Procurement and Tendering Level 1 Flashcards

(99 cards)

1
Q

What guidance is available relating to procurement and tendering?

A

RICS professional guidance: Tendering Strategies 1st edition
Developing a construction procurement strategy and selecting an appropriate route 2nd ed
E-tendering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the differences in procurement between JCT standard and JCT with contractor’s design

A

In addition to the tender documents for JCT standard (BOQ or other pricing doc, preliminaries, design information)
In addition for the JCT with contractors design (employers requirements for CDP items).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What do you understand by pre-qualification

A

An initial state before an invitation to tender.
Pre-screening potential contractors against criteria to ensure they have capacity and capability.
Often is a pre-qualification questionnaire

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What types of tendering are you aware of?

A
  • Single stage
  • Two stage
  • Negotiated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What do you understand by serial tendering

A

In the RICS practice guidance on Tendering Strategies describes serial tendering as:
A hybrid/advanced method of tendering combining normal competitive tender (single or two stage) with negotiation.
Often used for clients who have a number of phases of similar work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What do you understand by single stage tendering

A

RICS guidance tendering strategies describes single stage tendering as most common type of tendering strategy for obtaining price for whole construction works.
Invitation to tender docs issued to several competing contractors who all have chance to bid for project based on identical tender docs.
Usually done at RIBA stage 4 so contractors receive most detailed information to base their bid on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What do you understand by two stage tendering

A

RICS guidance tendering strategies describes two stage tendering as being used where time is constrained as it enables design and tendering to overlap or where design process would benefit from technical input of contractor in later design stages.
First stage tender docs issued at RIBA stage 2 or 3. Instead of a bid for constructing the whole project, contractor is selected on basis of quality of their bid, quality of their team and preliminaries price and OHP allowances.
Contractor joins team to complete design to RIBA stage 4.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the main factors that govern procurement route selection

A

Choosing most suitable tender strategy:
All three types of tender selection can be used for any procurement route but some more suitable than others.
2 stage useful if quick start on site required as tendering and design can overlap.
Traditional project design more advanced before tendering. Contractor not responsible for design so single stage ok.
D&B projects pass larger proportion of risk and design responsibility to contractor so 2 stage tender can benefit from contractors understanding of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How do single and two stage tenders differ?

A

Design info available (RIBA Stage)
Basis for selection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What do you understand by procurement?

A

Procurement refers to the process of acquiring materials and services for project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the difference between procurement and tendering

A

Procurement encompasses the overall process of acquiring goods and services for a project and includes deciding the strategy on how those goods are to be acquired by reviewing clients requirements (time, quality and cost) and their attitude to risk.
Tendering is specifically the process of inviting and evaluating the bids for construction work:
IE - bidding process to obtain a price and
- how contractor is actually appointed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What procurement options are you aware of?

A

Types of procurement strategy :
- Traditional (lump sum)
- Traditional (remeasurement or measure and value)
- D&B
- Construction management
- Management contracting
- Partnering

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are some of the benefits and pitfalls of the procurement options identified?

A

Traditional:
Pros - competitive fairness
- client control of design quality and performance
- reasonable price certainty at contract award
Disadv - if design not complete when tendered can lead to less certainty and can cause expensive disputes
- overall project duration may be longer as tender takes time
- no input into design or planning by contractor
D&B:
Pros: client risk reduced due to single point responsiblity
- integrated constructor contribution to project planning
- price certainty obtained before project commences
Disadv: - clients may find difficult to prep adequate ERs
- client commits to concept design at early stage
- bids difficult to compare
- no design evaluation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which procurement option carries the most client risk?

A

Depends what type of risk - RICS practice guidance “Developing construction procurement strategy” refers to the different categories of risk which could include:
- strategic risk (failure to getting planning permission, or funding)
- external risk (changes in environment)
- project risk (overspend or delay to programme)
- discovery risk (poor ground condition etc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When is a contract formed during procurement and tendering?

A

Contract is formed when offer is accepted and terms agreed - when contract signed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Explain the Find a Tender (FTS) e-tendering platform

A

It is a platform where high value contracts in UK public and utility sectors are advertised.
It replaced the EU Tenders Electronic Daily on 1 Jan 2021.
High value is usually above £139,688 (incl VAT).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

When do tenders need to be legally posted on FTS

A

Public Contracts Regs 2015 -
Central Governmt £10,000 net VAT
Sub-central authorities and NHS trust £25k net VAT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is your understanding of the traditional procurement route?

