Contract Administration Flashcards
What is a cost reimbursable contract?
- Sometimes called a cost plus contract
- The contractor is reimbursed the actual costs in carrying out the works, plus a fee
- This may be used on where the scope of the work cannot be properly defined at the outset i.e. fire, emergency alterations or repairs.
- Tendering may include an outline specification, any drawings and an estimate of costs.
- High risk – final cost is not known, the costs for which the contractor is entitled to must be set out very clearly.
What is a lump sum contract?
- A single lump sum price is agreed before the works begin
- Appropriate where the project is well defined and significant changes are unlikely
What is a re-measurement contract?
- Used where design can be described in reasonable detail, but the amount cannot.
- Rates are obtained from tenders and the actual contract sum cannot be determined until completion.
- Allow an early start on site and the client takes the risk for any unknowns.
What is a measured term contract?
- Used where the client has a regular programme of works that they would like to be undertaken by a single contractor
- Generally used for minor works or maintenance works.
- Appointment is based on an agreed schedule of rates
What are your duties as CA?
- Issue contract certificates
- Routinely inspect the works
- Issue instructions
- Evaluate applications for extensions of time
- Evaluate contractor applications for payment, undertake valuations and issue payment certificates.
- Certify completion of the works
What are the differences between MW and IC?
- Use of named sub-contractors
- Listed relevant events and relevant matters
- Sectional completion
- Use of collateral warranties
- Use of bonds
Why did you recommend the use of IC?
- Use of sectional completion
- Use of bonds or warranties
What certificates do you issue?
- Contract instructions
- Payment Certificates
- Extension of time certificate
- Practical completion certificate
- Certificate of making good defects
- Final Certificate
How do you engage named subcontractors?
- Draw up the relevant JCT subcontract – JCT IC Sub-C
What are the procurement routes?
- Traditional
- Design and Build
- Management Contracting
- Construction Management
What is D&B, advantages and disadvantages?
- Advantages
Single point of responsibility
Design and construction can overlap
Risk for design and construction is offloaded to the contractor - Disadvantages
Project becomes cost driven over quality
Requires robust employers requirements
Difficult to compare bids from the tendering contractors
What is traditional, advantages and disadvantages?
- Advantages
Client has full control over the design
Cost certainty before construction commences
- Disadvantages
Longer overall programme duration
High consultants fees
Client takes all design risk
What are the main forms of JCT contract you know?
JCT Intermediate Building Contract, 2016 (+with contractor’s design portion).
JCT Minor Works Building Contract 2016 (+with contractor’s design portion).
JCT Design and Build.
Management Building Contract 2016.
Measured Term Contract 2016.
What kinds of works would be included within the contractor’s design portion of a contract and why?
It is used when the contactor has agreed to design specific parts of the works. They will usually sub-contract the works
whereby a specialist installer or manufacturer is required. Ensures buildability and other factors are taken into account. The
contractor is responsible for the procurement and must adhere to the programme.
Specialist works can include; installation of services, roof replacement etc.
Takes the liability of the design off the client and design team.
What are the responsibilities of a contract administrator
They are not a party to the contract and therefore must remain impartial at all times. Simply there to administer the contract.
Chair pre contract meeting.
Issue contract instructions.
Deal with payment provisions.
Manage change procedures – design changes etc.
Involve with dispute avoidance.
Issue certificates.
Deal with completion / possession issues.
Explain the valuation process and the responsibilities of a contract administrator for a JC intermediate Contract / JCT Minor works contract?
A
Contractor must issue application for payment no later than the valuation date.
Valuation date occurs (stated in contract particulars – will change to closest business day).
Due date (date at which the CA values the works) is 7 days after the valuation date.
Contract administrator must issue a certificate for payment (interim cert) within 5 days after the due date – the cert = the
amount they deem should be paid at the due date.
Final date for payment in standard contract is 14 days from the due date.
If the employer intends to withhold any amount from the sum certified, the they must provide written notice of their intention no later than 5 days before the final date for payment.
