An intentional activity that realigns the performance of the project work with the project management plan is called:
a. Defect repair
b. Preventive action
c. Corrective action
d. A change order
C. By definition, anything done to bring expected future project performance back in line with the baseline plan is called corrective action.
Which of these processes is not part of Project Integration Management?
a. Develop project management plan
b. Monitor and control project work
c. Control resources
d. Close project or phase
C. Control resources is not a process in project integration management
A predetermined value of a measurable project variable that represents a limit that requires action to be taken if it is reached is called:
a. Threshold
b. Tolerance
c. Not to exceed
d. Performance measurement
A. By definition, a threshold is a value of a measurable project variable that represents a limit that requires action to be taken if it is reached.
Coordinating, unifying, and consolidating are associated with which of the nine knowledge areas?
a. Scope management
b. Risk management
c. Integration management
d. Communications management
The best answer choice is C because integration management comprises coordinating, unifying, and consolidating activities of the project.
The project that Walter has been managing is coming to an end. He is in the closing activities. Prior to finalizing the Close Project process, he needs to verify that the project has achieved the project scope. To which of the following documents must he refer in order to determine this?
a. Work Breakdown Structure
b. Earned Value measurement
c. Stakeholder register
d. Project management plan
The best answer choice is option D because the project management plan contains the Scope Management plan and the scope baseline
All of the following choices are inputs to the Develop Project Management Plan process except:
a. Project charter
b. Enterprise environmental factors
c. Project scope statement
d. Outputs from other processes
The best answer choice is C because the project scope statement is not an input to the Develop Project Management Plan process.
An intentional activity that ensures the future performance of the project work is aligned with the project management plan is known as
a. Defect repair
b. Preventive action
c. Corrective action
d. A change order
B. Preventive action is an intentional activity that ensures the future performance of the project work is aligned with the project management plan.
The document that enables the project manager to move forward with the project by enabling them to apply organizational resources is called:
a. The Statement of Work (SOW)
b. The business case
c. The communications plan
d. The project charter
D. By definition, the charter is a document that has been issued by the project initiator or sponsor that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities
Your product, as currently configured, will not be accepted unless some minor changes are made. Your project team has delivered the results of those changes and verified that the product will now be acceptable to the stakeholders. This is an example of which process group?
a. Monitoring and Controlling
b. Planning
c. Initiating
d. Executing
A. The best answer choice is A because this question concerns monitoring and controlling the result of the executing process and initiating changes when necessary to meet the product requirements.
Clyde is working for an audio systems manufacturer as the project manager of a new project to develop a high-quality audio monitoring system. Since the product of this project may be used by government surveillance agencies, the quality is critical. Clyde is in the process of using quality standards from the organization’s quality policy to develop the project charter. Which of the following best describes what Clyde is doing?
a. Using organizational process assets to develop the project charter
b. Using the Statement of Work to develop the project management plan
c. Using enterprise environmental factors to develop the charter
d. Using industry standards to develop the charter
The best answer choice is A. Clyde is using the existing organizational process assets to develop a new charter for the project
Accurate and timely information is critical in a project environment. Which of the following process groups helps to assure that all information is accurate and timely?
a. Planning
b. Closing
c. Monitoring and Controlling
d. Initiating
The best answer choice is C. The processes in the Monitoring and Controlling process group help to monitor all project information to assure that it is accurate and timely.
navigate. You are managing a project tasked with manufacturing a new consumer grade commuter airplane that has just been approved by the FAA. Production of the airframe is scheduled to begin the following week, but your lead assembly supervisor has just informed you that some specific fastening components for the fuselage are not going to be delivered on time. You decide to change the schedule and direct your team to work on the subassemblies for the navigation system. This is an example of which of the following?
a. Fast tracking
b. Crashing the schedule
c. Corrective action
d. Preventive action
The best answer choice is D because the project manager is taking preventive action to address the change in schedule tasks and in order to keep the project on schedule.
