Cost Flashcards
(61 cards)
navigate. Project Cost Management is primarily concerned with the cost of the resources needed to complete project activities. The processes of Project Cost Management include:
a. Project execution, budget planning, force field analysis, visioning
b. Estimating costs, root-cause analysis, brainstorming, problem solving
c. Visioning, fishbone diagramming, gap analysis, controlling costs
d. Plan cost management, estimate costs, determine budget, control costs
D. Project Cost Management includes the following four processes: Plan Cost Management, Estimate Costs, Determine Budget, and Control Costs.
Defining how costs will be estimated, budgeted, managed, monitored, and controlled is part of which of the following processes?
a. Project Integration Management
b. Project Time Management
c. Plan Cost Management
d. Select Financial Metrics
C. Plan Cost Management is the process defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.
navigate. Marsha is a new project manager and is working on determining her project budget. Because this is her first project, she wants to make certain that she doesn’t go over budget. In order to keep everything well organized, she has decided to begin by establishing the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. In which of the following processes is Marsha involved?
a. Determine Budget
b. Control Costs
c. Estimate Costs
d. Plan Cost Management
The best answer choice is D because the question defines Plan Cost Management.
A component of a project or program management plan that describes how costs will be planned, structured, and controlled is called:
a. Activity cost estimates
b. Basis of estimates
c. Cost management plan
d. Spend plan
C. The cost management plan describes the structure and criteria that will be used for cost planning, estimating, budgeting, and reporting.
navigate. Your company is in the process of estimating costs for the manufacture of a new concept aircraft navigation system. Initial estimates, based on manufacturing 200 of these units, was calculated at a fixed cost of $40,000 for tooling and a cost of $2,500 per unit. Market demand has risen above the original estimate, and the company has decided to produce 50 additional units. This has resulted in an increase of $300 additional cost per unit. Based on the new figures, and assuming the initial fixed cost for tooling remains the same, what is the estimated cost to manufacture 250 units?
a. $550,000
b. $560,000
c. $740,000
d. $700,000
The best answer choice is c. In order to calculate this problem, the sum of fixed cost plus variable cost is multiplied by the final number of units. In other words, $40,000 + [(2,500 + $300) × 250] = $740,000.
navigate. When estimating costs, project budgets typically include management reserves as well as contingency reserves. Select the option below that is true regarding management reserves.
a. They are seldom included in the funding requirements
b. They are included to cover unapproved changes
c. They are a factor in determining Earned Value
d. They are not part of the cost baseline
The best answer choice is D because management reserves are not included when creating the cost baseline.
navigate. Tim is working on the cost estimate for his project. Because he is in the early phase of this project, he will develop a Rough Order of Magnitude (ROM) estimate. What is the expected degree of accuracy?
a. –25% to +75%
b. –5% to +10%
c. –25% to +25%
d. –50% to +25%
The best answer choice is A. The ROM typically varies between a –25% and a +75% accuracy.
navigate. Estimating costs is the process of determining the total cost for completing the project, and the accuracy of these estimates will increase as the project progresses. While working on a cost estimation for your new project, you have been asked to provide a Rough Order of Magnitude (ROM). What is the expected degree of accuracy using this type of estimate?
a. –10% to +25%
b. –50% to +50%
c. –5% to +10%
d. –25% to +50%
The best answer choice is B because ROM estimates typically vary by + or – 50%
navigate. Estimate Costs is the process of developing an approximation of the cost of resources necessary to complete project work. Which of the following tools and techniques is NOT used to estimate costs?
a. Analogous estimating
b. Parametric estimating
c. Bottom-up estimating
d. Cost aggregation
D. Cost aggregation is a technique used to develop the cost baseline.
navigate.You’ve just provided a 1,000-hour rough order of magnitude estimate at the beginning of a project. Based on studies that have been done, what would be the expected accuracy of this estimate?
a. –5% to + 10%
–b. 10% to + 25%
c. –25% to + 75%
d. It is not possible to provide an estimate at this time
C. A rough order of magnitude estimate done in the beginning of a project will have an accuracy range of –25% to + 75%.
navigate. Many projects require the project manager to manage both direct and indirect costs. Which of the following is an example of an indirect cost?
a. Expenses incurred for travel to the project location
b. Costs for purchasing materials and supplies necessary to complete a project
c. Overhead for the portion of the office you occupy
d. Payments to contractors hired to perform work on your project
C. Indirect costs are those costs not directly attributable to a project, such as overhead, management salaries, and so on.
