Construction Tech Flashcards
(211 cards)
What are the RIBA stages of work?
The RIBA Plan of Work organises the process of briefing, designing, constructing and operating building projects into eight stages and explains the stage outcomes, core tasks and information exchanges required at each stage.
what are the 8 stages of RIBA
0 - Strategic definition.
1 - Preparation and briefing.
2 - Concept design.
3 - Spatial coordination.
4 - Technical design.
5 - Manufacturing and construction.
6 - Handover.
7 - Use.
Strategic Definition
the client’s business case and strategic brief are assessed to ensure they have been properly considered’ and the scope of the project is defined.
Prep and Briefing
developing the information that the design team will need to commence the design process at Stage 2
Concept design
represents the design team’s initial response to the client’s requirements. Concept design generally takes place after feasibility studies and options appraisals have been carried out and a project brief has been prepared.
Spatial Coordination
is fundamentally about testing and validating the Architectural Concept, to make sure that the architectural and engineering information prepared at Stage 2
technical design
The technical design stage (sometimes referred to as ‘design’) develops the design in sufficient detail for co-ordination to be completed and enables packaged, production information to be prepared which can be passed to the contractor and their supply chain to construct the development.
Manufacturing and construction.
The main contractor will produce working and fabrication information documents at Stage 5 to enable coordination of the full design including manufacturing of off-site materials and components.
Handover.
The building contractor will hand over documents including a building owner’s manual and the health and safety file. For the design and build teams, Stage 6 can still involve practical tasks, such as discharging planning conditions and rectifying defects.
Use.
The design team and construction team typically have no duties during Stage 7 of a project, but ongoing feedback is useful for future projects. Post Occupancy Evaluation services help fine-tune a building and inform future projects.
How are pad foundations connected to steel columns
Through holding down bolts cones and stancion plate
How are internal stud partitions formed?
- Head and base track
- Stud fixed at 600mm centres (plasterboard typical width 1200mm)
- Insulation between studs
- Pattressing
- Door openings formed
- Abutments, tees, fair ends
- Plasterboard
- Head detail (depends on frame)
What does the Building Safety act mean for construction?
For the construction industry, it means an overhaul in existing regulations, creating lasting change and makes clear how higher risk buildings should be constructed and managed to ensure that those who use them are safe and feel safe.
What updates were there on the 18th edition electrical guidance?
It is now a requirement to protect final circuits supplying socket-outlets with a rated current not exceeding 32 A using arc fault detection devices (AFDD) in Higher Risk Residential Buildings, Houses in Multiple Occupation, Purpose-built student accommodation and Care homes
What is and Arc Fault detection device?
AFDDs are protective devices installed in consumer units to provide protection from arc faults. They use microprocessor technology to analyse the waveform of the electricity being used to detect any unusual signatures which would signify an arc on the circuit
What did the tanking detail sign off require?
Product spec and details to be signed off by building inspector
What did the grouting process in Halifax involve?
metre by metre grid dill and grout of shallowing mine workings
What are the benefits of raft foundations?
The principal aim of a raft foundation is to spread the load of the building across the entire available surface area under the building. This reduces the stress on the ground below, providing a solid foundation that can accommodate ground movement whilst still maintaining structural integrity.
What are the disadvantages of raft foundations?
In some cases, large amount of reinforcement is required for raft foundation which increases the cost of project.
Special attention on raft foundations is required in case of concentrated loads.
If they are not treated properly, there is a chance of edge erosion.
Skilled workers are required to construct the raft foundations.
What are other types of foundations?
Strip
Trench fill
Raft
Piling
Why did you advise that a raft foundation was required for the modular building?
Required as advised by the modular build contractor for drainage and load distribution
Why is fire stopping required for certain partitions?
Fire rated partitions are required to ensure smoke and fire seal to maintain integrity
Why did you advise that partitions could be built to the underside of the ceiling?
Fire compartmentation could be maintained and cost saving and programme saving
What is MMC?
- Modern methods of construction
- Generic term to embrace all processes which reduce level of on-site labour intensity and delivery risk
- UK government has formally defined 7 types - structural (3D boxes, 2D panels, structural components, 3D printing), and non-structural (3D printing, pods & panels & components, smarter materials, better processes)