Schedule Flashcards
(60 cards)
You’ve been assigned a project that is in the early stages of estimating. At this point, you only have a high-level understanding of the requirements and the WBS is decomposed only to level two. You have previously done this type of project before and the project sponsor is asking for an initial timeline along with milestone dates and minimal detail. Which of the following techniques should provide you the duration estimate?
a. Analogous estimating
b. Parametric estimating
c. Three-point risk analysis
d. Monte Carlo simulation
A. Analogous estimating is used for projects during the early phases when there aren’t a lot of details.
Which of the following techniques is a form of progressive elaboration, in which the work accomplished in the near term is planned in detail, whereas work further in the future is planned at a higher level?
a. Progressive detailing
b. Rolling wave planning
c. Schedule development
d. Parsing the data
B. Work can exist at various levels of detail depending on where it is in the project life cycle. During early strategic planning when information is less defined, work packages may be decomposed to the known level of detail. As more is known about the upcoming events in the near term, work packages can be further decomposed into activities.
A milestone list identifies all project milestones and indicates whether the milestone is mandatory, such as those required by contract, or optional, such as those based on historical information. Which of the following best describes a milestone?
a. A summary of the project schedule
b. A list of project constraints
c. Documented assumptions
d. A significant point or event in a project, program, or portfolio
D. By definition, a milestone is a significant point or event in a project, program, or portfolio.
navigate. Based on some schedule revisions you made, Joe is now working 65 hours during Week 1, 12 hours during Week 2, and 30 hours during Week 3. What technique should you use to allocate Joe’s time better?
a. Crashing
b. Fast-tracking
c. What-if scenario analysis
d. Resource optimization
D. Use resource optimization to even out Joe’s schedule.
There is an issue with your project schedule. As the project manager, you need to determine whether you need to initiate a change request, take corrective action, or implement a preventive action. From the following options, select the answer that led you to believe there was an issue with the schedule.
a. Activity resources
b. Earned Value
c. Planned value
d. Schedule data
The best answer choice is D because it is the only option that is an input to the Control Schedule process
A technique used to estimate costs or durations by applying an average or weighted average of optimistic, most likely, and pessimistic values when there is a high degree of uncertainty with the individual activity estimates is called:
a. Analogous estimating
b. Three-point estimating
c. Parametric estimating
d. Statistical estimating
B. When a lot of uncertainty, risk, or unknowns surround an activity or a work package, you can use three-point estimating to give you a range and an expected duration.
navigate. What are the four inputs to plan schedule management?
a. Project management plan, project charter, EEFs, organizational process assets
b. Project charter, WBS, SOW, EEFs
c. SOW, product scope, requirements documents, acceptance criteria
d. Project management plan, project charter, project assumptions, project constraints
A. The four inputs are the project management plan, the project charter, the enterprise environmental factors (EEFs), and the organizational process assets
On your construction project, you’ve scheduled the “frame house” activity to immediately follow the “pour foundation” task. By definition, this is an example of what type of scheduling relationship?
a. Finish-to-start
b. Start-to-start
c. Finish-to-finish
d. Cannot be determined at this point
A. The start of the framing is dependent upon completion of the pour foundation task.
navigate. Brenda is working on a network diagram for her project schedule on a project management textbook her company is publishing. Her writers are working on the text and she wants to get the available drafts to her editors as soon as possible. She has determined that it is not necessary for the writers to complete the entire draft before the editors begin. How should Brenda show this relationship on her network diagram?
a. FS
b. SS
c. FS + 1
d. SF
B. The best answer choice is B. Although Brenda can supply her editors with the partial manuscript and have them begin editing before the manuscript is complete, this should be shown as a Start-to-Start relationship because the editors cannot begin their work before the writers have started their work. If Brenda wished to wait until the manuscript was complete before giving it to her editors, this would be shown as a Finish-to-Start relationship
navigate. Your project sponsor has asked you what the impact on the schedule would be if one of the resources on your team was pulled off and put on another project. What technique should you use to determine the impact?