A

Described in RICS practice guidance: Developing a Construction procurement strategy”
Design is usually completed before competitive tenders invited (RIBA stage 4)
Client will usually select and appoint design team prior to contractor
Contractor usually selected on best value - not always lowest price
Contractor assumes responsibility and financial risk for construction works to design produced by clients design team.
Client take responsibility and risk for design and performance of design team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What are the strengths of the traditional procurement route?

A

RICS guidance “developing construction procurement strategy”
- competitive fairness (all bids on same basis)
- process is design led and client has direct influence (high quality and design)
- reasonable price certainty
- where public expenditure or audit demands are rigid - satisfactory strategy in terms of public accountability
- well know procedures
- change possible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the weaknesses of the traditional procurement route?

A

RICS guidance “developing construction procurement strategy”
- if process is sped up through tender (design not complete) can result in less cost and time certainty and lead to dispute
- overall project duration longer
- little or no input into design or planning by contractor
- strategy based on price competition may lead to adversarial relationship
- designers and contractor have little incentive to advise the client on factors that may benefit operational costs of completed facility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is your understanding of the design and build procurement route?

A
  • contractor assumes risk and responsibility for designing and building project
  • ## client employ design team to carry out preliminary design work and prepare project brief including employers requirements
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are the strengths of D&B procurement route?

A
  • client only has to deal with one firm (single point responsibility)
  • client risk reduced due to single point responsibility
  • integrated constructor contribution to design and project planning
  • price certainty generally obtained before construction starts
  • total project time may be reduced as design and tender can overlap
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What are the weaknesses of D&B procurement route?

A
  • difficulties can be experienced in preparing adequate brief or defining exactly what required
  • client required to commit to concept design at early stage
  • bids are difficult to compare as design may vary
  • no design evaluation
  • client changes to scope of project can be expensive
  • design liability is limited by standard contracts available
  • quality may be compromised
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is your understanding of the construction management route?

