Procurement and Tendering Level 1 Flashcards
(99 cards)
What guidance is available relating to procurement and tendering?
RICS professional guidance: Tendering Strategies 1st edition
Developing a construction procurement strategy and selecting an appropriate route 2nd ed
E-tendering
What are the differences in procurement between JCT standard and JCT with contractor’s design
In addition to the tender documents for JCT standard (BOQ or other pricing doc, preliminaries, design information)
In addition for the JCT with contractors design (employers requirements for CDP items).
What do you understand by pre-qualification
An initial state before an invitation to tender.
Pre-screening potential contractors against criteria to ensure they have capacity and capability.
Often is a pre-qualification questionnaire
What types of tendering are you aware of?
- Single stage
- Two stage
- Negotiated
What do you understand by serial tendering
In the RICS practice guidance on Tendering Strategies describes serial tendering as:
A hybrid/advanced method of tendering combining normal competitive tender (single or two stage) with negotiation.
Often used for clients who have a number of phases of similar work.
What do you understand by single stage tendering
RICS guidance tendering strategies describes single stage tendering as most common type of tendering strategy for obtaining price for whole construction works.
Invitation to tender docs issued to several competing contractors who all have chance to bid for project based on identical tender docs.
Usually done at RIBA stage 4 so contractors receive most detailed information to base their bid on.
What do you understand by two stage tendering
RICS guidance tendering strategies describes two stage tendering as being used where time is constrained as it enables design and tendering to overlap or where design process would benefit from technical input of contractor in later design stages.
First stage tender docs issued at RIBA stage 2 or 3. Instead of a bid for constructing the whole project, contractor is selected on basis of quality of their bid, quality of their team and preliminaries price and OHP allowances.
Contractor joins team to complete design to RIBA stage 4.
What are the main factors that govern procurement route selection
Choosing most suitable tender strategy:
All three types of tender selection can be used for any procurement route but some more suitable than others.
2 stage useful if quick start on site required as tendering and design can overlap.
Traditional project design more advanced before tendering. Contractor not responsible for design so single stage ok.
D&B projects pass larger proportion of risk and design responsibility to contractor so 2 stage tender can benefit from contractors understanding of the project.
How do single and two stage tenders differ?
Design info available (RIBA Stage)
Basis for selection
What do you understand by procurement?
Procurement refers to the process of acquiring materials and services for project
What is the difference between procurement and tendering
Procurement encompasses the overall process of acquiring goods and services for a project and includes deciding the strategy on how those goods are to be acquired by reviewing clients requirements (time, quality and cost) and their attitude to risk.
Tendering is specifically the process of inviting and evaluating the bids for construction work:
IE - bidding process to obtain a price and
- how contractor is actually appointed.
What procurement options are you aware of?
Types of procurement strategy :
- Traditional (lump sum)
- Traditional (remeasurement or measure and value)
- D&B
- Construction management
- Management contracting
- Partnering
What are some of the benefits and pitfalls of the procurement options identified?
Traditional:
Pros - competitive fairness
- client control of design quality and performance
- reasonable price certainty at contract award
Disadv - if design not complete when tendered can lead to less certainty and can cause expensive disputes
- overall project duration may be longer as tender takes time
- no input into design or planning by contractor
D&B:
Pros: client risk reduced due to single point responsiblity
- integrated constructor contribution to project planning
- price certainty obtained before project commences
Disadv: - clients may find difficult to prep adequate ERs
- client commits to concept design at early stage
- bids difficult to compare
- no design evaluation
Which procurement option carries the most client risk?
Depends what type of risk - RICS practice guidance “Developing construction procurement strategy” refers to the different categories of risk which could include:
- strategic risk (failure to getting planning permission, or funding)
- external risk (changes in environment)
- project risk (overspend or delay to programme)
- discovery risk (poor ground condition etc)
When is a contract formed during procurement and tendering?
Contract is formed when offer is accepted and terms agreed - when contract signed
Explain the Find a Tender (FTS) e-tendering platform
It is a platform where high value contracts in UK public and utility sectors are advertised.
It replaced the EU Tenders Electronic Daily on 1 Jan 2021.
High value is usually above £139,688 (incl VAT).
When do tenders need to be legally posted on FTS
Public Contracts Regs 2015 -
Central Governmt £10,000 net VAT
Sub-central authorities and NHS trust £25k net VAT
What is your understanding of the traditional procurement route?
Described in RICS practice guidance: Developing a Construction procurement strategy”
Design is usually completed before competitive tenders invited (RIBA stage 4)
Client will usually select and appoint design team prior to contractor
Contractor usually selected on best value - not always lowest price
Contractor assumes responsibility and financial risk for construction works to design produced by clients design team.
Client take responsibility and risk for design and performance of design team.
What are the strengths of the traditional procurement route?
RICS guidance “developing construction procurement strategy”
- competitive fairness (all bids on same basis)
- process is design led and client has direct influence (high quality and design)
- reasonable price certainty
- where public expenditure or audit demands are rigid - satisfactory strategy in terms of public accountability
- well know procedures
- change possible
What are the weaknesses of the traditional procurement route?
RICS guidance “developing construction procurement strategy”
- if process is sped up through tender (design not complete) can result in less cost and time certainty and lead to dispute
- overall project duration longer
- little or no input into design or planning by contractor
- strategy based on price competition may lead to adversarial relationship
- designers and contractor have little incentive to advise the client on factors that may benefit operational costs of completed facility.
What is your understanding of the design and build procurement route?
- contractor assumes risk and responsibility for designing and building project
- ## client employ design team to carry out preliminary design work and prepare project brief including employers requirements
What are the strengths of D&B procurement route?
- client only has to deal with one firm (single point responsibility)
- client risk reduced due to single point responsibility
- integrated constructor contribution to design and project planning
- price certainty generally obtained before construction starts
- total project time may be reduced as design and tender can overlap
What are the weaknesses of D&B procurement route?
- difficulties can be experienced in preparing adequate brief or defining exactly what required
- client required to commit to concept design at early stage
- bids are difficult to compare as design may vary
- no design evaluation
- client changes to scope of project can be expensive
- design liability is limited by standard contracts available
- quality may be compromised
What is your understanding of the construction management route?
RICS practice guide “Developing a construction procurement strategy”
- client doesn’t allocate risk and responsibility to single main contractor
- client employs design team - construction manager is engaged as a fee-earning professional to manage, programme and co-ordinate the design and construction activities and facilitate collaboration.
Construction work is carried out by individual trade contractors often specialists through direct contacts with client for distinct trade or work packages