navigate. Parametric, analogous, and bottom-up are estimating tools and techniques that are used in which of the following processes?
a. Plan Cost Management
b. Determine Budget
c. Estimate Costs
d. Control Costs
The best answer choice is C because the estimating techniques listed are tools and techniques of the Estimate Costs process
As project manager, you have an allocation of time or money in the schedule or cost baseline for known risks with active response strategies. By definition, this is your ______________________.
a. Slush fund
b. Contingency reserve
c. Management reserve
d. Funding limitation
B. Your contingency reserve is within the control of the project manager and is used for project risks.
You are managing a project that has a work package having a lot of risk and uncertainty associated with it. Knowing this, what type of estimate should you produce?
a. Bottom-up
b. Analogous
c. Parametric
d. Three-point
D. A three-point estimate accounts for high-level risk and uncertainty
navigate. You’ve been asked to produce an estimate for a newly approved project. Because the estimate is for a customer, it needs to be as accurate as possible. Although it will some take time, the best estimate you can provide will be through the use of which of the following estimating techniques?
a. Parametric
b. Analogous
c. Three-point
d. Bottom-up
D. A bottom-up estimate is the most accurate estimate. It also takes the most time to prepare
The advantages of analogous estimating include how easy it is to perform and the fact that you can create the estimate without a lot of detailed information. A disadvantage would include what?
a. It can be used only when projects are similar in fact, not just in appearance.
b. A computer program is needed.
c. Interaction costs may be overlooked.
d. It is time consuming
A. Analogous estimating uses expert judgment and historical information to develop cost estimates. However, to be accurate, comparative projects must be similar in fact, not just in appearance
Which of the following is the primary output to the Determine Budget process?
a. Risk register
b. Reserve analysis
c. Project funding contingencies
d. Cost baseline
D. The best answer choice is D because it is the primary output to the Determine Budget process. The other outputs including Project funding requirements, and updates to cost estimates, the project schedule, and the risk register.
An amount of the project budget or project schedule held outside of the performance measurement baseline (PMB) for management control purposes and reserved for unforeseen work that is within the scope of the project is called:
a. Management reserve
b. Contingency reserve
c. Risk reserve
d. Warranty reserve
A. Management reserve is used for project changes to scope and cost. It covers work that is in scope but unplanned.
navigate. You’ve just completed estimating the costs for your project. Prior to execution, you need to establish a time-phased project budget, excluding any management reserves, that can only be changed through formal change control procedures. It will then be used as a basis for comparison to actual results. This is formally called:
a. The project baseline
b. The cost baseline
c. The project management plan
d. The performance measurement baseline
B. The cost baseline is the authorized budget for the project, allocated over a timeline.
Which of the following choices are considered components of the schedule performance index?
a. Leads and lags
b. Critical Path Method
c. Earned Value and Planned value
d. Earned Value and Actual Cost
The best answer choice is C. Schedule performance index is the ratio of Earned Value to Planned value. The formula is SPI = EV / PV.
navigate. Project costs are determined to a great degree by the effectiveness of the execution of the project work. Actual progress can be compared to planned progress by utilizing work performance information to generate activity metrics for evaluation. This type of performance reporting comparison is used in which of the following?
a. COQ
b. EVM
c. WBS
d. BAC
The best answer choice is B because EVM (Earned Value Management) is used to evaluate project progress.
navigate. Which of the following is a measure of the cost efficiency of budgeted resources expressed as the ratio of Earned Value to Actual Cost?
a. CV
b. SV
c. CPI
d. SPI
The best answer choice is C. CPI (Cost Performance Index) compares Earned Value to Actual Cost to determine the cost efficiency of the project.
navigate. You need to determine how well your project is progressing from a cost standpoint. You have determined that your actual cost at this point in time is $150,000 and your Earned Value is $135,000. Which of the following represents your Cost Performance Index?
a. 0.9
b. 1.1
c. $15,000
d. $135,000
The best answer choice is A. Using the formula CPI = EV / AC, the resulting Cost Performance Index is 0.9, indicating that the project is over budget at this point in time.
If your SPI is greater than 1.0, which of the following is true?
a. The project is behind schedule.
b. The project is ahead of schedule.
c. Your project is on schedule.
d. Your earned value is zero
The best answer choice is B. An SPI greater than 1.0 indicates the project is ahead of schedule.