Contract Practice - Level 1 Flashcards
(167 cards)
What key function does a contract perform on a construction project?
Defines the parties rights and obligations in the project
What is a contract?
A legally binding promise between two or more parties to fulfill an obligation in return for consideration
A basic binding contract should comprise four key elements: offer, acceptance, consideration and intention to create legal relations
Define express terms?
Express terms are terms of agreement which are expressly agreed between parties, ideally they will be written down in a contract between the parties but where the contract is agreed verbally they will the terms discussed and agreed between the parties.
Define implied terms?
A contractual term that has not been expressly agreed between the parties but has been implied into the contract either by common law or by statute
What six conditions need to be met for a contract to be in place?
1) offer
2) Acceptance
3) consideration
4) intent to create legal relations
5)
6)
What is tort?
a civil wrong that causes a claimant to suffer loss or harm, resulting in legal liability for the person who commits the tortious act.
What are the influences which will affect contract selection?
Cost / time / quality
Risk
Contract value
Can you name three standard forms of contracts that can be used on a construction project?
JCT
NEC
FIDIC
What do you understand about the following forms of contract;
FIDIC
JCT
NEC
FIDIC - largely used internationally
JCT - most commonly used in UK
NEC - more widely used in government contracts, promotes collaborative working
What does JCT stand for?
Joint Contract Tribunal
Name the key components of the JCT contract suite.
Domestic contract
Minor works
Intermediate
Standard
D&B
Major projects
When was the JCT contract suite last updated?
2024
Tell me about some of the key changes that were made.
Added
- sustainability
- collaborative working
- notification and negotiation of disputes
- extension of time and unforeseen conditions
- focus on building safety
- modernised and streamlined
Added JCT Target Cost Contract
How does JCT facilitate electronic working?
JCT electronic version - download and amend
How does the JCT work alongside the Construction Playbook?
JCT have produced a pdf flowchart to show how JCT contracts delivers Construction Playbook policies and activities.
Construction Playbook sets 14 key policy areas and key activities within procurement stages.
JCT
How has the JCT contract suite incorporated diversity and inclusion?
The 2024 suits adopts gender-neutral language
What is the JCT Fluctuations Hub used for?
JCT contracts have fluctuations provisions to allow price increase and decrease through construction programme. Aim is to transfer risk from contractor to employer.
Mechanism for dealing with inflation.
The JCT Fluctuations Hub seems to be information resource - collection of articles and learning resources.
Explain the JCT Target Cost Contract to me.
Introduces option for parties who want to use target cost and difference sharing arrangements. Instead of lump sum the method of renumeration is payment of Allowable Cost of works plus a Contract Fee and if applicable a difference share calculated in accordance with contract.
What form of NEC contract might the Target Cost Contract be a good alternative for?
NEC Target Cost contract
What are the main parts of the JCT contracts?
Agreement:
Recitals
Contract particulars
Attestation
Condtions:
1 - Definitions & Interpretation
2 - Carrying out Works
3 - Control of Works
4 - Payment
5 - Changes
6 - Injury, Damage, Insurance
7 - Assignment, performance bonds etc
8 - Termination
Schedules
What are the JCT schedules?
1 - 6 Supplemental provisions
Schedule 1 - Design Submission
Schedule 2 - Supplemental
Schedule 3 - Insurance options
Schedule 4 - Code of Practice
Schedule 5 - Third party rights
Schedule 6 - Form of Bonds
How are relevant events and relevant matters dealt with under NEC?
They are referred to as compensation events and dealt with differently as they are dealt with as soon as possible together rather than being left to the end of the contract.
How does NEC deal with loss and expense?
Dealt with as whole with the compensation event - the issue is reviewed by engineer and parties work collaboratively to resolve.
What types of insurance are required under JCT?
Option A - contractor takes out and maintains joint names all risk insurance
Option B - Employer takes out and maintains joint names all risk insurance for new building
Option C - Refurbishment/alterations to existing structures - Employer takes out and maintains joint name all risk for works
What is all risk insurance? - protection against physical loss or damage to the works
What are specified perils? - fire, explosions, earthquakes, flooding etc