Contract Practice Flashcards
What is the Construction Act?
Housing Grants Regeneration and Construction Act 1996
What did the Construction Act (1996) introduce?
Introduced regular payment terms for projects more than 45 days long, right to suspend the works, right to adjudicate, and disallowed paid when paid clauses.
When was the Construction Act revised?
The Local Democracy, Economic Development and Construction Act 2009
What were the main changes under the revised Construction Act (2009)?
Amended to:
* Disallow conditional payment clauses such as ‘paid when certified’
* Disallow tolent clauses around adjudication
* Contracts no longer had to be written
What are the different families of contract that you are aware of?
JCT, NEC, FIDIC, ICE
What are some of the differences between NEC and JCT?
NEC:
* Used for building & civil engineering projects
* NEC has different contract strategies that can make it bespoke to the project
* Construction programme forms part of the contractual documentation
* Has additional mechanisms such as early warning notices, risk mitigation meetings and compensation events.
JCT:
* JCT used for building projects only
* JCT has a standard set of clauses
* Construction programme is not a contractual document
What do you consider when you advise the selection of a contract?
- Type of work
- Sector of work
- Procurement route in line with the Client’s key objectives
- Provisions possible under the contract.
What are liquidated damages?
A genuine pre-estimate of the likely loss incurred to the client should the contractor cause the completion date to be missed.
What is an extension of time?
A mechanism that extends the completion date and alleviates the levying of liquidated damages to the contractor when there is a relevant event.
What is a relevant event?
A situation that entitles the contractor to an extension of time.
Can you give some examples of relevant events?
- Variations
- Instructions
- Deferment of possession of site
- Force majeure
- Suspension by the contractor for non-payment
What’s the difference between a relevant event and a relevant matter?
A relevant event entitles the contractor to more time, but not money, while a relevant matter entitles the contractor to additional time and money.
What is a loss & expense claim?
The contractor is entitled to reimbursement for the actual loss and/or expense incurred as a result of the progress of the works being materially affected by a relevant matter.
What did you learn from reading the RICS guidance note on deciding the appropriate JCT contract?
Comparison of contract provisions – how the suitability of a contract changes in line with its provisions.
For example, Minor Works do not have the provision for sections / sectional completion.
Can you name 3 differences between the D&B 2016 and SBC 2016?
- Design responsibility sits with the contractor in D&B but retained by the Employer in SBC
- Terminology differences such as EA vs. CA
- Changes vs. variations.
- The QS and their role are named within the SBC, but not the D&B
- Valuations differ regarding the IVD
In D&B, the due date is pushed out until the Contractor sends a valuatio
What is the QS’ role named within the SBC?
- Valuations
- Variations
- Assess L&E claims
Talk me through how you compiled the contract documents for Acrisure? What did you include?
Used the tender documents to form the basis of the contractual documents
Legal and pricing information:
* JCT contract including the particulars
* Schedule of amendments
* CSA
* General conditions and preliminaries
Employer’s Requirements:
* Design information for each consultant
* Including reports, drawings and specifications
Contractor’s Proposals:
* Contractor’s completed design
* CSA
* Programme
* Clarifications and Exclusions
Landlord / Basebuild Information:
* Tenant Fit Out Guide for the building
* Other LL info such as subdivision plans
What would you typically find included in the Employer’s Requirements?
Design information comprising drawings and specifications.
Can you tell me the time frames for undertaking a valuation?
- Interim valuation date (as stated in the contract particulars)
- My payment recommendation is to be issued +7 days to the due date
- Payment notice is issued +5 days from the due date
- Final date for payment is +14 days from the due date (unamended)
- Pay less notice to be issued -5 days before the final date for payment
What are some typical amendments you would make to the contract?
- Payment terms – final date for payment changes from the default 14 days from the due date to 28 or 30 days.
- Addition of Article 10 which notes that the incorporation of the schedule of amendments prevails over the articles and conditions stated in the JCT.
What are the advantages of having a schedule of amendments?
Can tailor it to the client’s needs and requirements e.g. payment terms to suit their business and their processing team.
What are the disadvantages of including a schedule of amendments?
- Not backed up by case law.
- Could be seen as unfair or favouring one party.
What is Practical Completion? What happens when it is achieved?
- The works are substantially complete subject to minor snags.
- Triggers the release of the first moiety of retention to the contractor.
- Ownership is transferred to the Employer, and the Contractor no longer insures the works.
- Employer insures the works.
- The rectification period commences.
What factors did you consider when advising the client on the most appropriate contract?
- Procurement route
- Nature of the project
- The scope of works
- Measure of control by the client
- My client’s key objectives