Design and specification Flashcards

(43 cards)

1
Q

What goes into a specification?

A
  • SoW.
  • Prelims.
  • Materials and Workmanship.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What guidance do you follow for producing a specification?

A
  • BS 8000.
  • Design and Specification Guidance Note.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the advantages of using NBS Chorus?

A

You can select the items you want and it pulls them through into a document with the detail saving you time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What parts did you do of the specification?

A

SoW, prelims, Materials and Workmanship.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Would you specify fire stopping?

A

No this is done by a specialist.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the advantage of taking the design to RIBA Stage 4?

A
  • More control over design.
  • More cost certainty.

[- Easier for contractor to price.
- Better understanding of project.]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How did you ensure the durability of products?

A
  • Specify BS.
  • Guarantees [insurance backed].
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What protections were in place for the products?

A

Collateral warranties and manufacturers guarantee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a heritage statement?

A

Describes the historical significance of a building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Note: Design and spec - Ferry Lane.
- TDD (vendors).
- 20 metres from nearest protected staircase (should be max 18 metres).
- Proposed erecting protected corridor to reduce travel distance.

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Ferry Lane - How did erecting a wall reduce the protected stairwell route?

A

Reduced the travel distance as it created a protected corridor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Ferry Lane - How did you assess the level of fire protection required from the newly erected wall?

A
  • AD B.
  • BS 9999.
  • Recommended 30 min fire rated plasterboard and fire doors.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Ferry Lane - Take me through the full specification of the partition wall.

A
  • Plasterboard 12.5mm thick.
  • Mineral wool insulation.
  • Fire doors 30 minute.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Wembley Arena: You mentioned that you noted numerous items that could be upgraded to improve the building’s sustainability. Aside from LED lighting, what did you identify and recommend?

A
  • Solar panels.
  • Low-flow taps.
  • PIRs.
    [- Energy efficient heating and cooling.]
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Wembley Arena - a) How were the works presented to your client in the PPM?
b) How were the sustainability works presented?

A

a) - Schedule [condition and year for each item].
- Report [explaining schedule].
b) Included within recommendations section of the report which summarised the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Wembley Arena - What was your client’s key driver for the PPM requirement?

A
  • Understand costs for maintaining the property.
  • What years to undertake maintenance.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Wembley Arena - How might the presentation of a PPM differ somewhat to providing your client with a vendor’s TDD?

A
  • PPMs outline the maintenance over a number of years (typically 10 years).
  • TDDs report on the condition of the building in its current state in terms of purchasing a building (shorter term costs).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

For D&B what RIBA Stage would you take the design to?

A

RIBA Stage 3 - Spatial Coordination.

19
Q

What’s the difference between Building Regulations and British Standards?

A
  • Building Regs: minimum standards (mandatory).
  • British Standards: best practice (voluntary).
20
Q

How are provisional sums dealt with post-contract?

A
  • Provisional sum and works omitted.
  • Contract instruction issued with defined works and cost [variation not CI if the cost differs].

[PS amount is deducted from contract sum and actual cost of instruction/variation is added]

21
Q

Can you name some headings within the prelims document?

A
  • Description of Work.
  • The site.
  • The contract.
22
Q

When is planning permission required?

A

Not required for:
- Internal works.
- Permitted development.

  • New build.
  • Change of use.
  • Extension.
23
Q

How long does planning permission take?

A
  • Typically around 8 weeks for normal property.
  • Around 12 weeks for Listed building [both LBC and normal planning considered together].
24
Q

What information is required when submitting a planning application?

