Construction technology Flashcards

(45 cards)

1
Q

What detail is included for a flat cold roof?

A

Plasterboard, vapour control layer, roof structure, insulation in between, deck, covering. [Part H].

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How did you prevent potential problems from a cold roof?

A

Ensure there’s enough ventilation throughout the roof.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Where would you expect to see a cavity barrier and why?

A
  • Between walls, floor and around windows and doors [wall cavity].
  • Prevents the spread of fire and smoke to other areas and floors.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What would you need to consider when constructing a partition wall?

A
  • AD M: min 1.2m wide.
  • Does it need to be fire rated i.e. a protected corridor? [12.5mm plasterboard, fire doors].
  • Installing deflection heads.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a deflection head?

A

A detail at the top of partitions to allow for structural movement of the floor/roof above.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Langley Quay: Explain the instruction in more detail and what you advised?

A
  • Office refurb.
  • Two options - one lower spec, one higher spec.
  • £60k more, 4 weeks longer.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Langley Quay: What was included in the higher spec that wasn’t in the standard spec?

A

Option 1:
- Retain suspended ceiling.
- Retain floor covering.
- Retain partitions.
Option 2:
- New ceiling.
- New floor covering.
- Remove partitions (open plan).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Langley Quay: What was the impact of the different design solutions?

A

Lower spec:
- Short-term investment.
Higher spec:
- Longer-term investment.
- £60k more, 4 weeks longer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Langley Quay: Any amendments/additions to the MEP?

A

Undertook validation of existing M&E – ended up retaining it all.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Langley Quay: Any consideration towards improving EPC rating? What advice did you provide to achieve this?

A
  • Yes, upgraded to a B rating from a C rating.
  • Advised installing LEDs and PIRs as property was close to a B rating and this would likely achieve this – energy consultant advised for certainty.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Campden Hill Towers: Please explain in more detail the defects identified here. What did you visually inspect?

A
  • Pre-cast concrete panels were deteriorating.
  • Spalling concrete.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Campden Hill Towers: What was the likely cause of the defect?

A

The steel fixings holding the panels up were expanding and damaging the panels (risk of falling debris).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Campden Hill Towers: What was your immediate recommendation to the client following your inspection?

A
  • Erect crash decking to protect the pedestrians below.
  • In-depth survey to be undertaken (abseil).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Campden Hill Towers: How did you recommend the defect diagnosis works proceed?

A

Survey by abseil due to building height and surrounding area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Campden Hill Towers: How was disrepair assessed?

A
  • Initial survey from ground level.
  • In-depth survey undertaken by specialist.
  • Report produced which I reviewed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Campden Hill Towers: a) What repair works were ultimately recommended?
b) How long was the programme for this?

A

a) Remove existing cladding and replace with new.
b) 6 months.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How did you determine there was lime pointing at Windsor Walk?

A
  • Victorian property.
  • Solid brickwork wall (lime typically used).
  • Sandy colour - cement mortar is grey.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What type of sand is required for lime mortar?

A

Washed sharp sand.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What’s the mix for lime?

A

1:3
Lime to sand.

20
Q

What’s the difference between hydraulic and non-hydraulic?

A

Hydraulic is stronger, non-hydraulic is more flexible.

21
Q

When was cement mortar first used?

A

Around the 1800s.

22
Q

What causes spalling brickwork?

A
  • Freeze-thaw.
  • Water ingress.
  • Putting cement mortar on lime mortar (water escapes through brick face).
23
Q

You mention artificial slates, how do you recognise them?

A

They have straighter and more complete finish compared to natural slates which are rougher.

24
Q

What type of air conditioning was specified on Windsor Walk?
Why was this system used?

