Technical Competency Questions - TARGETTED Flashcards
(224 cards)
How would you define fair and reasonable?
I would believe it would be considered by most people to be reasonable, right, or normal.
How would you financially manage sub-contractors/what techniques would you use?
- Payments
- EWNs
- Payment on time
- Contra-charges/levying costs
- Retention.
- Agreeing variations and claims when they occur
- Identify future variations as and when they occur,.
What did a Pay-Less notice used to be called?
- A withholding notice
Can you tell me about the Housing Grants, Construction and Re-Generation Act?
- is intended to ensure that payments are made promptly throughout the supply chain and that disputes are resolved swiftly.
- It includes the right to adjudication, right to suspend performance, etc.
What is the government payment charter?
NOW AMENDED: JAN 22 -
PAYMENT REPORTING REGULATIONS:
Sets out fair payment commitments for organisations in the construction industry to sign up and agree to. - All large contractors should follow the Construction Supply Chain Payment Charter. Now called the ‘Payment Reporting Regulations’ – changed in Jan 22. - This sets out fair payment commitments for companies and LLP’s - Public authorities are already required to pay within 30 calendar days. On central Government contracts, payment will be made to: - Tier 1 within 14 days, - Tier 2 within 19 days - Tier 3 within 23 days of the due date, which will be 7 days after the common assessment or valuation date established by the client in the Tier 1 contract.
Can you tell me about the Scheme for Construction Contracts?
- is a scheme which applies when construction contracts do not comply with the Housing Grants, Construction and Regeneration Act.
What are the components that make up the cost of a project to a contractor?
- Profits and overhead – staff, labour, materials, access equipment, prelims
How often do you report cost?
- Monthly however, we continually update the CVR when changes arise.
What is a cash flow forecast?
- A cash flow shows how much money the business or project expects to receive and pay out over a set period.
How do you use a cash flow?
- I use a cash flow by understanding what we’ve been certified from the client, how much money we have in the bank and then review what our sub-contractors have applied for and what else is to be paid (plant, material & labour etc). This helps me to understand what accruals I need to make
How do you manage risk and contingency?
- I manage risk by keeping a risk register and keeping this as a working document.
- Consistently having meetings with the engineers to understand the risks around and the contingency which has been allocated or removed.
What is CVR?
Cost Value Reconciliation
- Is the profit and loss statement for a project.
- Helps calculate the amount of work done to date and the cost incurred to date.
- It is the difference being the amount of profit or loss made at that point in time.
How can you calculate works completed to date?
- Visit site, carry out assessment and see what’s been done in line with what’s being claimed within a period
How do you know what costs you’ve incurred to date?
- By looking at what we’ve been charged for by a subcontractor or a supplier
- What we’ve paid out for in terms of material
What is the purpose of change control?
- Change control has three purposes:
1. All relevant parties are consulted
2. Enables change to be assessed in terms of time, quality and cost.
3. A record is formed to note any change.
What is EVA (Earned Value Analysis?)
- Is a method of measuring the projects progress at any given time.
- Forecasting it’s completion date and final cost
- Analyses the variance in the schedule and budget as the project proceeds
- Compares planned to work to that actually completed.
- Helps determine if works are progressing in line with programme.
What is the impact of change on cost?
Will depend upon if it is a domestic change or a client driven change
- Domestic will be negative
- Client will be positive.
How do you prepare a liability statement?
How do you prepare a cost value reconciliation?
It measures cost against the budget.
- I would firstly confirm the contract value/total which would be my starting point.
- I would look at the instructions in the period and update these and include these on my CVR
- I would then look at the Sub-contractor’s application and see if there are any changes or claims in the period from them.
- I would regularly update this document as soon as anything would arise.
- This would help me understand the work completed to date and ensure that we are on budget.
- This would give me a rolling ‘cost to complete’ on each package.
The client wants to make a change, how do you manage this?
- Implement the change control procedure.
How do you undertake the change control process?
- In my role, we would receive the PMI or change from the client.
- We would assess the change and upload this onto a change register
- I would then discuss the change with the relevant parties within CHt and we would then go to the Client if we needed further information.
- I would then start to pull together a quotation in line with the client’s requirements, clearly outlining our fees.
- I would then arrange a meeting to discuss this with the client with a view of gaining implementation.
- I would then review my documentation and close this out on the schedule with the cost clearly indicated.
What is a formal change control process?
PIMM:
- Propose change
- Impact Summary on project
- Make a Decision
- Make the Change
How did you deal with the potential movement of the PC date upstream?
- We firstly needed to clearly understand why the PC date had moved.
- It was clear that there was a lot of client change.
- I had a meeting with the Planner and Engineers who assessed each additional PMI/CE and we allocated additional time to this which gave a clearer indication of the programme and the potential new completion date.
- I then needed to advise the client of this so that we could get a contractually agreed EOT and get this implemented.
How did you ensure productivity was not reduced from the acceleration i.e working longer hours?
- Everyday there was a clear plan of works and what needed to be done and dates completion was required by; which was mutually agreed with the Sub-Contractor.
- We always agreed to pay for 2 extra hours but if the Sub-Contractor completed the tasks in a shorter period of time, we would pay the 2 hours as a bonus.