Who is responsible for administering the building contract?
What guidance is there for design and build?
Can you talk me through the RICS Contract Administration document?
Is the Contract Administrator a role before the construction phase starts?
What qualities does a CA require?
As RICS Contract Administration
- Knowledge and skill to apply relevant contractual provisions
- Act independently, impartially, and fair
- In-depth knowledge of construction and inter-relation between trades so changes and impact can be traced
- Appropriate record keeping procedures
- Be aware of different types of critical path and project programming techniques
Key tasks of a CA?
As RICS Contract Administration
- Chairing meeting
- Periodically inspect the works (not include checking compliance of work with design
- Employer’s obligation which could be delegated to design team)
- Give instructions (variations, change orders)
- Determine EoT applications
- Authorise interim payments
- Certify completion
- Settling adjusted contract sum (FA)
(- doesn’t include design - need to take care that instruction / design changes are approved by employer and designers)
- Comply with CDM 2015 regs as a designer role
- Reporting to client
What is required within a CA inspection?
As RICS Contract Administration
- Frequency depends on project
a) recording information: date and time, weather conditions, no. and type of operatives on site, instructions given on site, progress of works
b) review quality of workmanship
c) review progress in relation to programme
d) check materials being used
e) check works conform with spec and drawings (may have assistance)
f) note general info so CA can report to employer on progress and quality
g) record any measurement that might be needed for certification (valuation)
h) General awareness of H&S > confirm outcome in writing, inc any instructions, to employer and contractor
What is the CA’s role at completion?
CA vs PM vs EA?
CA steps with defects?
What is practical completion?
Can you rescind the PC statement once it has been issued?
What are the consequences for the contractor and employer once the PC statement has been issued?
What is a non-completion certificate?
What are the consequences of a non-completion certificate?
If a project was due to finish before Christmas, but an extension of time was given which meant the contractor finished after Christmas, is the contractor entitled to costs over the Christmas break, which is normally 2 weeks?
What is the defects liability period?
Why might the EA instruct the contractor to ‘open up’ works which have been covered up?
When issuing instructions for further opening up and testing to determine the extent of non-compliance what sort of things should the CA consider?
Assuming the EA has instructed the contractor to ‘open up’ the works, what are the potential outcomes? (including effect on cost and completion date)
If the works or materials aren’t in accordance with the Contract, what options does the Architect have available to them?
Architect may: - Instruct contractor to remove all defective work / for variations necessary, materials and goods at their own expense and time
- Notify in writing they can remain with appropriate deduction made from contract sum
- Instruct to open up and test further work to determine extent of any non-compliance
What’s the procedure for claiming an EoT?
From a CA point of view, what are the time periods related to assessing relevant events and adjusting the completion date?
If the contractor successfully demonstrates a relevant event and CA adjusts the completion date, is the Contractor due additional preliminaries?