a. Variance analysis
b. What-if scenario analysis
c. Fast-tracking
d. Resource leveling
B. A what-if scenario analysis will show how the schedule will be affected by losing the resources
Plan Schedule Management is the process of establishing the policies, procedures, and documentation for the planning, development, management, execution, and controlling of the project schedule. The key inputs to this process include each of the following EXCEPT:
a. The project charter
b. The scope management plan
c. The development approach
d. The schedule management plan
D. The schedule management plan is an output to the process, not an input.
An analytical technique used to determine the essential features and relationships of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project is called:
a. Reserve analysis
b. Contingency planning
c. Cost/benefit analysis
d. Scope padding
A. Reserve analysis is an analytical technique to determine the essential features and relationships of components in the project management plan to establish a reserve for the schedule duration, budget, estimated cost, or funds for a project.
navigate. Which of the following allows the project team to place buffers on any project schedule path to allow for limited resources?
a. Critical Path Method
b. Critical Chain Method
c. Fast-tracking
d. Resource leveling
The best answer choice is B. The critical chain method uses buffers to allow for project uncertainties.
navigate. The technique of compressing a project schedule resulting in an incremental cost increase defines which of the following techniques?
a. Fast tracking
b. Crashing
c. Resource leveling
d. All of the above
The best answer choice is B because crashing can provide schedule compression but typically results in increased project costs.
The PMO at your organization requires project managers to use the Critical Path Method to create their project schedules. Which of the following best describes this requirement?
a. Enterprise environmental factor
b. Organizational process asset
c. Project scheduling methodology
d. Projectized organizational structure
The best answer choice is C because the Critical Path Method represents a project scheduling methodology.
I can’t start the installation of the roof shingles until after the roof frame is complete.” This is an example of which type of dependency?
a. Discretionary
b. Mandatory
c. Finish-to-finish
d. Start-to-start
B. A mandatory dependency is a relationship that is contractually required or inherent in the nature of the work
Which of the following are outputs of the Control Schedule process?
a. Schedule forecasts
b. Work performance data
c. Project calendars
d. Schedule data
The best answer choice is A because all of the other choices are inputs to the Control Schedule process.
Which of the following choices best defines the sequence of activities that represents the longest path through a project and determines the shortest possible duration?
a. Earned Value calculation
b. Critical chain
c. Critical path
d. WBS
The best answer choice is C because critical path is the term described in the question.
Xavier is concerned with the project schedule and needs to perform some analysis. Which of the following tools and techniques should he consider for his analysis?
a. CPI and CV
b. SV and SPI
c. EV and PV
d. AC and BAC
The best answer choice is B. Tools used in the variance analysis activity for the Control Schedule process include Schedule Variance (SV) and Schedule Performance Index (SPI).
Variance analysis is conducted periodically throughout the project. In addition to identifying variances, a variance analysis should also address which of the following?
a. The cost of taking corrective action
b. The root cause of the variance
c. How best to communicate the variance to a client
d. Who should be held responsible for the variance
B. Variance analysis shouldn’t just identify variances; it should also address the root cause of the variance and whether corrective or preventive actions are desired or even possible.
Activities are the actions needed to create the deliverables. Activity attributes can include which of the following?
a. Constraints and assumptions
b. Milestones
c. Certification requirements
d. Cost estimates
A. Multiple activity attributes can be associated with each scheduled activity that may be included within the activity list. Activity attributes include activity identifier or code (usually an extension from the WBS numbering scheme); activity description; predecessor and successor activities; logical relationships; leads and lags; imposed dates; constraints; assumptions; required resources and skill levels; geographic location of performance; and the type of effort.
You are developing duration estimates for your schedule. What input would you use to identify the working days and shifts upon which each specific resource is available?
a. The project management plan
b. A precedence diagram
c. A network diagram
d. A resource calendar
D. A resource calendar can be quite complex. Information you might compile for a resource calendar includes the skill levels of human resources, the geographic location of work, resource availability, the corporate calendar, and constraints on the number of hours per day a resource can be used
If you need to reduce schedule duration and you want to overlap activities, you would:
a. Crash and schedule
b. Add more resources
c. Fast-track
d. Work overtime
C. Fast-tracking is doing activities in parallel that would normally be done sequentially.
Tom is working in a weak matrix organization and is managing a new project. He is experiencing some issues with resource availability coinciding with his resource requirements at specific times in the project execution. After considering his options, and realizing he does not have any additional budget to use for acquiring more human resources, Tom has decided to optimize the resources he has. Which of the following methods would be most appropriate based on this scenario?
a. Crashing
b. Update schedule baseline
c. Resource leveling
d. Update project budget
The best answer choice is C. Because resource availability is typically low in a weak matrix organization, resource leveling is Tom’s best option because critical resources are only available at certain times.