A
  • VRF (Variable Refrigerant Flow).
  • More energy efficient.
  • Doesn’t need ductwork like a VAV (Variable Air Volume) system.
25
What are the limitations of a VRF system?
You can get leaks.
26
Note: Con Tech - Campden Hill Towers. - Project. - £150k. - Cladding remediation. - Time and cost implications: £60k more, 4 weeks less. Cost was more expensive to remove panels but better longevity than wrapping.
27
Note: Con Tech - Langley Quay. - Project. - £200k. - Remove tenant chattels, refurb of office. - Two design options - one high spec (long-term), one low spec (short-term - retain existing ceilings, partitions and floor covering).
28
a) On Campden Hill Towers you completed works to a residential tower block. What did you have to issue to commence works? b) Why is this required? c) Do you know of any legislation relating to this?
a) Section 20 notice. b) Landlords to notify leaseholders of major works where costs exceed £250 per leaseholder. c) LTA 1985.
29
Bricket Road, St Albans: What is an Initial Notice?
Notify local authority that construction has started and BCA is being used. [Local authority has 5 working days to review and reject otherwise it passes]
30
Travelodge, Gray's Inn Road: Talk me through the build up of the external wall system.
- Render. - EPS insulation (expanded polystyrene). - Sheathing board. - LSF. - Void [cavity barrier missing]. - Vapour control layer. - Plasterboard.
31
Travelodge, Gray's Inn Road: Do hotels need to comply with the BSA 2022?
- They do, but are not classed as HRBs. [Care homes, hospitals, prisons aren't HRBs either as they typically have their own safety procedures].
32
Campden Hill Towers: What were the different time and cost implications?
Removal: - £60k more. - 4 weeks less. [Removed panels using a pulley/winch to lower to ground floor]
33
Campden Hill Towers: What happened to the structure when the cladding was removed?
The structure beneath was a concrete frame so it was temporarily left exposed while the panels were removed.
34
Bricket Road, St Albans: What design requirements did you consider?
- Fit-out - kitchens, offices. - M&E layout. - Fire stopping locations. - Partitions.
35
Langley Quay: What were the different time and cost implications for the two options?
High spec: £60k more, 4 weeks longer.
36
Travelodge, Gray's Inn Road: What was the Euroclass rating of the insulation?
Euroclass C (EPS insulation).
37
Bricket Road, St Albans: You said you reviewed an Initial Notice as part of the LtA. What's the alternative to using an Inital Notice for Building Regulations?
Full Plans Application [LABC route]. [Initial Notice is for BCA route].
38
Bricket Road, St Albans: For the LtA review you say you reviewed fire stopping locations. What would you refer to to find out fire stopping locations?
- Fire strategy plan. [- As-built drawings. - O&Ms.]
39
(Follow on from Bricket Road mention of Initial Notice and ensuring compliance with Building Regulations): What is the building control process for non-HRBs?
- BCA or LABC route. - Initial Notice or Full Plans application. Submit documents to BCA/LABC: - Proposed and existing plans. - SoW. - Services drawings (M&E). - Fire strategy plans. [- Structural and energy calculations.] [- Site plan.]
40
(Follow on from Bricket Road mention of Initial Notice and ensuring compliance with Building Regulations): What is the building control process at the end of a project for non-HRBs?
- Final inspection. - Provide documents for review i.e. drawings and test certificates [to BCA]. - Final certificate.
41
Travelodge, Gray's Inn Road: What are AD B requirements for cavity barriers?
Placed: - At wall and floor junctions. - Around windows and doors. - Between demises. Fire resisitance: - 30 mins [resistance for fire and smoke] [and 15 mins limit of temperature - fire insulation]
42
Campden Hill Towers: What are the implications of removing the cladding to a building? How was this to be mitigated?
- Exposes concrete frame [acceptable short-term but need weathertightness long-term]. AD L: - Thermal performance (U-values) [can't reduce only match or improve]. - Airtightness [can't reduce only match or improve]. - Moisture [vapour control layer and ventilation must be considered].
43
Travelodge, Gray's Inn Road: How did the building materials interact inadequately?
- No cavity barriers > fire hits EPS insulation directly which is combustible [Euroclass C]. [If they say 'but doesn't the sheathing board provide fire resistance?' say it does but there were gaps in this instance]
44
Travelodge, Gray's Inn Road: a) Was this an FRAEW? b) What's the difference between an FRAEW and an EWS1 form?
a) Yes. b) - FRAEW: Provides risk rating and recommendations [for remediation]. - EWS1 form: Assesses financial risk [for valuers].
45
Campden Hill Towers: What is the Section 20 process?
3 stages: - Notice [of Intention to complete works] - 30 day consultation period. - Provide estimates - 30 day consultation period. - Notice of chosen contractor [only if not cheapest].