Chapter 13 Flashcards

(8 cards)

1
Q

Projects run late and over project, what are requierments do deal with it?

A

DDMMI

Define characteristics of importance
Define limits to their variation
Measure the characteristics
Making progress visible & Feedback
Instituting corrective action

pp. 316-320

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are examples of visual control systems?

A

Gantt chart
Traffic lights
Information boards
etc

pp. 326

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the performances?

A

Cost performance indicator = earned value /actual spend

Schedule performance indicator = earned value/planned spend

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the predictions?

A

Estimated cost at completion = Original budget / cost performance indicator

Estimated time of completion = original time estimate/schedule performance indicator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the variances?

A

Cost variance = Earned value - actual spend

Schedual variance = Earned value - planned spend

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is earned value?

A

The value of the budgeted version of how many activities that has been completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is planned spend?

A

The amount of budgeted money at the point where a certain amount of activities should be finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the technique earned value?

A

Brings together time and cost performance into a monetary quantity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly