control system?
a. Rods will not move.
b. Rods will drive all the way in.
c. Rods will drive in some distance then stop.
d. Rods will insert, and then withdraw.
d. Correct - When N41 fails high, the rate circuit will sense that Reactor power is rising faster than Turbine power, and will send a signal to insert rods. After the rate of change signal has had time to decay away the Tave deviation generated (by inserting rods) will cause the rods to withdraw.