Contract practice Flashcards
What key function does a contract perform on a construction project?
A contract outlines the rights and obligations of the parties involved in a construction project.
What is a contract?
A contract is a legally binding agreement between two or more parties.
Define express terms?
Express terms are specific provisions that are clearly stated in a contract.
Define implied terms?
Implied terms are provisions that are not explicitly stated but are assumed to be included in a contract.
What six conditions need to be met for a contract to be in place?
- Offer 2. Acceptance 3. Consideration 4. Intention to create legal relations 5. Capacity to contract 6. Legality of purpose.
What are the main suites of construction contracts?
The main suites of construction contracts include JCT, NEC, FIDIC, ICE
What is tort?
Tort is a civil wrong that causes harm or loss to another person, leading to legal liability.
What are the influences which will affect contract selection?
Factors such as project size, complexity, risk allocation, and client preferences influence contract selection.
Can you name three standard forms of contracts that can be used on a construction project?
- JCT 2. NEC 3. FIDIC.
What do you understand about the following forms of contract; NEC, JCT,
These are standard forms of construction contracts that provide frameworks for project delivery and risk management.
What does JCT stand for?
JCT stands for Joint Contracts Tribunal.
Name the key components of the JCT contract suite.
Key components include the main contract, schedules, and various forms for different project types.
When was the JCT contract suite last updated?
The JCT contract suite was last updated in 2024
Tell me about some of the key changes that were made.
Key changes included updates to
language
Collaborative working
Included provision for BSA 22
Email
How was the JCT contract suite modernised through the last update?
The suite was modernised by incorporating electronic working and clearer language. BSA22 BRPD and BRPC
How does JCT facilitate electronic working?
JCT facilitates electronic working by allowing service of notices via email
How does the JCT work alongside the Construction Playbook?
JCT aligns with the Construction Playbook by promoting best practices and standardising procurement processes.
How has the JCT contract suite incorporated diversity and inclusion?
The JCT contract suite has incorporated diversity and inclusion by neutralising language
What is the JCT Fluctuations Hub used for?
The JCT Fluctuations Hub is used to manage price fluctuations in construction contracts. The minor works no longer includes fluctuations and as works under these contracts are usually relatively small and simple in nature.
Explain the JCT Target Cost Contract to me.
The JCT Target Cost Contract is a form of contract where the contractor is paid a target cost, with incentives for cost savings.
A target cost contract is a type of cost reimbursable contract under which the contractor is paid the ‘actual cost’ (usually defined in the particular contract) it incurs in carrying out the works, but subject to a target cost which is agreed by the parties at the beginning of the project.
The target cost is the cost to the contractor of completing the project, comprising:
•
the base cost of the physical works (based on the sum of prices in a bill of quantities, schedule of rates or an activity schedule), the cost of temporary works, sub-contractor costs and preliminary costs
•
overheads and profit
•
a contingency for contractor’s risks under the contract
At the end of the project, the parties will apply a mechanism/formula to calculate whether savings were made and the project delivered for less than the target cost, or whether costs overran and the cost of delivering the project was more than the target cost. The contractor will then either share the savings with the employer
What form of NEC contract might the Target Cost Contract be a good alternative for?
What are the main parts of the JCT contracts?
https://www.jctltd.co.uk/docs/MW-2024.pdf
What are the JCT schedules?
JCT schedules detail specific project information, including pricing and timelines.
How are relevant events and relevant matters dealt with under NEC?
Relevant events and matters called compensation events and there are strict procedures and time scales for addressed defined procedures for notifications and adjustments