A
  • Site plan.
  • Existing and proposed drawings.
  • Application form.
    Conservation areas:
  • Design and Access (D&A) statement
  • Heritage statement.
25
When is CDM required?
- On all projects. - Duties placed on contractor for domestic but still applies.
26
What's the difference between a guarantee and a warranty?
Guarantee: - Covers product performance [typically]. - 10-30 years cover [typically]. [- Can have insurance backed guarantees which offer stronger recourse as there's a fallback route.] Warranty: - Covers workmanship [typically]. - 1-10 years cover [typically]. - Third-party protection in contracts i.e. collateral warranty. [If your roof leaks because it was installed incorrectly the warranty from the installer would cover the fix. If your roof leaks because the roofing material cracked or failed the guarantee from the manufacturer would cover the replacement material]
27
What are the Approved Documents and their contents for: - Part A. - Part B. - Part C. - Part D. - Part E. - Part F. - Part G. - Part H. - Part J. - Part K. - Part L. - Part M. - Part O. - Part P. - Part S. - Part T.
- Part A: Structure. - Part B: Fire safety. - Part C: Site prep. - Part D: Toxic substances. - Part E: [Ear] Sound (resistance to). - Part F: [Fan] Ventilation. - Part G: [Germs] Sanitation. - Part H: Drainage. - Part J: Combustion appliances. - Part K: [Kicking K] Protection from falling. - Part L: Conservation of fuel and power. - Part M: Access to and use of buildings. - Part O: Overheating. - Part P: Electrical safety. - Part S: Electric vehicle charging. - Part T: Toilets.
28
What does PAS stand for?
Public Available Specification.
29
Note: Design and spec - Campden Hill Towers. - Project. - £150k. - Erection of a crash deck was included as performance spec. - Crash deck spec: sufficient size to prevent people being injured from falling debris, area needed to be covered. - Designs sent back as fire escape routes weren't clear [option C].
30
Campden Hill Towers - Why didn't you include the crash deck design as part of the contractor's design portion in the contract?
- Speed [quicker to go direct to design consultant]. - Only contractor on the project was facade repair specialist [not typical contractor who builds scaffolding]. [Scaffold design consultant, third-party sign off included in spec] - Second phase was to address cladding options (overclad or replace with new) [PAYE direct appointment to CA (no principal contractor)].
31
Campden Hill Towers - What design considerations did you have to make when writing the specification?
- Scaffolding to cover public highway. - Fire escape routes were clear. - Licences from the council to erect crash deck [done via scaffold contractor].
32
Campden Hill Towers - How did you request that amendments were made to the scaffolding design?
- Returned Contractor's Design Document marked 'C' (resubmit with amendments made). [- Have 14 days to respond otherwise automatically marked as 'A'.]
33
Are there any considerations you have to make if you're undertaking substantial repairs to a roof?
- If more than 50% of the roof is replaced the thermal performance must be upgraded to comply with AD L. [U-value requirements provided in AD L for pitched and flat roofs].
34
Can you talk me through the RIBA Stages?
- 0 - Strategic Definition: Define objectives. - 1 - Preparation and Brief: Develop brief and budget. - 2 - Concept Design: Initial designs. - 3 - Spatial Coordination: Planning and regulation compliance. - 4 - Technical Design: Detailed design (spec). - 5 - Manufacturing and Construction: Works on-site. - 6 - Handover: Completion, handover docs. - 7 - In Use: Maintenance (if necessary).
35
What are the British Standards for: - Specifications. - Inclusive environments. - Fire safety. - FRAEW. - Fire alarms/detection. - Scaffolding.
- BS 8000. - BS 8300. - BS 9999. - PAS 9980. - BS 5839. - BS EN 12811.
36
Campden Hill Towers: What RIBA stage was this when you discussed crash decking with a consultant to establish the requirements?
RIBA stage 4: Technical Design.
37
Campden Hill Towers: How did you ensure the crash deck designs were adequate - did you review these?
No, included in the spec that competent third-party had to sign designs off.
38
Campden Hill Towers: Who would have design responsibility for the crash deck?
Design consultant. [Third-party's role is to check not take on responsibility for designs]
39
Campden Hill Towers: Did the cladding removal require planning permission?
Yes, property was in a conservation area.
40
When undertaking design work, how do you ensure it's compliant?
- AD or BS. - Get competent third-party to create spec and sign works off. - BCA to review at the end.
41
Wembley Arena: What are some remediation items you identified and how did you budget?
- Roof leaks [liquid repair]. - Clear gutters. - WC refurb [broken toilets and sinks]. - Redecoration. [- Fluorescent lighting [defective - LEDs recommended].] - Spread the costs across the 10 year reporting period.
42
Campden Hill Towers: What was included in the performance specification for the crash deck?
- General position [cover public highway, fire escapes kept clear, marked up drawing]. - BS EN 12811. - AD A. - CDM Regs. - WaH Regs 2005. - Had to be signed off by competent third-party.
43
Campden Hill Towers: a) What process would you follow if someone got injured after erecting the crash deck? b) Who would be liable?
a) - Notify HSE. [- HSE investigate.] [- Prosecution or fine, enforcement notice, claim from individual injured.] - Rectify cause [if possible]. b) - Design issue: Design consultant [not wide enough]. - Crash deck construction issue: Sacffolding contractor.