A

RICS practice guide “Developing a construction procurement strategy”
- client doesn’t allocate risk and responsibility to single main contractor
- client employs design team - construction manager is engaged as a fee-earning professional to manage, programme and co-ordinate the design and construction activities and facilitate collaboration.
Construction work is carried out by individual trade contractors often specialists through direct contacts with client for distinct trade or work packages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What are the strengths of the construction management route?
- relative time-saving potential for overall project time (overlapping design and construction process) - trade contractors and construction manager contribute to design and planning project - roles, risks, relationships are clear for all participants - changes in design can be accomodated later than with some other routes, provided design packages not let
26
What are the weaknesses of the construction management route?
- price or time certainty not achieved until last trade packages have been completed - client needs to be informed and proactive - client must provide good quality brief to design team - route relies on client selecting a skillful committed team - close time and information control required - relies on proficient and committed construction manager
27
What is your understanding of the management contracting route?
RICS practice guide "Developing Construction Procurement Strategy" - management contractor engaged by client to manage whole building process. Contractor paid fee on top of construction costs for managing Different to construction management as management contractor has contractual links with works contractors. Employer has no contractual link with works contractor
28
What are the strengths of the management contracting procurement route?
- programme benefits due to overlapping design and construction process - enables management contractor and works contractors to contribute to design and project planning - changes can be accommodated provided the packages affected have not been let
29
What are the weaknesses of the management contracting procurement route?
- the client must provide a good quality brief to the design team; design will not be complete until the client has committed significant resources to project - poor certainty of price if offered at an early stage and potential cost commitment depends on design team estimates - relies on good quality and committed management contractor - route reduces resistance to works contractors claims where such demands are passed on to the client by the management contractor - design must be closely managed -
30
What is your understanding of the public private partnership (PPP) procurement route?
Arrangement where project or service is provided by private sector in partnership with public sector. Long term contractual relationship between public and private sector parties (usually 25 -30 years) Private sector agree to finance and build and operate facility (eg hospital, school, road or prison).
31
What are the strengths of the public private partnership (PPP) procurement route?
- infrastructure project can be obtained without placing a capital burden on public purse - transfer of risk to private sector
32
What are the weaknesses of the public private partnership (PPP) procurement route?
- it may be considered to be relatively expensive approach when compared with other routes - costs of preparing bids can be exceptionally high - government is committed to making payment for the life of concession unless income flow is entirely dependent on cash tolls.
33
Name three of the criteria that need to be considered before selecting a procurement route
performance price time
34
What robust tendering techniques do RICS say can help ensure a positive tender result?
35
Name 3 of the items that RICS say that a robust tendering technique provides?
1. Accountability 2. Auditability 3. Ensuring everything has been picked up 4. Parity 5. Helping to reduce claims of corruption 6. Ensuring correct price has been paid for proposed works
36
Name 3 key steps to good procurement management?
37
What are the 5 major steps in a procurement plan?
38
Explain your understanding of the impact of contractual relationships on the procurement route
39
Explain the roles and relationships of the parties under the various procurement routes.
40
What forms of procurement route are available that allow an early start on site?
"Developing a procurement strategy" suggests any of the routes that allow process of design and tender selection to overlap EG D&B or a management contracting route.
41
How does the procurement route chosen affect cost certainty?
RICS guidance "developing a construction procurement strategy" - traditional should produce cost certainty at end of tender stage provided design was sufficiently complete - D&B also more cost certainty but harder to introduce changes - Management contracting - less certainty until all packages have been let.
42
What methods of procurement are available to reduce confrontation?
Anything that introduces collaboration and removes adversarial nature of tendering - D&B Partnering
43
Explain your understanding of the following terms: time certainty
Time certainty is having an agreed duration for a project. For example JCT intermediate contract includes commencement and completion date and has penalties for contractor if doesn't complete on time
44
Explain your understanding of the following terms: quick start
Quick start means that contractor can commence work on site as soon as possible. Achievable with two stage tendering, particularly if D&B is used so that design can be completed whilst early stages start
45
Explain your understanding of the following terms: earliest finish
The shortest duration of procurement and construction - so any procurement / tendering strategy where there is overlap between processes and where contractor is involved in planning / timing
46
Explain your understanding of the following terms: cost certainty
A route where an agreed fixed price is agreed.
47
Explain your understanding of the following terms: cost control
Cost control means that there is a method of dealing with valuation of changes and risk
48
Explain your understanding of the following terms: competition
In terms of tendering competition means that there is more than one company bidding for the project
49
How can you demonstrate value for money?
By following a competitive tender route, analysing tender returns and reporting to client
