Contract admin Flashcards
(101 cards)
What’s the difference between Minor Works and Intermediate contracts?
MW:
- Simple buildings.
- 3 months rectification period.
IC:
- Moderate complexity.
- Clerk of Works.
- Sectional Completion.
What documents are included within contract documents?
- Spec.
- Drawings.
- Prelims.
- Preambles.
[- Payment terms.]
What is the purpose of prelims and preambles?
Prelims:
- Describes the nature of the works.
- Contract details [IVD, LD rate, rectification period, PC date].
Preambles:
- Explanation of the contract e.g. objectives, site information (address etc).
Who are the parties on the contract?
- Employer.
- Contractor.
- Consultants.
What are some key contract events?
- IVD.
- PC.
- Rectification period.
- Final Certificate [ends contractor’s obligations (except for latent defects)].
What are collateral warranties?
An agreement where a third party is covered despite not being part of the original contract.
What’s the difference between Sectional Completion and Partial Possession?
- Sectional Completion is pre-planned.
- Partial Possesion is not pre-planned.
What information is provided within a CPP and what legislation states a CPP is required?
SHES.
- Site information.
- Hazards.
- Emergency procedures.
- Site rules.
- CDM Regulations 2015.
Can you tell me some different types of procurement?
- Traditional (client team).
- Design and Build.
- Management contracting: manages design and works but doesn’t complete works directly (Quinn on Windsor Walk).
What information goes into PCI?
SHED.
- Site information.
- Hazards.
- Emergency procedures.
- Drawings.
Is the Contractor’s Design Portion optional?
Yes.
What’s the alternative to including contractor’s design in a contract?
It could be designed entirely by the client’s side.
What specification would be used for a project designed entirely by the client’s side?
Prescriptive specification.
What information is included when appointing a consultant?
- Works.
- Costs.
- Timeline.
What is a novation agreement?
When one party replaces another and takes on the rights and obligations.
[Substituted contract].
What are the timelines for Interim Valuations?
Application for payment (valuation) by IVD > Interim Valuation Date > Due date (7 days after IVD) > Payment certificate (CA - within 5 days of due date)/Pay less notice (up to 5 days before final payment date) > Final payment date (14 days after due date).
What is the base date?
Date from which fluctuations will apply i.e. inflation rises will be borne by contractor from this point. Typically date of tender returns.
What is the process when a contractor submits an EOT claim?
1) EOT application received from contractor for delay stating Relevant Event.
2) Assessment by CA ‘as soon as reasonably practical’ is best practice (within 12 weeks of notice otherwise).
3) Accept/reject claim [Loss and expense claim based on prelims].
What is the difference between a Relevant Event and Relevant Matter?
Relevant Event: EOT – caused by client or neutral event.
Relevant Matter: money (no time extension) – caused by client.
What is the purpose of Loss and Expense?
To reimburse the contractor for loss suffered in continuing to work.
Client only required to pay for actual loss.
a) When can an employer claim for Liquidated Damages?
b) Does the client need to suffer actual loss to be abe to claim them?
a) When the contractor fails to meet the completion date.
b) No, if contractor misses completion date they can claim LDs.
How are Liquidated Damages paid?
- Payment from contractor
or - Taken from money due [to the contractor].
[Contractor required to pay rate pre-determined in the contract. Calculated as actual loss e.g. loss of rent.]
What is time at large?
No PC date. Contractor no longer bound to complete works by a specific date.
Gray’s Inn Road, London: a) What is Practical Completion?
b) What rule of thumb guide is there on whether to issue PC if snags are outstanding?
a) Works in the contract are substantially complete.
b) It won’t impact occupation.