Design Economics and Quantification and Costing Flashcards
(105 cards)
What sources of cost information are available when preparing a new estimate or cost plan?
- BCIS
- Pricing Books
- Previous project information
- In house cost data
- Direct contact with supply chain
- Rate books, eg - DfE projects
What is benchmarking?
The use of historical project data from projects of similar size and scope, to provide a cost per functional unit or m2
How would you undertake a benchmarking exercise?
- Produce a comparison document to compare schemes, of similar scope and size, broken down elementally
- Identify any project anomalies and omit, in order to determine a cost per functional unit or m2
Give me some examples of capital costs
- Cost of construction
- Land acquisition
- Consultant fees
Give me some examples of operational costs
- Maintenance costs
- Utilities usage
- Repair or replacement costs
How could you dramatically reduce the capital cost of a building?
- Reduce GIA
- Reduce building height
- Reconsider design solutions, for example, concrete frames may require more substantial substructures due to the weight of the frame
Can you tell me what the NRM series are?
NRM 1 - Order of cost estimating and planning for building capital works (used for RIBA 0-2)
NRM 2 - Detailed measurement for building works (used for RIBA 3-4)
NRM 3 - Order of cost estimating and planning for building maintenance works (used for LCC)
What are the different methods for cost estimating?
- cost per m2
- Cost per functional unit
- Using the elemental method, eg stairs per nr
What are the different ways you can build up a cost plan?
- Prime cost sums
- Provisional sums
- Cost for design works, in terms of elemental components
What are provisional sums?
- An allowance to undertake works that are not sufficiently designed in detail
- Can be defined or undefined
What is the difference between defined and undefined provisional sums?
- Defined provisional sums = the sum for the works inclusive of preliminaries and programme
- Undefined provisional sums = the sum of works excluding preliminaries and programme allowances
How are provisional sums expended?
- Contract Administrator issues an instruction to spend
- Add and omit exercise undertaken to include for actual cost of works
How does NEC deal with provisional sums?
- Unamended NEC does not allow for provisional sums
- NEC approach is if works can’t be properly defined, they should be excluded until they can be
- In my experience, if a provisional sum has been included, it is dealt with under the compensation event process
What is inflation?
The general increase of prices over a set period of time
How would you rebase time and location for a cost plan or estimate?
- Using BCIS indices
- Inflate for tender (up to the start of construction)
- Inflate for construction (up to the midpoint)
- Inflate for location (ensuring the correct location factor has been applied)
What indices would you use for Tender Inflation and Construction Inflation, and for location?
All in Tender Price Index (TPI)
Location factors on BCIS
What would you include in a cost plan or estimate?
- Cover letter
- Executive summary
- Assumptions and exclusions
- Grand Summary (construction cost estimate, MC preliminaries, MC OH&P, Risk allowances, professional team fees, inflation)
- Elemental breakdown
- Inflation calculation
- Cash flow, if required
Give me some examples what you might assume in a cost plan
- Current substation doesn’t need replacing
- No asbestos in building
- Internal wall height
- No works to existing infrastructure required
Give me some examples of items you might exclude from a cost estimate or plan
- Land acquisition fees
- Legal fees
- VAT
- Insurances
Why do you exclude VAT from a cost plan or estimate?
- Employers may incur different levels of VAT
- VAT should be calculated by a tax advisor / specialist
Do you need a programme to complete a cost estimate or plan?
- I wouldn’t need a full programme but at least indicative dates are required to inform preliminaries, OH&P and inflation
How does good cost planning benefit the client?
- Confirms viability of scheme
- Allows client to make informed financial decisions
If you saw a project was giving an early indication of overspend, how could you recommend your client bring the scheme back into budget?
- Look at areas for value engineering
- Look at over and above scope and where works could be omitted, if not required
- Look at securing additional funding
What do you write about in your market conditions report?
- Looks at local supply chain availability
- looks at trends in construction in the local region
- Inflation analysis, labour availability and material prices news
- Reviewing external factors, such as Red Sea Attacks on material imports and Russia-Ukraine war and effects of prices and availability of materials