Contract Practice Flashcards
How do you feel about oral contracts?
- Difficult to prove any specific Terms & Conditions, and can make it difficult to prove any agreement
- Ideally all contracts should be written down to refer to
What do you understand by the term contract law?
The body of law that govern and implements agreements between parties 
What are the key elements to make a contract legally binding?
Offer, acceptance, consideration, and the intention to create legal relations
What are express terms?
Expressed terms are terms, ideally written down, that have been discussed and agreed between parties
What are implied terms?
Imply terms are terms not expressly agreed, but are implied by law
What are some of your considerations when you were recommending an appropriate construction contract?
- The client
- Priorities in relation to time, cost, quality, and risk
- Procurement route
- Value, nature and complexity of works
- Public or private sector client
What is the Housing Grants, Construction, and Regeneration Act 1996?
The overarching legislation to ensure construction activities and contracts are fair and reasonable for all parties
Are you aware of any addendum to the Housing Grants, Construction, and Regeneration Act 1996?
The Local Democracy, Economic Development and Construction Act 2009
Can you summarise your knowledge of the Local Democracy, Economic Development and Construction Act 2009
THE ACT PROVIDED THE PROVISION FOR STATUTORY REFERRAL TO ADJUDICATION FOR CONSTRUCTION CONTRACTS
Contracts:
- Can be both written and oral under the addendum (previously only written contracts)
Payment:
- Need for adequate payment mechanisms to determine what payments are due and when
- Payment when certified clauses no longer acceptable
Payment notices:
- At least one party must issue a payment notice (usually client)
- Must be issued no later than 5 days after due date
- Must be issued even if payment is nil
Default payment notices:
- If the client does not issue the payment notice, the payee is entitled to serve a payment notice for the amount due (would be the contractors assessment of works completed)
Pay less notice:
- Can be used to amend the payment due
- Must be issued before final date for payment (under NEC=7 days, and JCT=5 days before final date for payment)
Suspension for non-payment:
- Contractor can suspend all works and obligations under their contract for non payment
- Client is obligated to pay contractor reasonable expenses for their exercising the suspension of works
Could a client make any changes they wanted under their construction contract?
Any changes could be made providing aligned with legislation such as the construction act
What are the maximum number of days you can go without paying your contractor?
The construction act states contractors are entitled to interim payments if the scheme is anticipated to exceed 45 days
Can a contractor the suspend works for non-payment?
Yes, under the Construction Act 2009, a Contractor can suspend their works, and all other obligations under their contract, for non-payment
What is a Parent Company Guarantee?
Parent company guarantee is when a contractor, who is managed by a larger, more financially stable company, can obtain confirmation from their parent company, that if anything was to happen to them, the parent company would step into complete the works
When might a parent company guarantee be required?
- when a small contractor forms part of a larger, financially stable organisation
- Can be used in lieu of a performance bond
- gives the client comfort that if the smaller contractor goes insolvent, the parent company will meet all obligations under the contract on behalf of that smaller company
What do you understand about the contracts (rights of third parties) act 1999?
- The act allows third-party to a contract to enforce the terms of that contract
- the third parties must be a beneficiary under that contract to enforce those terms (under NEC, beneficiaries can be named within the contract data)
What are the advantages and disadvantages of the third-party rights act?
Advantages:
- No separate documents required, such as collateral warranties, so time and cost are saved
- Provides certainty from the contract execution, rather than collateral warranties which may not be agreed until the end of the works
Disadvantages:
- Lack of flexibility: any provisions explicit under the third-party rights act (including amendments) would be applicable to all third parties under that contract. Any provisions have been included for one third-party, that provision would apply to all, therefore it could lead to problems
Why might the third-party rights act be used instead of a collateral warranty?
- If a lot of collateral warranties are required under a contract, there can be a lot of administration and cost involved
- Third-party right are easier to get in place because there’s no separate document required
What is a collateral warranty?
The collateral warranty is contractual link between two parties, where one would not otherwise exist
Can you provide an example of how a collateral warranty could be used?
If employer and contractor have a design and build contract, and contractor has a subcontract with an MEP subcontractor, then a collateral warranty could be executed between the employer and that MEP subcontractor
Why might a collateral warranty be requested from the client?
To provide a contractual link to a subcontractor who was undertaken specialist design, so they can hold that subcontractor accountable for defective workmanship or defective design
A collateral warranty might be requested in the event of a contractor going into solvent, there would be a contractual link between the subcontractor and the employer
What ways can benefits be transferred to 3rd parties under building contracts?
- assignment
- third parties act
- collateral warranty
What is assignment under building contracts?
Assignment is when the benefit of a contract contract is transferred from one party to another, but the burden of that contract remains with the original party
Who might want benefits under a construction contract, in relation to assignment?
- Bank
- Funders
- Tenants
What is a bond?
Construction bonds are taken out for protection against non-payment or lack of performance in the event a party were to default under the contract