Which of the following should be included in the project charter?
a. All supporting documentation
b. Risk register
c. The specific business need the project is designed to address
d. Stakeholder register
The best answer choice is C because the project charter is the document that initiates the project and describes the specific business need that the project is designed to address.
navigate. Stephanie is a YouTube v-logger. Her husband, Dave, works for photographic equipment manufacturer. Because of the advent of new technology and a unique wireless geo-location system, Dave has just developed a new video camera that has an input for a secondary camera lens, which allows Stephanie to videotape herself from two different points of view at the same time. Her YouTube subscribers, some of which are also v-loggers, have seen Stephanie’s review of the product on her YouTube channel and have started calling Stephanie and asking where they can buy one of these new cameras. Dave’s company decides to meet with some of the v-loggers to under stand their wants and needs for a new product line around the two-lens concept. Dave documents the initial assumptions and reviews previous lessons learned from a similar new product line before pitching the idea to the Project Selection Committee. This example illustrates the concept of
a. Market advance
b. Project feasibility assessment
c. Business need
d. Technology advance
The best answer choice is B because the scenario illustrates meeting with stakeholders and evaluating assumptions and lessons learned to evaluate the feasibility of a new project.
navigate. Darla’s project is coming to the end of a specific phase. She has scheduled a phase-end meeting with her team in order to get the required sign-offs on specific deliverables. This particular phase end is a natural time to evaluate the team’s performance in the phase that is ending. Darla is sending a communication to her team members regarding this meeting. Which of the following is the correct nomenclature for a meeting of this type?
a. Phase exit
b. Monitoring gate
c. Kill gate
d. Milestone review
The best answer choice is A. Typical terms include phase gate, kill point, and stage gate.
A written document that records the status and resolution of current situations that could have an impact on project objectives is a(n)
a. Communications plan
b. Issue log
c. Issue record
d. Work performance report
B. An issue is a current condition or situation that may have an impact on the project objectives. An issue log is used to document and monitor the resolution of issues.
From the following documents, select the one that formally authorizes the project.
a. Business case
b. Statement of Work
c. WBS
d. Project charter
The best answer choice is D because the project charter is the document that formally authorizes and initiates the project.
Which of the following is not a subsidiary plan that is typically included in the project management plan?
a. Cost management plan
b. Scope Management plan
c. Performance improvement plan
d. Communications Management plan
The best answer choice is C because any performance improvement plan is not a subsidiary plan and is not included as part of the project management plan
The overall focus of integrated change control is to
a. Maintain the integrity of performance baselines
b. Manage approved changes
c. Coordinate changes across the knowledge areas
d. All of the answer choices are correct
D. The overall focus of integrated change control is to
review all change requests
manage changes to deliverables, project documents, and the project management plan
communicate decisions
consider changes in an integrated manner
Variances that are within the ______ are considered acceptable.
a. Baseline
b. Threshold
c. Boundaries
d. 10% range
B. Variances within the threshold are acceptable.
At the end of a project when project documentation is being archived, which stakeholder is typically still working on the project?
a. The project team members
b. The project manager
c. The client and/or the client’s legal team
d. All stakeholders on the project
B. Archiving documentation is usually the last function prior to formally closing the project. The project manager is often the only remaining stakeholder actively working on the project.
One of your project team members has indicated that she will need an additional four days to complete an activity assigned to her. She assures you that this delay will have zero impact on the project cost. As an experienced project manager what should you do?
a. Approve the request.
b. Ask your team to look for any impact in other areas.
c. Assign more resources to the activity.
d. Deny the request
The best answer choice is B. Although your team has indicated the anticipated delay will have zero impact on the project cost, you need to determine whether the delay will have any impact on other areas such as schedule, quality, and scope. In this case, an impact analysis should be done by your project team.
Reducing the project budget by 10% is considered what?
a. A product change
b. A quality change
c. A project change
d. A necessary requirement
C. Reducing the project budget is considered a project change. Because of balancing competing demands, it’s necessary to consider the impact a budget reduction will have on the scope, schedule, and quality constraints on a project.
One of your team members at the software development company you work for has created a new coding process that results in decreasing development time by an average of 30%. You record this development in order to
a. Help the team member receive recognition
b. Make this information available for future projects
c. Motivate the other team members to be more creative
d. Document it as an exception to standard procedure
The best answer choice is B because this scenario specifically involves documenting lessons learned that may be valuable for future projects.