Data Sheets - Miscellaneous Other Flashcards Preview

API 510 > Data Sheets - Miscellaneous Other > Flashcards

Flashcards in Data Sheets - Miscellaneous Other Deck (75)
Loading flashcards...
1

Define - Repair (key words) (510: 3.53)

Restore - Suitable

2

Define - Alteration (key words) (510: 3.2)

Physical Change

3

Define - RBI's two Primaty Factors (510: 5.2)

Probability Consequence)

4

Define - Location on vessel of Vessel MAWP (VIII: UG-98.a & 510: 3.37)

Top

5

Define - Imperfection that exceeds the acceptance criteria (510: 3.15)

Defect

6

Define - A flaw that may or may not exceed the acceptance criteria (510: 3.25)

Imperfection

7

Design - Joint Category of a vessel longitudinal weld (VIII: Fig UW-3)

A

8

Design - Joint Category of a vessel circumferential weld (VIII: Fig UW-3)

B

9

Design - RT Factors representing Full RT (VIII: UG-116.e.1 & 2)

RT-1, RT-2

10

Design - RT Factors representing Spot RT (VIII: UG-116.e.3)

RT-3

11

Design - Weld Type - Butt Double Welded (VIII: Fig. UW-12)

Type 1

12

Design - Weld Type - Butt Single Welded With Backing (VIII: Fig UW-12)

Type 2

13

Design - Weld Type - Butt Single Welded Without Backing (VIII: Fig UW-12)

Type 3

14

Design - Vessel service that always requires Full RT (VIII: UW-11.a.1)

Lethal

15

Design - Maximum set pressure for single relief device on a vessel (VIII: UG-134.a)

MAWP

16

Design - Marking on nameplate indicating vessel was PWHT (VIII: Fig UG-118)

HT

17

Design - Marking on nameplate indicating vessel is in Lethal Service (VIII: UG-116.c)

L

18

Design - ASME Sect VIII stamp for routine vessels (VIII: UG-116.a.1.a)

U

19

Design - ASME Sect VIII stamp for miniature vessels (VIII: UG-116.a.1.b)

UM

20

Design - ASME Sect VIII stamp for relief devices (VIII: Fig UG-129.1)

UV

21

NDE - Number of CMLs to obtain thickness readings during inspection (key word) (510: 5.6.2.1)

Representative

22

NDE - Number of Nozzles to obtain thickness readings during inspection (key word) (510: 5.6.2.1)

Representative

23

NDE - Lead letter used during RT to check for backscatter radiation (V: T-223)

B

24

NDE - Lead letter used during RT to indicate a film-side IQI (V: T-277.1.b)

F

25

NDE - Hole size that must be visible in RT when using a hole-type IQI (V: T-283.1)

2T

26

NDE - Two primary gamma-ray RT sources (577: 9.8.4)

Ir 192, Co 60

27

Relief Valves - How relief devices should be transported (576: 5.8.4.2)

Upright

28

Relief Valves - How relief device intervals are determined (key word) (510: 6.6.2.1)

Performance

29

Welding - Variables needed on WPS (IX: QW-200.1.b)

Essential & Non-Essential

30

Welding - Varuables needed on PQR (IX: QW-200.2.b)

Essential