Mandatory Questions - TARGETTED Flashcards
What is an alliance?
- An alliance an agreement where the parties involved agree to act in good faith and to collaborate to achieve a common goal.
What is partnering?
- Partnering is a management approach used by two or more organisations to achieve specific business objectives by maximising the effectiveness of each participant’s resources.
What are the core professional obligations for members?
- Must comply with CPD requirements;
- Must co-operate with the RICS
- Must promptly provide all information reasonably requested by the Standards and Regulation board.
What are the core professional obligations for firms?
- Firms must publish a complaints handling procedure and maintain a log;
- PI must be in place that meets the standards approved by the RICS
- Principal must make arrangements for their work to continue in the event of incapacity, death or absence;
- Must co-operate with RICS
- Must provide all information to Standards and Regulation board.
- Firms must display that they are regulated by the RICS
- Firms must report any matter that they are required to report under the registration for Firms.
What are the different types of New Rules of Measurement?
- NRM 1: Order of cost estimating and cost planning for capital building works;
- NRM 2: Detailed measurement for building works
- NRM 3: Order of cost estimating and cost planning for building maintenance works
Tell me about Testing and Commissioning
- Testing and commissioning is to be carried out on all installations to ensure that they are safe and meet the design requirements.
- Testing and commissioning ensures optimum performance and conformity with the design specification; the result is maximum comfort and efficiency with minimal energy, maintenance and life cycle costs.
What are the payment terms under the Housing Rights and Grants Act?
- The due date for payment is when the claim is made by the payee or if no claim is made within thirty days of the works being completed.
- A payment notice must be provided five days after the due date.
- The final date for payment is 17 days after the due date.
- Pay less is 7 days before the final date for payment.
What is a key piece of legislation for Sub-Contractors and Payment?
- Housing, Grants, Construction and Regeneration Act (HGCRA) 1996 and;
- The Scheme for Construction Contracts
- Local Democracy, Economic Development and Construction Act 2009
What does the HGCRA 1996 do?
- It is intended to ensure that payments are made promptly throughout the supply chain and that disputes are resolved swiftly.
Tell me about time barring under the NEC?
- Clause 61.3 provides that, if the contractor does not notify a compensation event within eight weeks of becoming aware of the event, he is simply not entitled to compensation under the contract.
When was the NEC 2 introduced?
- 1995 and was taken over by NEC3.
When was the NEC 3 introduced?
- 2005 but was amended in 2013.
When was the NEC 4 introduced?
- 2017.
Difference between NEC 2 and NEC 3?
- Termination was introduced
- Option F was introduced
- Dispute resolution was clearly introduced in NEC 3 (Options W1 & W2)
- No mention of the Housing Rights and Grants Act at NEC 2
What is the difference between NEC 3 and NEC 4?
- Introduction of a Professional Services and Term
- Clause 28 – Assignment - transferring of rights to another party
- Clause 29 – Disclosure - publicise the works without the client’s agreement.
- A dispute can only be referred to adjudication if it has first been referred to the Senior Representatives
- NEC 4 now gender neutral
- Employer has become ‘Client’ and Works Information’ becomes ‘Scope’
- Risk Register is now Early Warning Register
- There is now an alliance contract.
What are the different options under the NEC?
- Option A: Priced contract with activity schedule.
o Lump Sum
o Payment on completion of defined activities
o Suitable for traditional or D&B. - Option B: Priced contract with bill of quantities.
o Contractor is entitled to be paid interim payment based on percentage of each BoQ item. - Option C: Target contract with activity schedule.
o Target cost set by activity schedule
o Target moves with compensation events
o Option C uses pain/Gain mechanism to share risk. - Option D: Target contract with bill of quantities.
o Target set by BoQ
o Target moves with CE’s
o Uses pain/Gain mechanism to share risk. - Option E: Cost reimbursable contract.
o Cost plus – actual costs plus pre-agreed overhead.
o Option E used when scope cannot be clearly defined. - Option F: Management contract.
o Works designed/constructed by multiple sub-contractors
o Financial risk taken by the Client. - Option G: Term contract
What is the pain/gain mechanism?
- The financial risks are shared between the client and the contractor in an agreed proportion.
What are the different types of JCT contract?
- Standard Building Contract.
- Intermediate Building Contract.
- Minor Works Building Contract.
- Major Project Construction Contract.
- Design and Build Contract.
What are the key differences between the NEC and JCT contract?
- Provisional sums – JCT contains, NEC does not
- Payment terms under JCT clear cut, NEC appears in 3 different locations;
- JCT contains comprehensive detail on insurance, NEC detail is brief.
- The QS is not mentioned in the NEC, just project manager
- JCT: Variations, NEC: Compensation Events
- NEC operates ‘Early Warning Process’
- NEC – programme is a contract document, in JCT it is not.
Who is the current RICS president?
Clements Lau
Who is the RICS CEO?
Richard Collins
What is the role of the RICS?
The Royal Institution of Chartered Surveyors promotes and enforces the highest professional qualifications and standards in the development and management of land, real estate, construction and infrastructure
What is the benefit of RICS membership/ Why do you want to be a MRICS?
- The RICS qualification denotes integrity, transparency and excellence in the built environment.
- I feel that this would definitely install confidence in clients, stakeholders etc.
- I would get support and access to other professionals and can work to the best practices in the industry and ensure consistency whilst developing myself.
What are the RICS five rules of conduct? (RISTR!! Respect, Integrity, Service, Trust, Responsibility)
- Members and firms must be honest, act with integrity and comply with their professional obligations, including obligations to RICS
- Members and firms must maintain their professional competence and ensure that services are provided by competent individuals who have the necessary expertise
- Members and firms must provide good-quality and diligent service.
- Members and firms must treat others with respect and encourage diversity and inclusion.
- Members and firms must act in the public interest, take responsibility for their actions and act to prevent harm and maintain public confidence in the profession.