50
How do you ensure diligent quality and change management is implemented?
By selecting an appropriate contract that includes procedures for quality and change management
51
How do you allocate risk?
Risk is allocated through the contract selection - which party is financially responsible for dealing with risk occurrences
52
How do you manage risk?
Identify risk - risk register Allocate risk - use of contract
53
What do the following mean; single stage tendering
Tender package is prepared and sent out to list of contractors at the same time. They all receive the same information and are given set period of time to price the pricing document (BQ or schedule or work)
54
What do the following mean; two stage tendering
First stage tender enquiry issued to bidding contractors at RIBA stage 2 or 3. Rather than requesting bid for constructing whole project contractor chosen on basis of quality of bid, quality of team and preliminaries price and OHP allowances. Selected contractor joins design team and assists with completing design to RIBA stage 4 and putting in bid for works at this stage.
55
What do the following mean; negotiated tenders?
effectively single stage tender with single contractor who returns initial price. This is negotiated with clients professional team. Benefit is speed with which price can be obtained, however, competitive advantage of formal bidding process is compromised
56
When and why would you use: - single stage tender - two stage tender - negotiated tender
Single stage - design completed to advanced stage (RIBA 4), most competitive price Two stage - increased contractor involvement with design, reduces timeframe for appointment Negotiated - most contractor involvement in design process, no programme implications. Lack of competitiveness.
57
Explain what tendering means.
It is an important phase in the procurement strategy but involves more than obtaining a price. - it is the bidding process to obtain a price - how a contractor is actually appointed.
58
What rules do you tender under?
JCT tender practice note 2017
59
What processes might this involved?
Procurement Act - advertising contract and following relevant process
60
How do you compile a tender list?
Practice guidance advises: - project teams to start considering suitable contractors as soon as project begins, may be on basis a previous experience, word of mouth or from meetings & presentations from contractors looking to secure new work. - open tendering - allows anyone to express interest - selective tendering - can be shortlist drawn up by project/client team or may be from pre-agreed framework / approved-suppliers list. - single contractor selection - works hand in hand with negotiation as tender technique. Shortlist of one.
61
How do you undertake pre-qualification?
A formal pre-qualification questionnaire (PQQ) depending on size and complexity of project. Work out if project is one that Procurement Act refers to.
62
Explain how you prepare tender documentation.
Choice of procurement route and contract type will have direct effect on how the tender documents are compiled. Under traditional contract - design information - BoQ / schedule of works / schedule of rates and preliminaries In D&B contract will include employers requirements
63
How do you deal with errors in tenders?
RICS guidance : - full arithmetical check for pricing side of tender return - logic check for rest of tender Apart from obvious arithmetical errors key issues to be aware of are: - obvious errors in programme dates - qualifications that render tender null and void - conflicts of interest JCT practice note dictates course of action if arithmetical errors exist.
64
Why is there wording in the tender documents that says the client is not bound to accept the lowest tender?
RICS guidance - lowest tender may not be only consideration.
65
How long would a typical tender period be and why is this the case?
Varies on project by project basis - important to give contractors a suitable period to respond to tender enquiries. Key factors include - - complexity of project - size of project - time of year - market conditions
66
Does a tender always represent actual cost?
No, may be design changes post tender. Client may decide to omit or add to scope of project. Certain aspects of tender may be negotiated.
67
How do you issue tender documents?
Traditional issue: all docs assembled into identical packages and issued by post at same time. Online e-tendering: online tendering portal that issue, track and provide portal for queries and return of tender.
68
Explain your understanding of e-tendering.
RICS guidance - E-tendering - electronic issuing and receipt of any tender documentation in electronic format as part of the procurement process.
69
What RICS guidance are you aware of relating to this?
RICS practice guidance : Etendering 2nd edition
70
Explain how you would manage the tender process.
Follow RICS guidance from Tendering Strategies : Consider how project-specific factors / abnormals influence a tender. 1. Does client have internal procedures to follow that need to be included in tender docs 2. Any land ownership issues that tenderers should be aware of? 3. Any non-working times tenderers should be aware of when producing their programme. 4. Any third party agreements to be aware of 5. Any concurrent activities on site (enabling works, furniture, fitout contracts) that may affect programme? 6. Has phasing of project been properly set out in project information.
71
Explain tender opening procedures you are aware of.
RICS guidance - Tender Strategies "Receiving tenders" - When tender sent out include time, date and location for tenders to be submitted. Should name person to address returns to. - once due date and time elapses no other tender return should be considered as part of opening process. - late tenders not considered on public procurement projects / private clients should give explicit instructions to include late tender returns. - Tender opening form should be used. Have second professional present to witness opening. Each tender opened and general raw info noted on tender opening form. - tender price - proposed programme - key comments/exclusions - alternative tender offers - confirmation that all docs submitted (or not) Tender opening schedule should be signed and dated by all present.
72
How would you evaluate a tender?
RICS guidance on procurement and tendering provides a framework for tender analysis, based on RIBA plan of work stages and RICS Code of Practice for tendering 2012. If public project - follow Procurement Act rules to ensure fair and transparent selection and award of contracts
