CAPM Formulas Flashcards Preview

PMP Exam > CAPM Formulas > Flashcards

Flashcards in CAPM Formulas Deck (13):
1

Planned Value

PV = percent complete of where the project should be

2

Earned Value

EV = percent complete * BAC

3

Cost Variance

CV = EV - AC

4

Schedule Variance

SV = EV - PV

5

Cost Performance Index

CPI = EV / AC

6

Schedule Performance Index

SPI = EV / PV

7

Estimate at Completion (typical variance)

EAC = BAC / CPI

8

Estimate at Completion (atypical variance)

EAC = BAC + AC - EV

9

Estimate at Completion

EAC = AC + ETC

10

Estimate to Complete

ETC = EAC - AC

11

To-Complete Performance Index (BAC)

TCPI = (BAC - EV) / (BAC - AC)

12

To-Complete Performance Index (EAC)

TCPI = (BAC - EV) / (EAC - AC)

13

Variance at Completion

VAC = BAC - EAC