Building Contracts - Bespoke & JCT Flashcards
What are the various forms of sub-contract commonly used?
- JCT (Joint Contracts Tribunal)
- NEC (New Engineering Contract)
- FIDIC
- Bespoke
What are some considerations when selecting the most appropriate form of contract?
Nature of client
Cost, time, quality and risk allocation
Procurement choice
Value of work
Complexity of work
Size and location of work
What is a bespoke contract?
They are tailor made to fit specific requirements of a project and often used when standard contracts are not suitable.
What are the advantages of a bespoke contract?
- Written by legal experts
- Rights and obligations of each party clearly set out
- Parties should be more-so familiar with the provisions of the form
What are the dis-advantages of a bespoke contract?
- Familiarity is decreased
- Expensive to draft
- Poorly drafted could lead to ambiguities
- Clauses or provisions may be untested in court.
Have you amended a standard form of contract?
No. As consultants we do not have legal training and all amendments should be carried out by the legal team.
What does JCT stand for?
Joint Court Tribunal
What types of JCT are available to you?
o D&B
o SBC 2016
o Major Works Contract
o Minor Works Contract
o Intermediate Build Contract
What key project characteristics influence which JCT contract is used?
- Size, value and type
- Need for contractor design
- Certainty on final cost
- employer experience
- Programme requirements
When would you use a minor works contract?
For smaller, basic construction project procured via the traditional method.
Tell me about the JCT minor works contract
For small basic projects, non complex
Employer responsible for design
Normally administered by architect or contract administrator
When would you use a JCT intermediate contract?
Designed for projects involving all recognised trades and skills where detailed contract provisions are needed for complex specialist work.
For contracts via the traditional method.
When would you use the JCT SBC?
For large complex projects
Employer responsible for design
Works can be carried out in sections.
For contracts via the traditional method.
When would you use a JCT major project contract?
Designed for large scale, major projects.
for contracts via the D&B method
Works are carried out by the contractors with experience and the ability to take greater risk
When would you use a JCT D&B?
Designed for projects where contractor undertakes design and build. Where Contractor takes all the risk and quality only as good as the employers’ requirements. Is quick and cost certain, can be carried out in sections.
When would you use a JCT Prime Cost?
Projects that require an early start on site
Design documents are not completed and wont be until work commenced.
suitable for projects using cost reimbursable or cost plus.
When would you use a JCT Construction management contract?
Employer appoints separate trade contractors and a construction manager to oversee works for a fee.
Suitable for projects via the management method.
What is a relevant event?
- An event, on or off site which causes delay to the completion date.
o These are variations or instructions
o Strike
o Terrorism
o Suspension by contractor for non-payment
o Force Majeure.
What happens when a relevant event occurs?
- As soon as the contractor notices a delay will occur, contractor must notify the Administrator in writing with clear substantiation with estimate of delay and why etc.
- Contractor administrator must respond within 12 weeks.
- If it has occurred, the contract administrator must assess the delay and issue a new completion date or EOT.
What is force majeure?
- Something which happens which is out of our control
o War, riot, terrorism acts, contamination, civil war, bad weather etc.
Under a relevant event, is the contractor entitled to loss and expense?
- No, a claim to an extension of time only
- Contractor will need to demonstrate loss and expense.
What is a relevant matter?
- A matter which the employer is responsible for.
- Effects the progress of the works
- May entitle the contractor to loss and expense.
Example of relevant matter?
- Failure to give the contractor possession of the site
- Delays in receiving instructions
- Disruption caused by work carried out by employer
What is a loss and expense claim?
Associated with delays but can be for any event where contractor incurs a loss due to the failure of the employer (Relevant matter)