Construction technology Flashcards
(45 cards)
What detail is included for a flat cold roof?
Plasterboard, vapour control layer, roof structure, insulation in between, deck, covering. [Part H].
How did you prevent potential problems from a cold roof?
Ensure there’s enough ventilation throughout the roof.
Where would you expect to see a cavity barrier and why?
- Between walls, floor and around windows and doors [wall cavity].
- Prevents the spread of fire and smoke to other areas and floors.
What would you need to consider when constructing a partition wall?
- AD M: min 1.2m wide.
- Does it need to be fire rated i.e. a protected corridor? [12.5mm plasterboard, fire doors].
- Installing deflection heads.
What is a deflection head?
A detail at the top of partitions to allow for structural movement of the floor/roof above.
Langley Quay: Explain the instruction in more detail and what you advised?
- Office refurb.
- Two options - one lower spec, one higher spec.
- £60k more, 4 weeks longer.
Langley Quay: What was included in the higher spec that wasn’t in the standard spec?
Option 1:
- Retain suspended ceiling.
- Retain floor covering.
- Retain partitions.
Option 2:
- New ceiling.
- New floor covering.
- Remove partitions (open plan).
Langley Quay: What was the impact of the different design solutions?
Lower spec:
- Short-term investment.
Higher spec:
- Longer-term investment.
- £60k more, 4 weeks longer.
Langley Quay: Any amendments/additions to the MEP?
Undertook validation of existing M&E – ended up retaining it all.
Langley Quay: Any consideration towards improving EPC rating? What advice did you provide to achieve this?
- Yes, upgraded to a B rating from a C rating.
- Advised installing LEDs and PIRs as property was close to a B rating and this would likely achieve this – energy consultant advised for certainty.
Campden Hill Towers: Please explain in more detail the defects identified here. What did you visually inspect?
- Pre-cast concrete panels were deteriorating.
- Spalling concrete.
Campden Hill Towers: What was the likely cause of the defect?
The steel fixings holding the panels up were expanding and damaging the panels (risk of falling debris).
Campden Hill Towers: What was your immediate recommendation to the client following your inspection?
- Erect crash decking to protect the pedestrians below.
- In-depth survey to be undertaken (abseil).
Campden Hill Towers: How did you recommend the defect diagnosis works proceed?
Survey by abseil due to building height and surrounding area.
Campden Hill Towers: How was disrepair assessed?
- Initial survey from ground level.
- In-depth survey undertaken by specialist.
- Report produced which I reviewed.
Campden Hill Towers: a) What repair works were ultimately recommended?
b) How long was the programme for this?
a) Remove existing cladding and replace with new.
b) 6 months.
How did you determine there was lime pointing at Windsor Walk?
- Victorian property.
- Solid brickwork wall (lime typically used).
- Sandy colour - cement mortar is grey.
What type of sand is required for lime mortar?
Washed sharp sand.
What’s the mix for lime?
1:3
Lime to sand.
What’s the difference between hydraulic and non-hydraulic?
Hydraulic is stronger, non-hydraulic is more flexible.
When was cement mortar first used?
Around the 1800s.
What causes spalling brickwork?
- Freeze-thaw.
- Water ingress.
- Putting cement mortar on lime mortar (water escapes through brick face).
You mention artificial slates, how do you recognise them?
They have straighter and more complete finish compared to natural slates which are rougher.
What type of air conditioning was specified on Windsor Walk?
Why was this system used?
- VRF (Variable Refrigerant Flow).
- More energy efficient.
- Doesn’t need ductwork like a VAV (Variable Air Volume) system.