Case Study Flashcards
1
Q
Why are you so adverse to recommending a Letter of Intent for a client?
A
- lack of robustness
- relevant case law, eg Turner&Townsend vs Abbey Trust
- potential ambiguities
All lead to LOI’s being in advisable
2
Q
Why do you believe additional professional fees would need to be required for the works if another contract was issued? It’s the same amount of works?
A
- programme was longer due to additional scope introduced
- execution & administration of another contract
3
Q
Is a letter of intent a contractual agreement?
A
- it’s a letter
- unless signed by both parties, or terminology suggests it is a legally binding contract
- I would also recommend my clients seek legal advice regarding LOI’s
4
Q
What challenges were presented for the refurbishment of 200BPR?
A
-
5
Q
What was the cost £m2 of the asbestos removal?
A
6
Q
Is there a cost limit on the NEC short form?
A
7
Q
What could you have done if the design was not complete? How could the contractor have priced the works?
A
- I am aware they could have implemented Prov Sums, but generally NEC does not allow for Prov Sums under unamended versions
- Could have continued design through construction, but client required cost certainty before entering into main contract
8
Q
What is the GIA of 200BPR?
A
5,000 m2
9
Q
A