Note: The contract gives the contractor the right to submit its own payment application - they are not required to and the CA can undertake the valuation without it.
Note: If the CA doesn’t issue a payment certificate within 5 days after the due date, if the contractor issued an application for payment this becomes a payment notice and acts as the cert, otherwise a contractor can send a payment notice to the CA.
How does the valuation process differ with regards to the JCT Design and Build Contract?
Essentially the same as the JCT intermediate contract BUT – Due dates can change.
If the contractor submits their application for payment before the valuation date, then the due date is still 7 days from valuation
date, but if received after the valuation date then the due date is 7 days from the day of receipt of the AFP.
How could an employer take part of a site back quickly?
By doing sectional completion.
Early possession – note: when early possession utilised the works or
section of are deemed to be at practical completion
regardless.
Acceleration.
What is practical completion? What happens contractually once PC is certified?
There is no definitive definition for the term Practical Completion.
It is when the works are complete to the satisfaction of the Contract Administrator and the contractor has abided with their duties under the CDM regulations.
The CA cannot certify PC where there are outstanding works or patent defects, but they also cannot withhold PC for minor outstanding defects.
HW Nevill (Sunblest) Ltd v William Press & Son Ltd [1981] (the flexible test) – PC will not be prevented where the works have been completed free from patent defects, other than ones to be ignored as diminimus or trifling (very minor in nature).
What is deemed diminmus or trifling will be different for each project / the intended end use – swimming pool analogy.
Once PC is certified:
Start of rectification period.
Liquidated damages cannot be claimed.
Release of half the retention.
Client then claims back possession of the site – insures it etc.
What is partial possession?
Mechanism to allow employer to take early possession of a site.
Contract might have provision for sectional completion to allow partial possession.
Effect of partial possession:
Any part of the works which partial possession is given is deemed to achieve practical completion.
Half retention must therefore be released.
Defects liability begin for that part of the works.
Liquidated damages reduce?
Client is responsible for that part of the works and will need to use its own insurances.
Contractor not obliged to give partial possession but can’t unreasonably withhold it.
Contactor may not wish to give partial possession due to occupants / other contractors on the site holding up works – may
lead to an extension of time application.
What is the difference between a contract being executed as a deed or underhand?
The Latent Damage Act 1986 stipulates the limitation period of building contract is (period for which a claimant can bring proceedings against a contractor):
6 years from completion for contracts signed underhand.
12 years for those executed as a deed.
The act prevents claimants bringing old cases against contractors and encourages them to do so without delay.
See also - The Limitation Act 1980
What contractual processes need to occur with regards to an extension of time?
The contractor is required to notify the CA whenever it becomes reasonably apparent that the progress of the works or any
section of the works is likely to be delayed by a relevant event.
The contractors notification should be in writing and should identify the relevant event that has caused the delay, request that an
extension of time should be granted and then provide details and evidence of causation of the relevant event. They should also
state whether the delay will impact the completion date and if so the amount of delay anticipated.
Contractually the contractor is also required to mitigate the delay even though it isn’t a result of their actions.
CA then analyses the contractors’ request for extension of time and to determine whether the identified relevant event has indeed
caused the delay. If this is found to be the case they must then grant the extension of time and agree a new contractual
completion date.
What are the two broad groups of relevant events? Give some examples of relevant events
Relevant events caused by the employer / relevant events caused by neutral events.
Relevant events caused by the employer: variations and instructions, delays handing over possession of the site, suspension of the contract due to non-payment.
Relevant events caused by neutral events: Force majeure - act of god (war, natural catastrophes), adverse weather conditions, specified perils (fire, floods), civil commotion (acts of terrorism, strikes etc).
What is single stage tendering?
Single stage tendering is a tendering procedure whereby a number of pre-selected contractors submit tenders on a competitive basis.
Each contractor provides a single cost for the whole of the construction works within a predetermined tender period.
Tenders are then analysed in terms of cost and quality before a single contractor is declared the preferred contractor and enters into a building contract with the client.