Case study questions Flashcards
(37 cards)
Can you talk me through the construction of Freshwater Court?
Fresh water court is of cavity brick construction with hollow beam concrete floors and a timber flat roof
How are you able to consider the age of the building?
I review old maps and photographs as well as the style of construction
What challenges did the location of the building have on your project?
As the building was situated in an exposed seafront location it was particularly prone to prevailing south westerly winds.
What caused failure of the roof?
In this case there was a strong south easterly wind during a storm. The UPVC trims and roof covering were stripped back.
How did you go about checking for potential conflict of interest?
I used our conflict of interest check form which ensure I had no vested interest in the building, I had no relationship with the client, leaseholders, managing agent or loss adjuster.
How did you go about preparing your specification?
What was the requirement to take samples?
To understand The roof buildup including establishing the type of deck and also providing an indication of whether the installation and deck were saturated which would have led to an alternative repair.
Why was wood wool slabs a risk?
Wood wool slab is classed a deleterious material as voids can form around the reinforcement. HSE Health and safety in roof work (Fifth Edition) also class them as fragile decks especially when exposed to water penetration. If retained fixing of insulation can be problematic and replacement will require structural engineering design.
Why was the roof deck able to be retained?
The roof deck was found to be 18mm ply wood and was found to be dry in all areas where samples were taken.
Why was it not a requirement to meet current building regulations
Because the waterproof membrane was not being removed
Why would a high-performance buildup felt system have been appropriate?
It would have provided the client with a 25 year guarantee.
How did you go about calculating insulation depth?
You value equals 0.6 what/M2 Kelvin
U value equals 1/0.16 equals 6.25 M2 K/W
Insulation type PIR board 100 mm r value
What implication with the new parapets heights had on planning?
By raising raising the parapet roof edges by 150 mm wood not have affected planning in our local area however, anything over this may have and I would check this on a case by case basis.
What association warranty would you have achieved with option two?
The contractor would have provided a 25 year warranty.
Why was liquid applied system suitable?
I have worked with the system called poly roof which is a suitable overlay system for bituminous felt as it is able to take up the movement of the felt.
What had caused does the bubbling?
Bubbling and booted can be caused by trapped air or moisture.
What had caused the corroded fixings?
The fixings were a galvanised type which corrode over time exacerbated by the coastal location.
How was your budget cost prepared for the various options?
I used costings from previous roofing projects such as William George court
Why did you invite four contractors tender?
I invited 4 contractors to tender as the project was small and, needed a quick turn around and was coming upto a busy season. this worked well as one contractor failed to return meaning I had 3 valid tenders.
How did you go about calculating the contingency sum?
I used information from previously completed projects.
Under option one who would’ve taken the design risk?
The design risk could have been allocated to the employer or the contractor depending whether we produced a full design or allowed the contractor to design
What are the pitfalls of letter of intents?
Can you talk me through the principles of the JCT repair and maintenance contract?