73
How would you deal with an error?
JCT tendering practice note - sets out process (should also be noted in tender instruction). Basic options - allow contractors to correct their error or for contractors to stand by their price. Any other errors identified should be notified to contractor asap so that they can clarify / resolve issue. If can't then they will be discounted from tender process.
74
How do you deal with qualifications?
Carefully review / consider qualification. These need to be issued to design team, project manager and client for comment.
75
Explain what you would include when compiling a tender report.
Following full analysis and tender interviews produce full post-tender estimate. Take the equalised tender figures from each contractor and add on other cost centres to show full project post tender estimate. The appropriate scoring mechanism should be approled to come up with overall score for pricing element on tender. Qualitative assessment should then be completed in line with agreed scoring mechanism. Before publication draft scoring should be discussed with team and client and any necessary amendments made. Once decision has been reached findings should be included in full tender report with recommendation for award of contract.
76
What are the main methods of choosing a contractor?
Single stage tendering Two stage tendering Negotiated
77
What are the procedures for tendering?
Choose which type & how to identify potential contractors to issue tender to. Assess suitable tender period Produce/compile tender documents Issue documents Review returns Interviews Report & Select
78
On what grounds would you re-tender?
79
Explain the rules of tendering you are aware of. e.g. codes of practice or procedures
Procurement Act RICS guidance on procurement and tendering RICS code of practice for tendering
80
What regulations govern the client during the tender process?
Procurement Regulations 2024
81
What public sector EU or international regulations relate to the tender process?
EU Directives on public procurement
82
Explain your understanding of the Government Construction Playbook in relation to the procurement of public works projects.
Key policies and guidance on how public works projects and programmes are assessed, procured and delivered
83
What is PAS 91 used for?
PAS 91 was a standardised pre-qualification questionnaire which was designed to simplify the bidding process for subcontractors in construction
84
What is electronic tendering?
Definition in RICS guidance Etendering - is that it is the preparation of tender documents in electronic format and introduction of RICS eTendering system. Relates to the management of contractor selection and price setting processes as part of the procurement of construction work.
85
Do you know of any e-tendering services?
RICS Etendering system.
86
What are the advantages of e-tendering?
Reduction of waste particularly in production of multiple copies of paper-based information, leads to less environmentally demanding and more sustainable tender process. Plus: Simplifies the process Reducing costs Avoid need for double / triple entry of same information Enables fairer assessment (avoids post issues and timing)
87
What is online bidding?
Use of an online portal to bid for projects
88
What is the aim of procurement law (in relation to public sector procurement) ?
To ensure fair process for selection and appointment of contractor for public funded projects
89
Explain the key provisions of the Procurement Act 2023 to me.
- Simplified procurement procedures - Enhanced transparency - Greater focus on social value - Prompt payment requirements - Introduces central debarment list
90
What legislation does the 2023 Act repeal?
Public Contracts Regs 2015 Defence and Security Public Contract Regs 2011 Utilities Contracts Regs 2016 Concession Contract Reg 2016
91
What is the purpose of the 2023 Act?
Introduce greater flexibility, transparency and accountability. Replace several piecemeal acts and EU legislation
92
What procurement activities does the 2023 Act cover?
public and utilities procurement in E&W
93
What are the notice requirements under the 2023 Act?
Pipeline notices Pre-market engagement notices Tender notices Transparency notices Contract change notices Performance notices Contract Termination notices Contract Award notices
94
How can a contract be modified under the 2023 Act?
Changes can only be made if they are permitted under various safe harbours. Allows changes that are not substantial or low value New rules allowing for increase / decrease in contract term by up to 10% Changes which result from materialistation of known risk (eg technology changes)
95
What are the main forms of procurement in construction?
Traditional D&B Contract management Management Contracting Partnering Public private partnerships
96
How is procurement impacted by public / private client requirements?
If the project is public funded must follow rules. Private procurement client can set rules to a degree, need to clearly define what project objectives are from outset.
97
How do time, cost, quality and risk impact procurement route selection?
The choice of procurement route is largely dependent on clients required balance of cost quality and time risks for the project. To establish the procurement strategy the team needs to establish what the client's attitudes and key drivers are, and needs to state them in a way and language that is understood by whole project team.
98
How do time, cost, quality and risk impact tender method selection?
The choice of tender method is largely dependent on clients required balance of cost quality and time risks for the project. To establish the procurement strategy the team needs to establish what the client's attitudes and key drivers are, and needs to state them in a way and language that is understood by whole project team.
99
What is a procurement strategy? What is the difference between a procurement and contract strategy?
RICS guidance on developing procurement strategy defines procurement strategy as identifying the best way of achieving the completion of a construction project - often taking into account the best value for money over the entire life cycle of the building or facility. Aim is to achieve optimum balance of risk, control and funding for a project. Choice of procurement strategy largely depends on client's required balance of cost quality and time risks. Contract strategy is about selecting the best and most appropriate contract for the parties - one part of the procurement strategy.